Professional Documents
Culture Documents
INSTALLATION DESIGN
FEASIBILITY STUDY
ETSU W/62/00568/REP
Contractor
Harland and Wolff Licences Ltd.
4.0 CONCLUSION 8
5.0 REFERENCES 9
EXECUTIVE SUMMARY
The initial objective of the project was to complete a feasibility study to determine the
viability of using a multi-piled foundation for supporting wind turbines offshore. The
feasibility study assessed the multi-piled foundation in two different environmental
scenarios. The data used for each scenario was attained from two sites currently under
consideration for development.
A study of current foundations was undertaken in order to establish the criteria the multi-
piled foundation must fulfil to be competitive in the market. Using preliminary weight
estimations a cost for the structure was calculated and compared with structures already in
the market in order to ascertain competitiveness. The manufacturing and structural
constraints of the concept were also compared with other concepts already in the market.
It is considered that the multi-piled foundation is currently more construction friendly
than gravity foundations and in the future should be more construction friendly than large
diameter/wall thickness monopiles.
The feasibility study concentrated mainly on the initial geometry of the multi-piled
foundation i.e. the number of legs and the pitch diameter of the piles. The loading on each
pile was calculated and evaluated. The tensile loads on the piles were deemed to be the
critical loads. Methods for reducing these loads were then assessed. The use of a heavy
material to ballast the structure was evaluated, this was thought not to be an economically
feasible method for reducing the tensile loads. The use of ground anchors was also
evaluated, the report concluded that they may be viable, but further design work should be
undertaken.
The report concluded that the multi-piled foundation was a competitive option for
anchoring of wind farms offshore. Also it was highlighted that there are still a number of
areas of the design that require further more detailed work.
1.0 STUDY OF CURRENT FOUNDATION CONCEPTS AND INSTALLATION
METHODS
Installation
• Driven 20-30m into seabed or,
• Grouted into position in pre-drilled holes.
Design
• Design and Manufacture generally simple.
• Unbraced nature has poor dynamic characteristics.
• Large diameter leads to fatigue problems.
Installation
• 3 Driven Piles.
• Leg consists of pile, pile sleeve and a number of braces.
Design
• Design & Manufacture expensive.
• Reduced loads due to low surface area.
• Corrosion allowance is reduced since diameter is reduced.
-1-
Installation
• Seabed must be prepared.
• No welding or grouting required offshore.
• Requires specialist heavy lifting equipment.
Design
• Design relatively straightforward.
• Manufacture requires large facilities situated close to a major waterway.
• Considerable amount of attention must be given to designing for scouring.
The condition of the seabed will make a considerable difference on the total cost. Some
seabed locations will need more preparation before installation than others. Added depth
will also attract higher installation costs. At lower water depths currently the most cost
competitive foundations are monopiles and gravity structures. The seabed, current
conditions and site location will normally decide which is used. The H&W foundation
concept is thought to be comparable in terms of total installed cost with both concepts. At
higher water depths the costs tend to favour lattice type structures. It is thought that the
-2-
H&W design should be comparable in price at to the lattice structure at higher water
depths.
For water depths less than 10 metres the costs could be between £200k and £500k and for
water depths between 10 metres and 20 metres, the cost could rise to between £400k and
£700k. For water depths greater than 20 metres, the concrete foundations needed would be
extremely heavy; therefore high-manufacturing and installation costs would be associated,
make the use of steel more economical for greater depths.
-3-
1.3.4 H&W Foundation Design
The foundation could be floated in water depths of 3m or above. However, there may be a
danger of craft colliding with the legs in shallower waters. The foundation design could be
employed in water up to 25m with little increase in the difficulty of the installation. Scour
will have a minimal effect on the foundation design as the load is supported on the piles
and not the seabed. The installation methodology is such that easily attainable equipment
can be used hence keeping costs down.
Structural integrity throughout the lifetime of the offshore WTG (Wind Turbine
Generator) foundation depends on the thoroughness of initial design investigations, on the
quality of the materials and manufacture, and on the in-service inspection and
maintenance.
