You are on page 1of 74

7.1 Breaker Failure 7.

1 Breaker Failure
Breaker Failure Protection Breaker Failure Protection

Ref : APP14 Ref : APP14

Issue B2 Issue B2
Last Release : June 2012 Last Release : June 2012

Program
g Program
g

Objective Objective
Operation Principle Operation Principle
Reset Conditions Reset Conditions
50 BF Protection integrated to BusBar protections 50 BF Protection integrated to BusBar protections
Setting guide - Example Setting guide - Example

Schneider Electric - Infrastructure Business 2 Schneider Electric - Infrastructure Business 2


Obj ti
Objective Obj ti
Objective
Operation
p Principle
p Operation
p Principle
p
Reset Conditions Reset Conditions
50 BF P
Protection
t ti integrated
i t t d to
t BusBar
B B protections
t ti 50 BF P
Protection
t ti integrated
i t t d to
t BusBar
B B protections
t ti
Setting guide - Example Setting guide - Example

Schneider Electric - Infrastructure Business 3 Schneider Electric - Infrastructure Business 3

Breaker Failure Breaker Failure


Objective of the Breaker Failure Protection Objective of the Breaker Failure Protection

● Reduction of the Total Fault Clearance time in case of a Circuit Breaker ● Reduction of the Total Fault Clearance time in case of a Circuit Breaker
Failure Failure

● Re-Trip order (second circuit) to the Circuit Breaker Coil (same or second) ● Re-Trip order (second circuit) to the Circuit Breaker Coil (same or second)

● Current Supervision through the Circuit Breaker ● Current Supervision through the Circuit Breaker

● In case of Fault Clearance Failure, issue of a back trip order to all adjacent ● In case of Fault Clearance Failure, issue of a back trip order to all adjacent
Circuit Breakers Circuit Breakers

● Operation must occur before second stage tripping time of remote distance ● Operation must occur before second stage tripping time of remote distance
protections protections

● Supervision of Circuit Breaker Status contacts is possible as option ● Supervision of Circuit Breaker Status contacts is possible as option
Schneider Electric - Infrastructure Business 4 Schneider Electric - Infrastructure Business 4
Breaker Failure Protection Breaker Failure Protection
● For Reliable Power System operation the protective scheme ● For Reliable Power System operation the protective scheme
must be dependable must be dependable

● Speed ● Speed
● Maintain System Stability ● Maintain System Stability
● Discrimination ● Discrimination
● Minimise the Plant Isolated ● Minimise the Plant Isolated
● Reliability
R li bilit ● Reliability
R li bilit
● Operates infrequently ● Operates infrequently

Schneider Electric - Infrastructure Business 5 Schneider Electric - Infrastructure Business 5

Breaker Failure Protection Breaker Failure Protection


● For Reliable Power System operation the protective scheme ● For Reliable Power System operation the protective scheme
must be dependable must be dependable

● Duplicate :- ● Duplicate :-
●Protective Relays ●Protective Relays
●Trip Coils ●Trip Coils
●DC Supplies ●DC Supplies
●Instrument Transformers ●Instrument Transformers

● Not Duplicated :- ● Not Duplicated :-


●Circuit Breakers ●Circuit Breakers
– Operating Mechanisms – Operating Mechanisms
– Hydraulic Systems – Hydraulic Systems
– Pneumatic Systems – Pneumatic Systems

Schneider Electric - Infrastructure Business 6 Schneider Electric - Infrastructure Business 6


Breaker Failure Protection Breaker Failure Protection
● Objective ● Objective

● Clear the faulted Apparatus with ● Clear the faulted Apparatus with
●Minimum Time Delay ●Minimum Time Delay
●Minimum Disruption to the Power System ●Minimum Disruption to the Power System

● Backup Protection Exists in Two Forms ● Backup Protection Exists in Two Forms
●Local Backup ●Local Backup
●Remote Backup ●Remote Backup

Schneider Electric - Infrastructure Business 7 Schneider Electric - Infrastructure Business 7

Remote Backup
p - Distance Remote Backup
p - Distance
Z3 Z3
Z2 Z2
Z1 Z1

21A 21B 21A 21B

● Advantages ● Advantages
● Not affected by adverse conditions at the local station ● Not affected by adverse conditions at the local station
● Backup for both relays and circuit breakers ● Backup for both relays and circuit breakers

● Disadvantages ● Disadvantages
● Time
Ti delayed
d l d tto maintain
i t i di
discrimination
i i ti ● Time
Ti delayed
d l d tto maintain
i t i di
discrimination
i i ti
● Sensitivity is affected by fault infeeds at remote busbars ● Sensitivity is affected by fault infeeds at remote busbars
● Wide spread disruption ● Wide spread disruption

Schneider Electric - Infrastructure Business 8 Schneider Electric - Infrastructure Business 8


Objective Objective

Operation Principle Operation Principle


Reset Conditions Reset Conditions
50 BF Protection integrated to BusBar protections 50 BF Protection integrated to BusBar protections
gg
Setting guide - Example
p gg
Setting guide - Example
p

Schneider Electric - Infrastructure Business 9 Schneider Electric - Infrastructure Business 9

Circuit Breaker Failure Circuit Breaker Failure

Main Main

50BF 50BF

Schneider Electric - Infrastructure Business 10 Schneider Electric - Infrastructure Business 10


Local Backup Local Backup
● Advantages ● Advantages
● Faster than Remote Backup ● Faster than Remote Backup
● Improved Sensitivity ● Improved Sensitivity
● Minimises System Disruption ● Minimises System Disruption

● Disadvantages ● Disadvantages
● May be Affected by Local Conditions ● May be Affected by Local Conditions
● “Accidental
“A id t l O Operation”
ti ” - Unwanted
U t dSSystem
t Disruption
Di ti ● “Accidental
“A id t l O Operation”
ti ” - Unwanted
U t dSSystem
t Disruption
Di ti

● Security ● Security
● No Unwanted Operation ● No Unwanted Operation

● Dependability ● Dependability
● Guaranteed Operation in Case of Fault ● Guaranteed Operation in Case of Fault

Schneider Electric - Infrastructure Business 11 Schneider Electric - Infrastructure Business 11

Local Backup
p Local Backup
p
● Two Main Types ● Two Main Types
● Relay Backup ● Relay Backup
●Provision of Main 1 and Main 2 Protection Relays ●Provision of Main 1 and Main 2 Protection Relays
● Breaker Backup ● Breaker Backup
●HV Breakers are Expensive and are not duplicated ●HV Breakers are Expensive and are not duplicated
●Two Independent Trip Coils but a Common operating Mechanism ●Two Independent Trip Coils but a Common operating Mechanism
●Possible Point of Failure ●Possible Point of Failure

● Breaker Failure Protection ● Breaker Failure Protection


● Backtrip Every Circuit Breaker that Capable of Supplying the ● Backtrip Every Circuit Breaker that Capable of Supplying the
Fault Fault
● Initiated by the Local Protection ● Initiated by the Local Protection
● Also called “Stuck Breaker Protection” or “Back Tripping ● Also called “Stuck Breaker Protection” or “Back Tripping
Protection” Protection”

Schneider Electric - Infrastructure Business 12 Schneider Electric - Infrastructure Business 12


Local Backup
p Local Backup
p

Schneider Electric - Infrastructure Business 13 Schneider Electric - Infrastructure Business 13

Duplicate Main Protection Duplicate Main Protection

Schneider Electric - Infrastructure Business 14 Schneider Electric - Infrastructure Business 14


Independent Trip Supplies Independent Trip Supplies

Schneider Electric - Infrastructure Business 15 Schneider Electric - Infrastructure Business 15

1 Correct operation of 1 Correct operation of


2 the CB 2 the CB
3 3

Normal tripping Normal tripping


time time
Schneider Electric - Infrastructure Business 16 Schneider Electric - Infrastructure Business 16
No Operation of No Operation of
1 CB 1 CB
2 2
3 3
4 4

Normal tripping Normal tripping


ti
time ti
time

Schneider Electric - Infrastructure Business 17 Schneider Electric - Infrastructure Business 17

Tripping by 50CB Tripping by 50CB


1 Interlock Criteria 1 Interlock Criteria
2 2
3 3

Correct Clearance by Correct Clearance by


CB CB

Normal time for Normal time for


breaker to open breaker to open

=> No CB Fail Issue => No CB Fail Issue

Schneider Electric - Infrastructure Business 18 Schneider Electric - Infrastructure Business 18


Tripping by 50CB Tripping by 50CB
1 Interlock Criteria 1 Interlock Criteria
2 2
3 3
4 4
No Clearance No Clearance
By CB By CB

Normal time for Normal time for


breaker to open breaker to open

=> 50BF Trip => 50BF Trip

Schneider Electric - Infrastructure Business 19 Schneider Electric - Infrastructure Business 19

Fault in one feeder without breaker Fault in one feeder without breaker
failure failure
21 21 21 21 21 21 21 21
D1 D2 D3 D4 D1 D2 D3 D4

D5 D6 D7 D5 D6 D7
G 21 21 21
G 21 21 21
1 Fault appearance
1. 1 Fault appearance
1.
2. Activation of MAIN zone 1 2. Activation of MAIN zone 1
(D1 and D2) (D1 and D2)
3 Activation of
3. 21 21 21 21 21 3 Activation of
3. 21 21 21 21 21
downstream BACK-UP downstream BACK-UP
zones 2, 3 and 4 (D4, D8, D8 D9 D10 D11 D12 zones 2, 3 and 4 (D4, D8, D8 D9 D10 D11 D12
D9, D10, D11 and D12) D9, D10, D11 and D12)
4 T
4. Tripping
i i order
d to
t D1 & D2 4 T
4. Tripping
i i order
d to
t D1 & D2
5. D2 = Breaker Failure 5. D2 = Breaker Failure
Fault clearance time too long, with high Fault clearance time too long, with high
6. Tripping order with remote
relays to D4,
D4 D8,
D8 D9
G risks of network instability,
instability caused by G 6. Tripping order with remote
relays to D4,
D4 D8,
D8 D9
G risks of network instability,
instability caused by G
(and D11 ?) (and D12 ?) the loss of most of interconnections. (and D11 ?) (and D12 ?) the loss of most of interconnections.
Schneider Electric - Infrastructure Business 20 Schneider Electric - Infrastructure Business 20
Fault in one feeder with breaker failure Fault in one feeder with breaker failure