The construction site required for the manufacture of the concrete structures ideally must
be adjacent to a quayside facility capable of loading the completed segments/structures
onto a barge for onward transportation to site. As the weight of a completed foundation
(subject to water depth) could be anything up to 2000 tonnes, the employment of a heavy
lift crane is a requirement - this can attract substantial costs. It is possible to make use of
buoyancy to reduce the weight having to be lifted by the crane, this was seen at
Middelgrunden. The site must then be accommodated with all the machinery and
materials required for this type of production. The machinery would also involve the
erection of a heavy lift crane suitable for lifting the heavy concrete blocks. After the
concrete is poured, it must be cured with fresh water. The curing process will be very
dependent on the weather conditions. In cold weather and during frost, the concrete
should have a certain minimum temperature at the time of placing and be protected for a
given period against heat loss and drying.
-4-
2.0 BASE INSTALLATION
After discussions with possible manufacturers, it was found that the size of the pontoon
that would be required to encircle the base shaft would be above the present
manufacturing capability. Smaller pontoons that could encircle the piles were pursued.
The pontoons would be installed on the first base to be deployed. After installation, the
floats would be unlatched and lifted onto the next base.
-5-
3.0 MULTI-PILED FOUNDATION FEASIBILITY STUDY
The aim of the foundation study was to prove that the multi-piled foundation was a
feasible option for certain seabed conditions. No single type of foundation will be
economically viable for all seabed conditions. Gravity foundations tend to be used where
the seabed is rocky and where it is difficult to pile. Piled foundations tend to be used
where the seabed is unable to support the weight of a gravity structure or where seabed
movement is high due to strong currents.
The multi-piled foundation feasibility study used the data from two sites, one in UK and
one in Ireland, to prove the concept. The conditions at each site were different therefore
giving a good basis for comparative study. The study considered various geometry’s for
the foundation, varying both the number of piles and size of the base and identifies the
most practicable combinations to suit expected ground conditions.
¾ Pile sizes to be used will be smaller/more readily available and cheaper to install than
equivalent monopile type foundations
¾ The structure can be manufactured using processes common to the marine industry.
¾ The geometry of the structure is flexible and can be adapted relatively simply for
different site conditions.
¾ A piled foundation will make the base more suitable where there is movement of the
seabed.
¾ The geometry of the foundation provides better scour resistance than a traditional
monopile.
¾ Water depth
¾ Wind, wave, currents and ice
¾ Accidental loading
The initial investigations carried out in the study analysed the tensile and compressive
loads in the piles. A number of simple computer models with varying number and lengths
of legs were analysed for site specific conditions to determine likely pile loads. As
expected pile loads decrease with an increase in length of leg and number of piles.
Calculations were then carried out to determine the compressive and tensile capacities of
various lengths and diameters of pile. The conclusion drawn from this analysis was that
the multi-piled foundation would be practical for certain geometries.
-6-
The study also assessed the viability of using ballast or ground anchors in order to not
exceed the practical/economic pile depths/sizes. The report concluded that initial
indications would suggest that the volume of ballast required would be uneconomic. The
report concluded that the use of ground anchors should be given further consideration. A
ground anchor 10m beyond the base of each pile would produce a tensile safe working
load of between 1500-3000kN.
The report concluded that any further study should evaluate the use of ground anchors.
An initial finite element analysis was carried out to prove the feasibility of the structural
concept and to identify areas for a further more detailed FE analysis. A dynamic FE model
will ultimately be required to fully address the issues of fatigue loading, dynamic response
and stress concentrations. The results show that the force concentrations will occur at the
pile/leg and tower/leg interfaces. Further detailed design work should evaluate how to
best transfer the loads at the interface points and hence minimize the amount of stiffening
required.
The study concluded by identifying a number of areas that should be considered for
further more detailed design. These include: -
- 7-
4.0 CONCLUSION
The main aim of the feasibility study was to assess the practicability of the multi-piled
foundation. Two different sites were selected and the feasibility of using the multi-piled
foundation on each was undertaken. An initial financial analysis has shown that the
concept should be economically viable in the market place. However more detailed design
work is required to calculate more accurately the final weight of the structure and the
manufacture/installation costs. Any further design work should be based on a specific site,
using data relative to that site for calculations. From the feasibility study the following
conclusions can be drawn: -
1. The multi-piled foundation concept appears to be feasible for supporting wind turbines
offshore.
2. The concept as presented is designed to utilize common lifting and piling equipment.
3. The structure size may be reduced with the utilization of ground anchors.
- 8-
3.0 REFERENCES
- 9-