21 21 21 21 21 21 21 21
50BF 50BF 50BF 50BF 50BF 50BF 50BF 50BF
D1 D2 D3 D4 D1 D2 D3 D4

D5 D6 D7 D5 D6 D7
G 21 21 21 G 21 21 21
50BF 50BF 50BF 50BF 50BF 50BF

1. Fault appearance 1. Fault appearance


2. Activation of MAIN zone 1 21 21 21 21 21 2. Activation of MAIN zone 1 21 21 21 21 21
((D1 and D2)) ((D1 and D2))
50BF 50BF 50BF 50BF 50BF 50BF 50BF 50BF 50BF 50BF
3. Activation of 3. Activation of
downstream BACK-UP D8 D9 D10 D11 D12 downstream BACK-UP D8 D9 D10 D11 D12
zones 2, 3 and 4 (D4, D8, zones 2, 3 and 4 (D4, D8,
D9,, D10,, D11 and D12)) D9,, D10,, D11 and D12))
4. Tripping order to D1 & D2 4. Tripping order to D1 & D2
5. D2 = Breaker Failure Fast fault clearance : 5. D2 = Breaker Failure Fast fault clearance :
6. Tripping
pp g order with local G without tripping
pp g of the remote relays
y G 6. Tripping
pp g order with local G without tripping
pp g of the remote relays
y G
[50BF] to D3, D5 and D6 without loss of the remote switchgears [50BF] to D3, D5 and D6 without loss of the remote switchgears

Schneider Electric - Infrastructure Business 21 Schneider Electric - Infrastructure Business 21

CB Fail - Sequences CB Fail - Sequences


If lt
Ifault If lt
Ifault

In In
Circuit Circuit
Breaker Breaker
CB interrupting time CB interrupting time
PR reset time PR reset time

In In
Protective Protective
Relay Relay
Tripping time CBF Tripping time CBF
set in the PR (*) reset set in the PR (*) reset
time time

Breaker Breaker
Failure Failure
Device CB Fail timer Device CB Fail timer

Fault Activation Tripping order CB opened Fault Activation Tripping order CB opened
appearance off the
th CBF sendd to
t the
th CB appearance off the
th CBF sendd to
t the
th CB

(*) : includes the activation of the tripping output contact (*) : includes the activation of the tripping output contact
Schneider Electric - Infrastructure Business 22 Schneider Electric - Infrastructure Business 22
Objective Objective
Operation Principle Operation Principle

Reset Conditions Reset Conditions


50 BF Protection integrated to BusBar protections 50 BF Protection integrated to BusBar protections
gg
Setting guide - Example
p gg
Setting guide - Example
p

Schneider Electric - Infrastructure Business 23 Schneider Electric - Infrastructure Business 23

Fault Clearance Detection Method Fault Clearance Detection Method


13 ms 13 ms

At the end of this timer, the At the end of this timer, the
corresponding threshold is not corresponding threshold is not
reached again in the negative reached again in the negative
area => The algorithm detects a area => The algorithm detects a
fault current clearance fault current clearance
13 ms 13 ms

Schneider Electric - Infrastructure Business 24 Schneider Electric - Infrastructure Business 24


Fault Clearance Detection Method Fault Clearance Detection Method

The algorithm detects a The algorithm detects a


permanent fault current permanent fault current
=> 50 BF Trip is issued => 50 BF Trip is issued

13 ms 13 ms

Schneider Electric - Infrastructure Business 25 Schneider Electric - Infrastructure Business 25

Fault Clearance Detection Method Fault Clearance Detection Method


The algorithm detects a fault The algorithm detects a fault
clearance clearance
=> No 50 BF trip => No 50 BF trip

13 ms 13 ms

Schneider Electric - Infrastructure Business 26 Schneider Electric - Infrastructure Business 26


Fault Clearance Detection Method Fault Clearance Detection Method
The algorithm detects a fault The algorithm detects a fault
clearance
l clearance
l
=> No 50 BF Trip issued => No 50 BF Trip issued

13 ms 13 ms

Schneider Electric - Infrastructure Business 27 Schneider Electric - Infrastructure Business 27

Objective Objective
Operation Principle Operation Principle
Reset Conditions Reset Conditions

50 BF PProtection
t ti integrated
i t t d to
t BusBar
B B 50 BF PProtection
t ti integrated
i t t d to
t BusBar
B B
protections protections
Setting guide - Example Setting guide - Example

Schneider Electric - Infrastructure Business 28 Schneider Electric - Infrastructure Business 28


50BF Operation
p 50BF Operation
p

Central Central
Unit Back Trip Unit Back Trip
CB CB
Failure(3) Order (4) Failure(3) Order (4)
– Tbf2 – Tbf2
BB1 BB2 BB1 BB2

Trip Order Trip Order


Other Coil 1 (1) Other Coil 1 (1)
Relay 50BF Relay 50BF
Coil 2 Coil 2
(2) – Tbf1 (2) – Tbf1
Peripheral Peripheral
UD UD Unit UD UD Unit
50BF 50BF 50BF 50BF
PU 50BF PU 50BF

Schneider Electric - Infrastructure Business 29 Schneider Electric - Infrastructure Business 29

CB Fail Element Logic


g CB Fail Element Logic
g
Bus-Coupler and Bus-Section CBs - Internally initiated Bus-Coupler and Bus-Section CBs - Internally initiated

Trip signal Tpabc: Tripping signal from 87BB Trip signal Tpabc: Tripping signal from 87BB
Local Local
from CU & Circuit from CU & Circuit
I>BB Breaker I>BB Breaker
Optional Optional
I< & tBF1 Local Retrip I< & tBF1 Local Retrip

& tBF2 & tBF2


Backtrip Signal to CU Backtrip Signal to CU
for adjacent bus zone for adjacent bus zone
trip trip
 I< Dead pole detection threshold  I< Dead pole detection threshold
 I>BB Overcurrent element for authorisation of local tripping confirmation  I>BB Overcurrent element for authorisation of local tripping confirmation

Schneider Electric - Infrastructure Business 30 Schneider Electric - Infrastructure Business 30


Objective Objective
Operation Principle Operation Principle
Reset Conditions Reset Conditions
50 BF Protection integrated to BusBar protections 50 BF Protection integrated to BusBar protections

Setting
ggguide - Example
p Setting
ggguide - Example
p

Schneider Electric - Infrastructure Business 31 Schneider Electric - Infrastructure Business 31

Setting
g Guide Example
p Setting
g Guide Example
p

CB Trip CB Trip
+ 50BF + 50BF
Initiation Initiation

20ms 20ms
CB max fault CB max fault
Main clearance time Security Main clearance time Security
Protection (50ms *) margin Protection (50ms *) margin
Aux. (50ms **) Aux. (50ms **)
Contact 10ms Contact 10ms
50BF ‘’Retrip’’
‘’R t i ’’ 50BF ‘’Retrip’’
‘’R t i ’’
‘’Re trip’’ timer tBF1 (100ms) Security Margin ‘’Re trip’’ timer tBF1 (100ms) Security Margin
(130ms) (130ms)
Adjacent 50BF Adjacent 50BF
Protection – Protection –
Trip Order 50BF Back Trip Trip Order 50BF Back Trip
timer tBF2 (200ms) timer tBF2 (200ms)

Be Careful : Be Careful :
No auxiliary relays (Master Trip,…) between the Trip Order given by the Main Protection No auxiliary relays (Master Trip,…) between the Trip Order given by the Main Protection
and the 50BF Relay Initiation and the 50BF Relay Initiation
* Example : * Example :
CB Opening Time = 2 cycles + arc clearance CB Opening Time = 2 cycles + arc clearance
time = 10 ms (at 50Hz) time = 10 ms (at 50Hz)
** Example
p : ** Example
p :
The security margin includes the time to receive the CB ‘’open position’’ status ‘’ (if The security margin includes the time to receive the CB ‘’open position’’ status ‘’ (if
used) + the drop off time of the 50BF relay + a pure Security margin. used) + the drop off time of the 50BF relay + a pure Security margin.
Schneider Electric - Infrastructure Business 32 Schneider Electric - Infrastructure Business 32
Setting
g Guide Example
p Setting
g Guide Example
p
The fault is typically cleared The fault is typically cleared
after : after :
(worst case) (worst case)

20ms (Main Protection) 20ms (Main Protection)


CB Trip [+ 10ms (auxiliary contacts)] CB Trip [+ 10ms (auxiliary contacts)]
+ 50BF +100ms (tBF1) + 50BF +100ms (tBF1)
Initiation + 10ms (auxiliary contacts) Initiation + 10ms (auxiliary contacts)
+ 50ms (Circuit Breaker) + 50ms (Circuit Breaker)
= 180ms = 180ms
20
20ms 20
20ms
Main Main
Protection Auxiliary contact Protection Auxiliary contact
(10ms *) CB max fault (10ms *) CB max fault
clearance time clearance time
50BF ‘’Retrip’’ (50ms) Security 50BF ‘’Retrip’’ (50ms) Security
Margin Margin
‘’Re
Re trip
trip’’ Timer tBF1 (100ms) (40ms) ‘’Re
Re trip
trip’’ Timer tBF1 (100ms) (40ms)
Adjacent 50BF Adjacent 50BF
Protection Protection
- Trip Order 50BF Back Trip Timer tBF2 - Trip Order 50BF Back Trip Timer tBF2
(200ms) (200ms)

* Example : * Example :
Security Margin Increased if the Security Margin Increased if the
50BF Protection directly operates 50BF Protection directly operates
the CB coil, and not through any the CB coil, and not through any
master trip contacts (auxiliary master trip contacts (auxiliary
relay) relay)

Schneider Electric - Infrastructure Business 33 Schneider Electric - Infrastructure Business 33

Setting
g Guide Example
p The fault is cleared by the adjacent CB,
typically after : (worst case) Setting
g Guide Example
p The fault is cleared by the adjacent CB,
typically after : (worst case)
20ms (main protection) 20ms (main protection)
[+ 10ms (auxiliary relay used for [+ 10ms (auxiliary relay used for
initiation)] initiation)]
+200ms
200ms (tBF2) +200ms
200ms (tBF2)
+ 30ms (intertrip) + 30ms (intertrip)
+ 20ms (auxiliary relay at remote end) + 20ms (auxiliary relay at remote end)
CB Trip + 50ms (Circuit Breaker) CB Trip + 50ms (Circuit Breaker)
+ 50BF = 330ms + 50BF = 330ms
Initiation Initiation

20
20ms 20
20ms
Main Main
Protection Protection
CB – max fault CB – max fault
clearance time clearance time
50BF ‘’Retrip’’ 30ms 20ms (50ms) 50BF ‘’Retrip’’ 30ms 20ms (50ms)

Re trip
‘’Re trip’’ Timer tBF1 (100ms) Re trip
‘’Re trip’’ Timer tBF1 (100ms)
Inter-trip * Inter-trip *
Adjacent 50BF Adjacent 50BF
Protection – Protection –
Trip Order 50BF Back Trip timer tBF2 (200ms) Trip Order 50BF Back Trip timer tBF2 (200ms)

Note : Note :
St ti time
Starting ti off the
th 50BF protection
t ti nott considered
id d (3 tto 5 ms d depending
di St ti time
Starting ti off the
th 50BF protection
t ti nott considered
id d (3 tto 5 ms d depending
di
on the filtering logic applied to the 50BF protection logical inputs) on the filtering logic applied to the 50BF protection logical inputs)

* Teleprotection typical operating time : * Teleprotection typical operating time :


minimum
i i : 20
20ms minimum
i i : 20
20ms
maximum : 37ms maximum : 37ms
Typical : 30ms Typical : 30ms
Schneider Electric - Infrastructure Business 34 Schneider Electric - Infrastructure Business 34
Typical Settings Typical Settings
● General : ● General :
● 20% In with a minimum fault current of 55% In ● 20% In with a minimum fault current of 55% In

● Resistor Current >10% : ● Resistor Current >10% :


● 80% ● 80%
● or 20% if fault current is < %160 ● or 20% if fault current is < %160

● Generator Circuits ● Generator Circuits


● 5% ● 5%

●Typical in UK 400kV and 275kV Networks ●Typical in UK 400kV and 275kV Networks

Schneider Electric - Infrastructure Business 35 Schneider Electric - Infrastructure Business 35

● For a current setting less than full load ● For a current setting less than full load
● Inhibit the BF relay during normal operating conditions ● Inhibit the BF relay during normal operating conditions
● Using Static Relays control the DC Supply ● Using Static Relays control the DC Supply

Schneider Electric - Infrastructure Business 36 Schneider Electric - Infrastructure Business 36


CB Resistor Current CB Resistor Current

● Resistor is used to reduce switching overvoltages due to ● Resistor is used to reduce switching overvoltages due to
large inductive loads large inductive loads
● Main CB opens first, the resistor reduces the current to a low ● Main CB opens first, the resistor reduces the current to a low
level,. Aux CB is opened 1 - 2 cycles later level,. Aux CB is opened 1 - 2 cycles later
● BF relay should not remain operated by resistor current ● BF relay should not remain operated by resistor current
● Is > 2 x Ir ● Is > 2 x Ir
● The minimum fault level takes priority.
priority Timer Setting can be ● The minimum fault level takes priority.
priority Timer Setting can be
increased to compensate for resistor contact separation increased to compensate for resistor contact separation

Schneider Electric - Infrastructure Business 37 Schneider Electric - Infrastructure Business 37

Operating Speed Operating Speed


● Timer Setting Considerations ● Timer Setting Considerations
● CB Trip
p Time ● CB Trip
p Time
●Main Contacts ●Main Contacts
●Resistor Contact Open ●Resistor Contact Open
● Current Detector ● Current Detector
●Operate Time ●Operate Time
●Reset Time ●Reset Time
● Main Protection ● Main Protection
●Reset Time ●Reset Time
● Timer ● Timer
●Overshoot / Accuracy ●Overshoot / Accuracy
● Discriminating (Safety) Margin ● Discriminating (Safety) Margin
● Maximum Allowable Backup Clearance Time ● Maximum Allowable Backup Clearance Time
● Scheme Arrangement ● Scheme Arrangement

Schneider Electric - Infrastructure Business 38 Schneider Electric - Infrastructure Business 38


Operating Speed Operating Speed
● www.neca.com.au
www neca com au ● www.neca.com.au
www neca com au

● 400kV and above ● 400kV and above


●175ms
175ms ●175ms
175ms

● At least 250kV but less than 400kV ● At least 250kV but less than 400kV
●250ms ●250ms

● more than 100kV but less than 250kV ● more than 100kV but less than 250kV
●430ms ●430ms

● Less than or equal to 100kV ● Less than or equal to 100kV


●As necessary to prevent plant damage and meet stability ●As necessary to prevent plant damage and meet stability
requirements requirements

Schneider Electric - Infrastructure Business 39 Schneider Electric - Infrastructure Business 39

Back Trip on Double Bus Systems Back Trip on Double Bus Systems

Schneider Electric - Infrastructure Business 40 Schneider Electric - Infrastructure Business 40


● Alternative for tripping time Reduction ● Alternative for tripping time Reduction
● 1 - Trip both coils 1 and 2 for major faults (87BB, 87T,…) ● 1 - Trip both coils 1 and 2 for major faults (87BB, 87T,…)
● 2 - No retrip order ● 2 - No retrip order
● 3 - if CB fail is raised, activate directly the back trip at Bus bar side ● 3 - if CB fail is raised, activate directly the back trip at Bus bar side

● Alternative for generator CB during switch off operation ● Alternative for generator CB during switch off operation
● Use of an under-voltage criteria, measured across the CB poles ● Use of an under-voltage criteria, measured across the CB poles

Schneider Electric - Infrastructure Business 41 Schneider Electric - Infrastructure Business 41


7.2 Autoreclose for Transmission 7.2 Autoreclose for Transmission
Auto-reclosing & Synchro-Check Auto-reclosing & Synchro-Check
in Transmission Systems - in Transmission Systems -
N t
Networkk Stability
St bilit Eff
Effectt N t
Networkk Stability
St bilit Eff
Effectt
Ref : APP14 Ref : APP14

Revision
Re ision B Revision
Re ision B
Last Issue: May 2012 Last Issue: May 2012

Summary
y Summary
y

Stability issues and definitions Stability issues and definitions


Stability limits and theory Stability limits and theory
Short circuits and stability Short circuits and stability
Autoreclose and stability Autoreclose and stability
Autoreclose applications Autoreclose applications

Schneider Electric - Energy Automation – Technical Institute 2 Schneider Electric - Energy Automation – Technical Institute 2
Stabilityy Issues and definitions Stability
y Issues and definitions

Schneider Electric - Energy Automation – Technical Institute 3 Schneider Electric - Energy Automation – Technical Institute 3

Problem: stabilityy issues Problem: stabilityy issues

● An electrical energy network is a complex structure system, made of a ● An electrical energy network is a complex structure system, made of a
certain amount of production units, interconnected through transmission certain amount of production units, interconnected through transmission
and distribution grids and distribution grids

● This system is normally in a given equilibrium state: it is said in ● This system is normally in a given equilibrium state: it is said in
synchronous operation synchronous operation

● In particular
particular, fundamental equilibrium between production and ● In particular
particular, fundamental equilibrium between production and
consumption must be ensured in terms of : consumption must be ensured in terms of :

● ACTIVE POWER (linked to the network frequency) ● ACTIVE POWER (linked to the network frequency)

● REACTIVE POWER (linked to the network voltage map) ● REACTIVE POWER (linked to the network voltage map)

Schneider Electric - Energy Automation – Technical Institute 4 Schneider Electric - Energy Automation – Technical Institute 4
Problem: stabilityy issues Problem: stabilityy issues

An electrical network in equilibrium state, i.e. in a given An electrical network in equilibrium state, i.e. in a given
steady state, is permanently subject to disturbances of any steady state, is permanently subject to disturbances of any
kind kind

● occasional or discontinue disturbances: ● occasional or discontinue disturbances:


● electrical faults: short-circuit, isolation fault, … ● electrical faults: short-circuit, isolation fault, …
● operations: line opening, equipment connection, ... ● operations: line opening, equipment connection, ...

● disturbances linked to normal operation: ● disturbances linked to normal operation:


● load
l d variations
i ti ● load
l d variations
i ti
● static converters operation ● static converters operation
● ... ● ...

Schneider Electric - Energy Automation – Technical Institute 5 Schneider Electric - Energy Automation – Technical Institute 5

Problem: stabilityy issues Problem: stabilityy issues

● Network parameters that can be affected (energy quality): ● Network parameters that can be affected (energy quality):

P Power P Power

U Voltage U Voltage

F Frequency F Frequency

HDR Harmonics HDR Harmonics

● Possible consequences : ● Possible consequences :


●Flicker (fast voltage variation) ●Flicker (fast voltage variation)
●Unbalances of 3 3-phase
phase system ●Unbalances of 3 3-phase
phase system
●Energy delivery cuts due to protections actions (loss of synchronism, ●Energy delivery cuts due to protections actions (loss of synchronism,
power swing, fault, …) power swing, fault, …)

Schneider Electric - Energy Automation – Technical Institute 6 Schneider Electric - Energy Automation – Technical Institute 6
Problem: stabilityy issues Problem: stabilityy issues

● The basic questions to be answered by network stability studies are the ● The basic questions to be answered by network stability studies are the
following: following:

●what happens during a disturbance (voltage and frequency drift, ●what happens during a disturbance (voltage and frequency drift,
protections tripping, …)? protections tripping, …)?
●what will be the new operation point after
f the disturbance has ●what will be the new operation point after
f the disturbance has
disappeared? disappeared?

Schneider Electric - Energy Automation – Technical Institute 7 Schneider Electric - Energy Automation – Technical Institute 7

Definitions and terminology


gy Definitions and terminology
gy

●Steady state ●Steady state


It is the network operation mode where all r.m.s. electrical values can be It is the network operation mode where all r.m.s. electrical values can be
considered as constant considered as constant

●Synchronous
Synchronous operation ●Synchronous
Synchronous operation
A synchronous machine connected to other synchronous machines through A synchronous machine connected to other synchronous machines through
electrical network is said in synchronous operation with the rest of the electrical network is said in synchronous operation with the rest of the
network if its electrical speed is equal to the network’s
network s voltage frequency at network if its electrical speed is equal to the network’s
network s voltage frequency at
connection node, or to other machines’ electrical speed connection node, or to other machines’ electrical speed
An electric network is said in synchronous operation if all connected An electric network is said in synchronous operation if all connected
machines are in synchronous operation with the network and between machines are in synchronous operation with the network and between
together together

Schneider Electric - Energy Automation – Technical Institute 8 Schneider Electric - Energy Automation – Technical Institute 8
Definitions and terminology
gy Definitions and terminology
gy

●Power swing ●Power swing


A generator is in power swing situation when mechanical values are A generator is in power swing situation when mechanical values are
s bjected to sustained
subjected s stained oscillations of finite amplit
amplitude
de aro
around
nd a stead
steady state s bjected to sustained
subjected s stained oscillations of finite amplit
amplitude
de aro
around
nd a stead
steady state
point point
The generator’s specific r.m.s. electrical values are then also subjected to The generator’s specific r.m.s. electrical values are then also subjected to
th
these oscillations
ill ti th
these oscillations
ill ti

●Static stability,
stability or small-signal
small signal stability ●Static stability,
stability or small-signal
small signal stability
An electric network is said in static stability conditions if, after a small An electric network is said in static stability conditions if, after a small
disturbance, it reaches a new steady state very close to initial steady state disturbance, it reaches a new steady state very close to initial steady state
A smallll di
disturbance
t b iis a di
disturbance
t b ffor which
hi h lilinearization
i ti off th
the system’s
t ’ A smallll di
disturbance
t b iis a di
disturbance
t b ffor which
hi h lilinearization
i ti off th
the system’s
t ’
equations is still justified equations is still justified

Schneider Electric - Energy Automation – Technical Institute 9 Schneider Electric - Energy Automation – Technical Institute 9

Definitions and terminology


gy Definitions and terminology
gy

●Transient stability ●Transient stability


An electric network is said in transient stability relatively to a large An electric network is said in transient stability relatively to a large
dist rbances cycle
disturbances c cle if it comes across a ne
new ssynchronous
nchrono s operation stead
steady dist rbances cycle
disturbances c cle if it comes across a ne
new ssynchronous
nchrono s operation stead
steady
state after the disturbance cycle state after the disturbance cycle
A large disturbance is a disturbance for which linearization of the system’s A large disturbance is a disturbance for which linearization of the system’s
equations
ti is
i nott justified
j tifi d any more equations
ti is
i nott justified
j tifi d any more

●Conditional stability ●Conditional stability


An electric network is said in conditional stability situation when its stability An electric network is said in conditional stability situation when its stability
is due to predefined and appropriate regulators’ action is due to predefined and appropriate regulators’ action

Schneider Electric - Energy Automation – Technical Institute 10 Schneider Electric - Energy Automation – Technical Institute 10
Different kinds of stabilityy Different kinds of stabilityy
ELECTRICAL NETWORKS’ STABILITY ELECTRICAL NETWORKS’ STABILITY
Ability to keep the system in equilibrium conditions Ability to keep the system in equilibrium conditions
Equilibrium between opposite forces Equilibrium between opposite forces

ANGLE VOLTAGE ANGLE VOLTAGE


synchronism maintaining voltage maintaining synchronism maintaining voltage maintaining
torques equilibrium reactive powers equilibrium torques equilibrium reactive powers equilibrium

Transient Mid and long Large voltage Transient Mid and long Large voltage
stability terms stability disturbances stability terms stability disturbances
Large disturb.
disturb Large disturb.
disturb

Small signal Small signal


stability Small voltage stability Small voltage
Steady state disturbances Steady state disturbances
P/ - relations Steady state P/ - relations Steady state
P/Q - V relations P/Q - V relations
Non-oscillatingg Oscillating instabilities Non-oscillatingg Oscillating instabilities
instabilities Insufficient damping instabilities Insufficient damping
Insufficient synchro. torque Unstable control Insufficient synchro. torque Unstable control
Schneider Electric - Energy Automation – Technical Institute 11 Schneider Electric - Energy Automation – Technical Institute 11

Mid and long


g term stability
y Mid and long
g term stability
y

●Slow phenomenon ●Slow phenomenon

● Mid term stability: ● Mid term stability:


●high amplitude frequency and/or voltage drifts ●high amplitude frequency and/or voltage drifts
●typical study duration of few minutes ●typical study duration of few minutes

● Long term stability : ● Long term stability :


●uniform system frequency ●uniform system frequency
●typical study duration of tens of minutes ●typical study duration of tens of minutes

Schneider Electric - Energy Automation – Technical Institute 12 Schneider Electric - Energy Automation – Technical Institute 12
Transient stabilityy Transient stabilityy

●High amplitude phenomenon ●High amplitude phenomenon

● Machine internal angle transient stability: ● Machine internal angle transient stability:
●large disturbances ●large disturbances
●fast dynamics (first aperiodical oscillations) ●fast dynamics (first aperiodical oscillations)
●typical study duration of few seconds ●typical study duration of few seconds

● Voltage
V lt transient
t i t stability
t bilit : ● Voltage
V lt transient
t i t stability
t bilit :
●large voltage disturbances ●large voltage disturbances
p , loads dynamics,
●events like operations, y , on load tap-changers,
p g , etc. p , loads dynamics,
●events like operations, y , on load tap-changers,
p g , etc.
●protections and control systems coordination ●protections and control systems coordination

Schneider Electric - Energy Automation – Technical Institute 13 Schneider Electric - Energy Automation – Technical Institute 13

Static stability
y Static stabilityy

●Low amplitude phenomenon ●Low amplitude phenomenon

● Concerns small disturbances, for which electric parameters variations ● Concerns small disturbances, for which electric parameters variations
are slow and continuous. Linearization of network’s model equations is are slow and continuous. Linearization of network’s model equations is
then jjustified ((in p
particular,, the time variable does not occur)) then jjustified ((in p
particular,, the time variable does not occur))

●small disturbances (quasi-steady state) ●small disturbances (quasi-steady state)


●system linearization ●system linearization
●stability margins; spinning reserve ●stability margins; spinning reserve
p
●protections and control systems
y coordination p
●protections and control systems
y coordination

Schneider Electric - Energy Automation – Technical Institute 14 Schneider Electric - Energy Automation – Technical Institute 14
Loss of angle
g static stability
y Loss of angle
g static stability
y

●Damping torque ●Damping torque


● Cd : torque coefficient that evolves in relation with speed disturbance ● Cd : torque coefficient that evolves in relation with speed disturbance
 
● Cd negative => aperiodical instability ● Cd negative => aperiodical instability

 

t t
disturbance duration disturbance duration
Schneider Electric - Energy Automation – Technical Institute 15 Schneider Electric - Energy Automation – Technical Institute 15

Loss of angle
g static stability
y Loss of angle
g static stability
y

●Synchronizing torque ●Synchronizing torque


● Cs : torque coefficient that evolves in relation with internal angle ● Cs : torque coefficient that evolves in relation with internal angle
di
disturbance
b  di
disturbance
b 
● Cs negative => oscillating instability ● Cs negative => oscillating instability

 

t t
disturbance duration disturbance duration
Schneider Electric - Energy Automation – Technical Institute 16 Schneider Electric - Energy Automation – Technical Institute 16
Conservation of angle
g static stability
y Conservation of angle
g static stability
y

● Damping and synchronizing torque coefficients are all positive ● Damping and synchronizing torque coefficients are all positive
● Internal angle  is subjected to a damped oscillation and reaches a final ● Internal angle  is subjected to a damped oscillation and reaches a final
value (generally different from initial value) that corresponds to a new value (generally different from initial value) that corresponds to a new
equilibrium equilibrium

 

t t
disturbance duration disturbance duration
Schneider Electric - Energy Automation – Technical Institute 17 Schneider Electric - Energy Automation – Technical Institute 17

Fault Shunt Fault Shunt

ZF = Fault shunt ZF = Fault shunt


= Combined Impedance of -ve ve and zero sequence = Combined Impedance of -ve ve and zero sequence
network impedances for particular fault. network impedances for particular fault.

Ø/E ZF = Z2 + Z0 Ø/E ZF = Z2 + Z0

Ø/Ø ZF = Z2 Ø/Ø ZF = Z2

Ø/Ø/E ZF = Z2 . Z0 Ø/Ø/E ZF = Z2 . Z0
Z2 + Z0 Z2 + Z0
3Ø ZF = 0 (short circuit) 3Ø ZF = 0 (short circuit)
Healthy ZF =  (open circuit) Healthy ZF =  (open circuit)

Schneider Electric - Energy Automation – Technical Institute 18 Schneider Electric - Energy Automation – Technical Institute 18
Stabilityy Limits and Theory
y Stability
y Limits and Theory
y

Schneider Electric - Energy Automation – Technical Institute 19 Schneider Electric - Energy Automation – Technical Institute 19

Mechanical modeling: Mechanical modeling:


active power / frequency coupling active power / frequency coupling

Schneider Electric - Energy Automation – Technical Institute 20 Schneider Electric - Energy Automation – Technical Institute 20
Generator and rotating
g fields Generator and rotating
g fields

INDUCED INDUCED
(stator) (stator)
MAGNETIC MAGNETIC
FIELD FIELD

balanced 3-phase balanced 3-phase


VOLTAGE SYSTEM VOLTAGE SYSTEM
INDUCTOR INDUCTOR
(rotor) e = p.Ω (rotor) e = p.Ω
Schneider Electric - Energy Automation – Technical Institute 21 Schneider Electric - Energy Automation – Technical Institute 21

Driving
g and resistant torques
q Driving
g and resistant torques
q

MECHANICAL ELECTRICAL MECHANICAL ELECTRICAL


TORQUE TORQUE TORQUE TORQUE
(dri ing torque)
(driving torq e) (braking torque) (dri ing torque)
(driving torq e) (braking torque)

delivered by the delivered by the


delivered by the delivered by the
turbine, linked to turbine, linked to
stator, linked to stator, linked to
mechanical power mechanical power
electrical power electrical power
produced
p produced
p
absorbed b by the absorbed b by the
loads (network) loads (network)

Shaft rotation Shaft rotation


speed Ω speed Ω

Schneider Electric - Energy Automation – Technical Institute 22 Schneider Electric - Energy Automation – Technical Institute 22
Rotating
g masses equation
q Rotating
g masses equation
q

● Acceleration or deceleration of the rotating masses is linked to the ● Acceleration or deceleration of the rotating masses is linked to the
difference between electrical torque (braking torque) and mechanical difference between electrical torque (braking torque) and mechanical
masses inertia constant J
torque (driving torque) through the rotating masses’ masses inertia constant J
torque (driving torque) through the rotating masses’
(kg.m²) (kg.m²)

J · ∂Ω/∂t = m(t) - e(t) J · ∂Ω/∂t = m(t) - e(t)

● Solving this differential equation permits to determine the generator’s


generator s ● Solving this differential equation permits to determine the generator’s
generator s
behavior when a disturbance occurs, that is to answer to the behavior when a disturbance occurs, that is to answer to the
fundamental question: fundamental question:

Will the internal angle  stabilize into a normal and Will the internal angle  stabilize into a normal and
synchronous
h ti ?
operation? synchronous
h ti ?
operation?
Schneider Electric - Energy Automation – Technical Institute 23 Schneider Electric - Energy Automation – Technical Institute 23

f / P coupling
p g f / P coupling
p g

● The fundamental rotating masses equation can be written as follows: ● The fundamental rotating masses equation can be written as follows:

J · (2/p)² · (f0 + f(t)) · ∂f/∂t = Pm(t) - Pe(t) J · (2/p)² · (f0 + f(t)) · ∂f/∂t = Pm(t) - Pe(t)

quasi-constant terms quasi-constant terms

frequency variation frequency variation


proportional to active power proportional to active power
unbalance unbalance

the proportionality relation is linked to the group the proportionality relation is linked to the group
‘turbine+generator’ construction (inertia, ...) ‘turbine+generator’ construction (inertia, ...)
Schneider Electric - Energy Automation – Technical Institute 24 Schneider Electric - Energy Automation – Technical Institute 24
The link with internal angle
g The link with internal angle
g

Mechanical power delivered to the generator: Pm Mechanical power delivered to the generator: Pm

Electrical power delivered by the generator : Pe Electrical power delivered by the generator : Pe

• Pm = Pe : constant internal angle • Pm = Pe : constant internal angle

• Pm > Pe : increasing internal angle • Pm > Pe : increasing internal angle

• Pm < Pe : decreasing internal angle e • Pm < Pe : decreasing internal angle e

Schneider Electric - Energy Automation – Technical Institute 25 Schneider Electric - Energy Automation – Technical Institute 25

Transmittable p
powers Transmittable p
powers

Schneider Electric - Energy Automation – Technical Institute 26 Schneider Electric - Energy Automation – Technical Institute 26
Apparent
pp p
power transmitted Apparent
pp p
power transmitted

G I R G I R

jXTI jXTI
ZT = RT + jXT ZT = RT + jXT
 
E VR RTI E VR RTI

The apparent power transmitted to infinite network (node R) is: The apparent power transmitted to infinite network (node R) is:

S = VR · I* = (VR · E · e-j - VR²) · e-j/ZT S = VR · I* = (VR · E · e-j - VR²) · e-j/ZT

Schneider Electric - Energy Automation – Technical Institute 27 Schneider Electric - Energy Automation – Technical Institute 27

Transmittable active power


p Transmittable active p
power

If the network resistance is neglected beside its reactance (RT << XT): If the network resistance is neglected beside its reactance (RT << XT):
● ZT = jXT ● ZT = jXT
●  = /2 ●  = /2

then the active power transmitted to the infinite network (node R) is: then the active power transmitted to the infinite network (node R) is:

P = Re(S) = (VR · E · sin) / XT P = Re(S) = (VR · E · sin) / XT

itt does therefore


t e e o e exist
e st a maximal
a a transmitted
t a s tted active
act e po o  = /
e for
power /2 itt does therefore
t e e o e exist
e st a maximal
a a transmitted
t a s tted active
act e po o  = /
e for
power /2
(static stability limit): (static stability limit):

Pmax = (VR · E) / XT Pmax = (VR · E) / XT


Schneider Electric - Energy Automation – Technical Institute 28 Schneider Electric - Energy Automation – Technical Institute 28
Transmittable active p
power Transmittable active p
power
G S L R G S L R
I I
Xd Xt Rt Xl Rl Xd Xt Rt Xl Rl

E VS VL VR E VS VL VR

If instead of fix E (constant excitation), one fixes VS (voltage regulation), If instead of fix E (constant excitation), one fixes VS (voltage regulation),
then the maximal transmitted active power from S towards R becomes: then the maximal transmitted active power from S towards R becomes:

P’max = (VR · VS) / (Xt + Xl) > Pmax


P P’max = (VR · VS) / (Xt + Xl) > Pmax
P

Schneider Electric - Energy Automation – Technical Institute 29 Schneider Electric - Energy Automation – Technical Institute 29

Transmittable active p
power Transmittable active p
power
G S L R G S L R
I I
Xd Xt Rt Xl Rl Xd Xt Rt Xl Rl

E VS VL VR E VS VL VR

As well, if one fixes VL ((voltage


g regulation
g at connection node),
) then the As well, if one fixes VL ((voltage
g regulation
g at connection node),
) then the
maximal transmitted active power from L towards R becomes: maximal transmitted active power from L towards R becomes:

P’’max = (VR · VL) / Xl > P’max > Pmax P’’max = (VR · VL) / Xl > P’max > Pmax

Voltage regulators action (excitation systems) allows then stable operation of the machine Voltage regulators action (excitation systems) allows then stable operation of the machine
in a zone where it is not « naturally » stable in a zone where it is not « naturally » stable
Schneider Electric - Energy Automation – Technical Institute 30 Schneider Electric - Energy Automation – Technical Institute 30
Static stability
y limit Static stability
y limit

static stability limit rotating


t ti masses equation
ti with
ith static stability limit rotating
t ti masses equation
ti with
ith
angles : angles :
Pm Pm
J·Ω·∂²/∂t² = Pm - PMax·sin J·Ω·∂²/∂t² = Pm - PMax·sin
stable unstable disturbance around the operating stable unstable disturbance around the operating
PMax PMax
point (Pm0 ; 0) : point (Pm0 ; 0) :
J·Ω·∂²/∂t² = - PMax·cos· J·Ω·∂²/∂t² = - PMax·cos·

Pm0 stable oscillation if Pm0 stable oscillation if


cos>0
PMax·cos cos>0
PMax·cos
i.e.: i.e.:
0 <  < /2 0 <  < /2

Pe = PMax · sin Pe = PMax · sin

0 0 /2
/2 ’
0   0 0 /2
/2 ’
0  

Schneider Electric - Energy Automation – Technical Institute 31 Schneider Electric - Energy Automation – Technical Institute 31

Areas equality
q y theorem Areas equality
q y theorem
b final situation: Pméca = Pm1 b final situation: Pméca = Pm1
a initial situation: Pméca = Pm0 a initial situation: Pméca = Pm0
-> new equilibrium point:  = 1 -> new equilibrium point:  = 1

Pm dynamic stability Pm dynamic stability


limit
acceleration phase: limit
acceleration phase:
A1 : kinetic energy stored by the A1 : kinetic energy stored by the
c machine during this phase c machine during this phase
PMax PMax
b A2 b’ b A2 b’
Pm1 Pm1
braking phase: braking phase:
A1 A1
A2 : kinetic energy restored by A2 : kinetic energy restored by
the machine during this phase the machine during this phase

Pm0 a energy conservation Pm0 a energy conservation


 A1 = A2  A1 = A2

Pe = PMax · sin Pe = PMax · sin

0 0 1 /2 m
/2 L   0 0 1 /2 m
/2 L  

Schneider Electric - Energy Automation – Technical Institute 32 Schneider Electric - Energy Automation – Technical Institute 32
Short circuits and stabilityy Short circuits and stability
y

Schneider Electric - Energy Automation – Technical Institute 33 Schneider Electric - Energy Automation – Technical Institute 33

Short-circuit Short-circuit

Pm Pm
G G
Pe Pe
initial state initial state
PMax PMax
Pm Pm
PMax PMax

Pm Pm

e e
0 /2
/   0 /2
/  

Schneider Electric - Energy Automation – Technical Institute 34 Schneider Electric - Energy Automation – Technical Institute 34
Short-circuit Short-circuit

Pm Pm
G G
Pe Pe
occurrence of a short-circuit occurrence of a short-circuit
PMax PMax
Pm Pm
PMax PMax

Pm Pm

e e
0 /2
/   0 /2
/  

Schneider Electric - Energy Automation – Technical Institute 35 Schneider Electric - Energy Automation – Technical Institute 35

Short-circuit Short-circuit

Pm Pm
G G
Pe Pe
acceleration phase acceleration phase
PMax PMax
Pm Pm
PMax PMax

Pm Pm

e e
0 /2
/   0 /2
/  

Schneider Electric - Energy Automation – Technical Institute 36 Schneider Electric - Energy Automation – Technical Institute 36
Short-circuit Short-circuit

Pm Pm
G G
Pe Pe
line tripping line tripping
PMax PMax
Pm Pm
PMax PMax

Pm Pm

e e
0 /2
/   0 /2
/  

Schneider Electric - Energy Automation – Technical Institute 37 Schneider Electric - Energy Automation – Technical Institute 37

Short-circuit Short-circuit

Pm Pm
G G
Pe Pe
braking phase braking phase
PMax PMax
Pm Pm
PMax PMax

Pm Pm

e e
0 /2
/   0 /2
/  

Schneider Electric - Energy Automation – Technical Institute 38 Schneider Electric - Energy Automation – Technical Institute 38
Influence of the type
yp of short-circuit Influence of the type
yp of short-circuit

Pm Pm
no short-circuit no short-circuit

one-phase-to-ground short-circuit one-phase-to-ground short-circuit

two-phase short-circuit two-phase short-circuit

two-phase-to-ground short-circuit two-phase-to-ground short-circuit

three-phase short-circuit three-phase short-circuit

0 /2
/2   0 /2
/2  

Schneider Electric - Energy Automation – Technical Institute 39 Schneider Electric - Energy Automation – Technical Institute 39

Influence of network mesh densityy Influence of network mesh density


y

G G G G

Pm Pm Pm Pm
PMax
M PMax
M PMax
M PMax
M

Pm Pm Pm Pm

0 /2   0 /2   0 /2   0 /2  

A2 > A1 : stable A2 < A1 : unstable A2 > A1 : stable A2 < A1 : unstable

Schneider Electric - Energy Automation – Technical Institute 40 Schneider Electric - Energy Automation – Technical Institute 40
Influence of fault clearing
g time Influence of fault clearing
g time

G G G G

t t t t
Pm Pm Pm Pm
PMax PMax PMax PMax

Pm Pm Pm Pm

0 /2   0 /2
/   0 /2   0 /2
/  

A2 > A1 : stable A2 < A1 : unstable A2 > A1 : stable A2 < A1 : unstable


Schneider Electric - Energy Automation – Technical Institute 41 Schneider Electric - Energy Automation – Technical Institute 41

Autoreclose and stabilityy Autoreclose and stability


y

Schneider Electric - Energy Automation – Technical Institute 42 Schneider Electric - Energy Automation – Technical Institute 42
Automatic recloser Automatic recloser

Pm Pm
G G
Pe Pe
initial state initial state
PMax PMax
Pm Pm
PMax PMax

Pm Pm

e e
0 /2
/   0 /2
/  

Schneider Electric - Energy Automation – Technical Institute 43 Schneider Electric - Energy Automation – Technical Institute 43

Automatic recloser Automatic recloser

Pm Pm
G G
Pe Pe
short-circuit short-circuit
PMax PMax
Pm Pm
PMax PMax

Pm Pm

e e
0 /2
/   0 /2
/  

Schneider Electric - Energy Automation – Technical Institute 44 Schneider Electric - Energy Automation – Technical Institute 44
Automatic recloser Automatic recloser

Pm Pm
G G
Pe Pe
trip trip
PMax PMax
Pm Pm
PMax PMax

Pm Pm

e e
0 /2
/   0 /2
/  

Schneider Electric - Energy Automation – Technical Institute 45 Schneider Electric - Energy Automation – Technical Institute 45

Automatic recloser Automatic recloser

Pm Pm
G G
Pe Pe
reclosing reclosing
PMax PMax
Pm Pm
PMax PMax

Pm Pm

e e
0 /2
/   0 /2
/  

Schneider Electric - Energy Automation – Technical Institute 46 Schneider Electric - Energy Automation – Technical Institute 46
Synchro-check
y Synchro-check
y

● The generator and the network are synchronous together ● The generator and the network are synchronous together

G G

Schneider Electric - Energy Automation – Technical Institute 47 Schneider Electric - Energy Automation – Technical Institute 47

Synchro-check
y Synchro-check
y

● Short-circuit: the link between the generator and the network is very ● Short-circuit: the link between the generator and the network is very
weak weak

G G

Pe increase
P i Pe decrease
P d Pe increase
P i Pe decrease
P d
=> F decrease => F increase => F decrease => F increase

Schneider Electric - Energy Automation – Technical Institute 48 Schneider Electric - Energy Automation – Technical Institute 48
Synchro-check
y Synchro-check
y

● Line opening: the generator evolves independently from the network ● Line opening: the generator evolves independently from the network

G G

Schneider Electric - Energy Automation – Technical Institute 49 Schneider Electric - Energy Automation – Technical Institute 49

Synchro-check
y Synchro-check
y

● Reclosing: it is essential to check the synchronism between generator ● Reclosing: it is essential to check the synchronism between generator
and network voltage before allowing line reclosing and network voltage before allowing line reclosing

G G

│V│ ≤ Vmax │V│ ≤ Vmax


││ ≤ max ││ ≤ max
LB: live
LB li b bus LB: live
LB li b bus LB: live
LB li b bus LB: live
LB li b bus
DB: dead bus │f│ ≤ fmax DB: dead bus DB: dead bus │f│ ≤ fmax DB: dead bus
LL: live line LL: live line LL: live line LL: live line
DL: dead line DL: dead line DL: dead line DL: dead line

Schneider Electric - Energy Automation – Technical Institute 50 Schneider Electric - Energy Automation – Technical Institute 50
Synchro-check
y Synchro-check
y

G G

LB-DL: wait LB-DL: reclose LB-DL: wait LB-DL: reclose

Schneider Electric - Energy Automation – Technical Institute 51 Schneider Electric - Energy Automation – Technical Institute 51

Synchro-check
y Synchro-check
y

G G

LB-LL: synchro-check LB-LL: synchro-check

synchronism conditions not OK: wait synchronism conditions not OK: wait

Schneider Electric - Energy Automation – Technical Institute 52 Schneider Electric - Energy Automation – Technical Institute 52
Synchro-check
y Synchro-check
y

G G

Be carefull between Be carefull between


LB-LL: synchro-check synchro-check and LB-LL: synchro-check synchro-check and
synchro-couplor !! synchro-couplor !!

synchronism conditions OK: reclose synchronism conditions OK: reclose

Schneider Electric - Energy Automation – Technical Institute 53 Schneider Electric - Energy Automation – Technical Institute 53

Autoreclose applications
pp Autoreclose applications
pp

Schneider Electric - Energy Automation – Technical Institute 54 Schneider Electric - Energy Automation – Technical Institute 54
• Most of insulation faults need repair before re-energisation • Most of insulation faults need repair before re-energisation

• Bus bar Fault • Bus bar Fault


• Underground cable Fault • Underground cable Fault
• Transformer Fault • Transformer Fault
• Generator Fault • Generator Fault
• Motor Fault • Motor Fault

• Protective relay tripping must therefore be definitive • Protective relay tripping must therefore be definitive
(Lockout with manual reset) (Lockout with manual reset)

Schneider Electric - Energy Automation – Technical Institute 55 Schneider Electric - Energy Automation – Technical Institute 55

In Over Head Line, some insulation fault due to lightning stroke will In Over Head Line, some insulation fault due to lightning stroke will
disappear after current feed interruption. disappear after current feed interruption.

Schneider Electric - Energy Automation – Technical Institute 56 Schneider Electric - Energy Automation – Technical Institute 56
1 Pole or 3 Pole Tripping ? 1 Pole or 3 Pole Tripping ?

Schneider Electric - Energy Automation – Technical Institute 57 Schneider Electric - Energy Automation – Technical Institute 57

Schneider Electric - Energy Automation – Technical Institute 58 Schneider Electric - Energy Automation – Technical Institute 58
1 pole or 3 pole tripping? 1 pole or 3 pole tripping?
Why 1 pole tripping on transmission network ? Why 1 pole tripping on transmission network ?
• 1 pole tripping maintain electrical link between power stations • 1 pole tripping maintain electrical link between power stations
which is helpful to maintain stability : which is helpful to maintain stability :
• If after a fault the 3 poles are opened, electrical link will disappear • If after a fault the 3 poles are opened, electrical link will disappear

• If after a fault onlyy 1 pole


p is opened,
p electrical link will remain p
partly
y y 1 pole
• If after a fault only p is opened,
p electrical link will remain p
partly
y

• Most of insulation fault are 1 phase because • Most of insulation fault are 1 phase because
the large distance between phases and ground. the large distance between phases and ground.

• Power system stability requirement is above material • Power system stability requirement is above material
1 3 1 3
cost increase (Non distributed energy may cost a lot) 2
cost increase (Non distributed energy may cost a lot) 2

> 85 % < 15 % > 85 % < 15 %

Schneider Electric - Energy Automation – Technical Institute 59 Schneider Electric - Energy Automation – Technical Institute 59

Therefore in transmission network single pole tripping is provided ... Therefore in transmission network single pole tripping is provided ...

… followed by single pole reclosing … followed by single pole reclosing

Schneider Electric - Energy Automation – Technical Institute 60 Schneider Electric - Energy Automation – Technical Institute 60
Single phase tripping in HV network. Single phase tripping in HV network.
why
h ? why
h ?
•In Distribution network, the network is meshed and not directly •In Distribution network, the network is meshed and not directly
connected to power plant. No risk to loose one line connected to power plant. No risk to loose one line

•The number of single line fault is lower than in •The number of single line fault is lower than in
transmission network transmission network

•Cost reduction of primary equipment and wiring simplicity •Cost reduction of primary equipment and wiring simplicity
is more important 1 2 3 is more important 1 2 3

60 % 20 % 20 % 60 % 20 % 20 %

Schneider Electric - Energy Automation – Technical Institute 61 Schneider Electric - Energy Automation – Technical Institute 61

•The tripping mode for distribution network is therefore •The tripping mode for distribution network is therefore
always
a ays 3 pphases,
ases, always
a ays 3 pphases,
ases,

… followed by
y a three p
phase reclosing
g … followed byy a three p
phase reclosing
g

Schneider Electric - Energy Automation – Technical Institute 62 Schneider Electric - Energy Automation – Technical Institute 62
Dead time to be coordinated with : Dead time to be coordinated with :
Minimum de-energisation time Minimum de-energisation time

Minimum de-energisation Minimum de-energisation


time depends also on fault time depends also on fault
d ti
duration. d ti
duration.

Circuit breaker operationg mechanism and chamber cooling Circuit breaker operationg mechanism and chamber cooling

Typically : O - 0.3 s - C - O Typically : O - 0.3 s - C - O

System stability requirements System stability requirements

Schneider Electric - Energy Automation – Technical Institute 63 Schneider Electric - Energy Automation – Technical Institute 63

Choice of Scheme Choice of Scheme

Schneider Electric - Energy Automation – Technical Institute 64 Schneider Electric - Energy Automation – Technical Institute 64
Choice of Scheme (1)
( ) Choice of Scheme (1)
( )
High Speed Auto-Reclose High Speed Auto-Reclose

1. Single transmission links. 1. Single transmission links.

2. 3Ø A/R. 2. 3Ø A/R.

3. 1Ø A/R for E/Fs 3. 1Ø A/R for E/Fs


Lockout for multiphase faults. Lockout for multiphase faults.

4. 1Ø A/R for E/Fs 4. 1Ø A/R for E/Fs


p
3Ø A/R for multiphase faults. p
3Ø A/R for multiphase faults.

Schneider Electric - Energy Automation – Technical Institute 65 Schneider Electric - Energy Automation – Technical Institute 65

Choice of Scheme (2)


( ) Choice of Scheme (2)
( )
Delayed 3Ø Auto-Reclose Delayed 3Ø Auto-Reclose

1. Densely interconnected systems. 1. Densely interconnected systems.

Minimal power transfer level Minimal power transfer level


reduction during dead time reduction during dead time

2. Power swings due to fault and tripping 2. Power swings due to fault and tripping
allowed to decay allowed to decay

Less shock to system than with high speed Less shock to system than with high speed
A/R A/R

Schneider Electric - Energy Automation – Technical Institute 66 Schneider Electric - Energy Automation – Technical Institute 66
1 Phase Auto-Reclose Factors 1 Phase Auto-Reclose Factors
R
Requiring
ii C Consideration
id ti R
Requiring
ii C Consideration
id ti
1
1. S
Separate
t control
t l off circuit
i it breaker
b k poles.
l 1
1. S
Separate
t control
t l off circuit
i it breaker
b k poles.
l

2. Protection must provide phase selection. 2. Protection must provide phase selection.

3. Mutual coupling can prolong arcing and require de- 3. Mutual coupling can prolong arcing and require de-
g time.
ionising g time.
ionising

4. Unbalance during dead time 4. Unbalance during dead time


(i) Interference with communications (i) Interference with communications
(ii) Parallel feeder protection may mal-operate (ii) Parallel feeder protection may mal-operate

5
5. More complex and expensive than 3Ø A/R 5
5. More complex and expensive than 3Ø A/R

Schneider Electric - Energy Automation – Technical Institute 67 Schneider Electric - Energy Automation – Technical Institute 67

High
g Speed
p Auto-Reclose ((H.S.A.R.)) ((1)) High
g Speed
p Auto-Reclose ((H.S.A.R.)) ((1))
Protection Protection
High speed < 2 cycles High speed < 2 cycles

Fast clearance at each line end. Fast clearance at each line end.
 Phase comparison  Phase comparison
 Distance schemes with signalling  Distance schemes with signalling
 Distance scheme with zone 1 extension  Distance scheme with zone 1 extension
 Direct intertrip  Direct intertrip

Phase selection required


q for 1Ø A/R Phase selection required
q for 1Ø A/R

Schneider Electric - Energy Automation – Technical Institute 68 Schneider Electric - Energy Automation – Technical Institute 68
High
g Speed
p Auto-Reclose ((H.S.A.R.)) ((2)) High
g Speed
p Auto-Reclose ((H.S.A.R.)) ((2))

Dead Time (short as possible) Dead Time (short as possible)


Circuit breaker minimum ‘open - close’ Circuit breaker minimum ‘open - close’
time time
 200 - 300 msecs.  200 - 300 msecs.

Same dead time at each line end. Same dead time at each line end.

De-ionising time De-ionising time


1Ø A/R longer  special steps 1Ø A/R longer  special steps

Schneider Electric - Energy Automation – Technical Institute 69 Schneider Electric - Energy Automation – Technical Institute 69

Delayed
y Auto-Reclosing
g (D.A.R.)
( ) ((1)) Delayed
y Auto-Reclosing
g (D.A.R.)
( ) ((1))
Protection Protection
High speed not critical for system stability High speed not critical for system stability
 
desirable to limit fault damage desirable to limit fault damage
 
improves probability of successful A/R improves probability of successful A/R

Dead Time Dead Time


Allow for power swings and rotor oscillations to die Allow for power swings and rotor oscillations to die
down. down.
Different settings for opposite feeder ends. Different settings for opposite feeder ends.
Typically 5 to 60 secs. Typically 5 to 60 secs.

Schneider Electric - Energy Automation – Technical Institute 70 Schneider Electric - Energy Automation – Technical Institute 70
Delayed
y Auto-Reclosing
g (D.A.R.)
( ) ((2)) Delayed
y Auto-Reclosing
g (D.A.R.)
( ) ((2))

Reclaim Time Reclaim Time


Allow c.b. capacity to recover to full interrupting Allow c.b. capacity to recover to full interrupting
value. value.

Number of Shots Number of Shots


1 (invariably)
( y) 1 (invariably)
( y)

Schneider Electric - Energy Automation – Technical Institute 71 Schneider Electric - Energy Automation – Technical Institute 71

Dead time to be coordinated with (next)


( ) Dead time to be coordinated with (next)
( )

● CB drive of the circuit breaker (400kV (GIS) – Example. ● CB drive of the circuit breaker (400kV (GIS) – Example.

Schneider Electric - Energy Automation – Technical Institute 72 Schneider Electric - Energy Automation – Technical Institute 72
Voltage checks in coupling Voltage checks in coupling
mode mode

Schneider Electric - Energy Automation – Technical Institute 73 Schneider Electric - Energy Automation – Technical Institute 73

Vectorial Vectorial
difference difference
Magnitude difference Magnitude difference
Angle difference Angle difference
Frequency difference Frequency difference

Frequency Frequency

Schneider Electric - Energy Automation – Technical Institute 74 Schneider Electric - Energy Automation – Technical Institute 74
7.3 Trip Circuit Supervision 7.3 Trip Circuit Supervision
Trip Circuit Supervision Trip Circuit Supervision

Ref : APP14 Ref : APP14

Issue A1 Issue A1
Last Release : March 2011 Last Release : March 2011

Operating Principle Operating Principle

Schneider Electric - Energy Automation – 09/2010 2 Schneider Electric - Energy Automation – 09/2010 2
Trip Circuit Supervision Trip Circuit Supervision
operating principle operating principle

Supervision Supervision
current current
Mechanical Mechanical
Command Command

Schneider Electric - Energy Automation – 09/2010 3 Schneider Electric - Energy Automation – 09/2010 3

Trip Circuit Supervision Trip Circuit Supervision


operating principle operating principle

Disappearance Disappearance
of supervision of supervision
current current
mechanical mechanical
Tripping circuit Command Tripping circuit Command
interruption interruption

Schneider Electric - Energy Automation – 09/2010 4 Schneider Electric - Energy Automation – 09/2010 4
Trip Circuit Supervision Trip Circuit Supervision
operating principle operating principle

Alarm Alarm
mechanical mechanical
Command Command

Schneider Electric - Energy Automation – 09/2010 5 Schneider Electric - Energy Automation – 09/2010 5

Applications Applications

Schneider Electric - Energy Automation – 09/2010 6 Schneider Electric - Energy Automation – 09/2010 6
Trip Circuit Supervision Trip Circuit Supervision
Applications Applications
• Improve
I the
th security
it andd availality
il lit off th
the ttripping
i i circuit
i it b
by a • Improve
I the
th security
it andd availality
il lit off th
the ttripping
i i circuit
i it b
by a
permanent continuity control. permanent continuity control.
• In case of circuit interruption
interruption, an alarm is generated • In case of circuit interruption
interruption, an alarm is generated

• Without this control, the interrupted circuit will only be detected after a • Without this control, the interrupted circuit will only be detected after a
fault without correct clearance. fault without correct clearance.

Schneider Electric - Energy Automation – 09/2010 7 Schneider Electric - Energy Automation – 09/2010 7

Trip Circuit Supervision Trip Circuit Supervision


Applications Applications
• Applicable iff the trip coil off circuit breaker is activated with a DC
C • Applicable iff the trip coil off circuit breaker is activated with a DC
C
polarity polarity
• In other cases,
cases an interruption of the trip circuit will cause an • In other cases,
cases an interruption of the trip circuit will cause an
immediate trip. immediate trip.
• Special application cases must be studied when using auxiliairy • Special application cases must be studied when using auxiliairy
tripping contacts or lock-out relays tripping contacts or lock-out relays

Schneider Electric - Energy Automation – 09/2010 8 Schneider Electric - Energy Automation – 09/2010 8
Trip Circuit Supervision Trip Circuit Supervision
Applications Applications
• Will allow a reduction of cyclic maintenance costs • Will allow a reduction of cyclic maintenance costs
• Will allow a more important delay between real circuit breaker tests. • Will allow a more important delay between real circuit breaker tests.
These tests become only required for the mechanical part control of These tests become only required for the mechanical part control of
the CB the CB

Schneider Electric - Energy Automation – 09/2010 9 Schneider Electric - Energy Automation – 09/2010 9

Trip Circuit Supervision Trip Circuit Supervision


Applications Applications
• Need to be coordinated with the circuit breaker manufacturer : • Need to be coordinated with the circuit breaker manufacturer :
- The maximum permanent current depends on the coil impedance, - The maximum permanent current depends on the coil impedance,
- The maximum permanent current must not cause any coil heating
heating, - The maximum permanent current must not cause any coil heating
heating,
- The electrical scheme of the CB tripping circuit must be in acordance - The electrical scheme of the CB tripping circuit must be in acordance
with the selected trip circuit supervision scheme with the selected trip circuit supervision scheme

Schneider Electric - Energy Automation – 09/2010 10 Schneider Electric - Energy Automation – 09/2010 10
Comparison Comparison
of different existing schemes of different existing schemes

Schneider Electric - Energy Automation – 09/2010 11 Schneider Electric - Energy Automation – 09/2010 11

Trip Circuit Supervision - Scheme n° 1 Trip Circuit Supervision - Scheme n° 1


+ + + +
Relay

Relay
elay

elay
Advantages Advantages
Re

Re
2 cables only between 2 cables only between
relay and circuit breaker relay and circuit breaker

- - - -

Alarm Alarm Alarm Alarm

Disadvantages
g Disadvantages
g
Circcuit Breaker

Circcuit Breaker

Circcuit Breaker

Circcuit Breaker
No trip circuit control if No trip circuit control if
CB open CB open
2a

2a

2a

2a
52

52

52

52
Contct position Contct position
when when
equipment equipment
energised energised

Schneider Electric - Energy Automation – 09/2010 12 Schneider Electric - Energy Automation – 09/2010 12
Trip Circuit Supervision - Scheme n° 2 Trip Circuit Supervision - Scheme n° 2
+ + + +

Relay

Relay

Relay

Relay
Advantages Advantages
2 cables only between 2 cables only between
relay and circuit breaker. relay and circuit breaker.

- - Wire up to the CB,


- - Wire up to the CB,
whatever the position. whatever the position.
Al
Alarm Al
Alarm Al
Alarm Al
Alarm

Disadvantages
g Disadvantages
g
ker

ker
ker

ker
Circuit Break

Circuit Break
Circuit Break

Circuit Break
(1) (1)
No trip circuit control if No trip circuit control if
CB open CB open
52b

52b
52b

52b
52a

52a

52a

52a
Requires additional Requires additional
resistance into the CB resistance into the CB
Contct position control box (1) Contct position control box (1)
when when
equipment equipment
energised (1) Avoid a Battery short circuit when the CB is already open but trip energised (1) Avoid a Battery short circuit when the CB is already open but trip
order still present. order still present.
Schneider Electric - Energy Automation – 09/2010 13 Schneider Electric - Energy Automation – 09/2010 13

Trip Circuit Supervision - Scheme n° 3 Trip Circuit Supervision - Scheme n° 3


+ + + +
elay

elay

elay

elay
Advantages Advantages
Re

Re

Re

Re
The trip coil is controlled The trip coil is controlled
whatever the CB position whatever the CB position

- - - -

Alarm Alarm Alarm Alarm


Disadvantages Disadvantages
Requires 3 wires between Requires 3 wires between
Circcuit Breaker

Circcuit Breaker

Circcuit Breaker

Circcuit Breaker
relay and CB. relay and CB.
52b

52b
52b

52b
2a

2a

2a

2a
Tripping cable between Tripping cable between
52

52

52

52
5

5
5

5
relay and CB not relay and CB not
controlled if CB open controlled if CB open
Contct position Contct position
when when
equipment equipment
energised energised

Schneider Electric - Energy Automation – 09/2010 14 Schneider Electric - Energy Automation – 09/2010 14
Trip Circuit Supervision - Scheme n° 4 Trip Circuit Supervision - Scheme n° 4
+ + + +

Relay

Relay

Relay

Relay
Advantages Advantages
The trip coil is controlled The trip coil is controlled
whatever the CB position whatever the CB position

- - - -

(1) Al
Alarm Al
Alarm (1) Al
Alarm Al
Alarm

Disadvantages Disadvantages
ker

ker
ker

ker
Requires 3 wires between Requires 3 wires between
Circuit Break

Circuit Break
Circuit Break

Circuit Break
relay and CB. relay and CB.
52a

52a

52a

52a
Tripping cable between Tripping cable between
relay and CB not relay and CB not
controlled whatever the controlled whatever the
Contct position
CB position (1) - only the Contct position
CB position (1) - only the
when coil is controlled when coil is controlled
equipment equipment
energised (1) if interrupted, the current value becomes identical of the current circulation when CB is energised (1) if interrupted, the current value becomes identical of the current circulation when CB is
open. open.
Schneider Electric - Energy Automation – 09/2010 15 Schneider Electric - Energy Automation – 09/2010 15

Trip Circuit Supervision - Scheme n° 5 Trip Circuit Supervision - Scheme n° 5


+ + + +
elay

elay

elay

elay
Advantages Advantages
Re

Re

Re

Re
The trip coil is controlled The trip coil is controlled
whatever the CB position whatever the CB position

- - - -

(1) Alarm Alarm (1) Alarm Alarm


Disadvantages Disadvantages
Requires 3 wires between Requires 3 wires between
Circcuit Breaker

Circcuit Breaker

Circcuit Breaker

Circcuit Breaker
relay and CB. relay and CB.

Tripping cable between Tripping cable between


2a

2a

2a

2a
52

52

52

52
relay and CB not relay and CB not
controlled whatever the controlled whatever the
Contct position
CB position (1) - only the Contct position
CB position (1) - only the
when coil is controlled
controlled. when coil is controlled
controlled.
equipment equipment
energised energised

Schneider Electric - Energy Automation – 09/2010 16 Schneider Electric - Energy Automation – 09/2010 16
Trip Circuit Supervision - Scheme n° 6 Trip Circuit Supervision - Scheme n° 6
+ + + +

Relay

Relay

Relay

Relay
Advantages Advantages
2 cables only between 2 cables only between
relay and circuit breaker. relay and circuit breaker.
Triping contact Triping contact
CB Tripping coil CB Tripping coil
Logic Input Logic Input
controlled whatever the controlled whatever the
(O t )
(Opto) - - CB position
(O t )
(Opto) - - CB position

Alarm Alarm Tripping cable between Alarm Alarm Tripping cable between
relay and CB controlled relay and CB controlled
whatever the CB position whatever the CB position
eaker

eaker

eaker

eaker
(1) (1)
Circuit Bre

Circuit Bre

Circuit Bre

Circuit Bre
Disadvantages Disadvantages
52b

52b
52b

52b
52a

52a

52a

52a
Requires installation of Requires installation of
additional resistance into additional resistance into
the CB control box (1) the CB control box (1)

Contct position Contct position


when when
equipment (1) avoid any damage of the tripping coil when trip order still present and circuit breaker equipment (1) avoid any damage of the tripping coil when trip order still present and circuit breaker
energised energised
already open. already open.
Schneider Electric - Energy Automation – 09/2010 17 Schneider Electric - Energy Automation – 09/2010 17

Trip circuit Supervision Trip circuit Supervision

Practical Example Practical Example


MVAX 91 MVAX 91

Schneider Electric - Energy Automation – 09/2010 18 Schneider Electric - Energy Automation – 09/2010 18
Typical Wiring - Requirements Typical Wiring - Requirements

● Be carefull : ● Be carefull :

● Test Circuit or secondary injection circuits must be inside the supervision ● Test Circuit or secondary injection circuits must be inside the supervision
loop loop

Schneider Electric - Energy Automation – 09/2010 19 Schneider Electric - Energy Automation – 09/2010 19

Trip Circuit Supervision Trip Circuit Supervision


practical Example with MiCOM practical Example with MiCOM
P123 P123

Schneider Electric - Energy Automation – 09/2010 20 Schneider Electric - Energy Automation – 09/2010 20
Trip Circuit Supervision Trip Circuit Supervision
MiCOM P123 MiCOM P123
Delay timer Delay timer
MiCOM serie 20 : MiCOM serie 20 :
P123 Only P123 Only

Logical input (Opto) Logical input (Opto)

Opto Opto
Al
Alarm ttrip
i Al
Alarm ttrip
i
&
ET circuit faulty &
ET circuit faulty
Trip contact Trip contact
energised energised

Trip contact energised =1 if Opto does not Avoid any intempestive Trip contact energised =1 if Opto does not Avoid any intempestive
detect any current alarm in case of detect any current alarm in case of
during TSUP timer permanent trip orders. during TSUP timer permanent trip orders.

Schneider Electric - Energy Automation – 09/2010 21 Schneider Electric - Energy Automation – 09/2010 21

Trip Circuit Supervision with overcurrent Trip Circuit Supervision with overcurrent
relays - scheme 1 relays - scheme 1
+ +
elay

elay
Re

Re
- -

Alarm Overcurrent relay Alarm Overcurrent relay


Circuit Breaker

Circuit Breaker
Trip coil Trip coil
52a

52a
Trip coil control Trip coil control

Schneider Electric - Energy Automation – 09/2010 22 Schneider Electric - Energy Automation – 09/2010 22
Trip Circuit Supervision with overcurrent Trip Circuit Supervision with overcurrent
relays - scheme 2 relays - scheme 2
+ +
Relay

Relay
- -
Overcurrent relay Overcurrent relay
Alarme Alarme
Circuitt Breaker

Circuitt Breaker
Trip
p coil Resistance Trip
p coil Resistance
52a

52b

52a

52b
Trip coil and auxiliary contacts control Trip coil and auxiliary contacts control

Schneider Electric - Energy Automation – 09/2010 23 Schneider Electric - Energy Automation – 09/2010 23

Trip Circuit Supervision with overcurrent Trip Circuit Supervision with overcurrent
relays - scheme 6 (optimal) relays - scheme 6 (optimal)
+ +
Relay

Relay
Logical input Logical input

- -
Overcurrent relay Overcurrent relay

Alarme Alarme
Circcuit Breaker

Circcuit Breaker
Resistance Resistance
Trip coil Trip coil
52a

52b

52a

52b
5

5
Trip coil and auxiliary contacts control whatever the CB Trip coil and auxiliary contacts control whatever the CB
position position

Schneider Electric - Energy Automation – 09/2010 24 Schneider Electric - Energy Automation – 09/2010 24
Trip Circuit Supervision Trip Circuit Supervision
Practical Example with MiCOM Practical Example with MiCOM
serie 40 serie 40

Schneider Electric - Energy Automation – 09/2010 25 Schneider Electric - Energy Automation – 09/2010 25

Trip Circuit Supervision with Programmable Trip Circuit Supervision with Programmable
Scheme Logics (Px40 range relay) Scheme Logics (Px40 range relay)
+ +
Relay

Relay
- -

Alarm Alarm
Disjoncteur

Disjoncteur

Release timer Release timer


D

D
52a
a

52a
a
52b
b

52b
b
Contact Contact
position when position when
equipment equipment
energised energised
Schneider Electric - Energy Automation – 09/2010 26 Schneider Electric - Energy Automation – 09/2010 26

You might also like