Professional Documents
Culture Documents
1 Breaker Failure
Breaker Failure Protection Breaker Failure Protection
Issue B2 Issue B2
Last Release : June 2012 Last Release : June 2012
Program
g Program
g
Objective Objective
Operation Principle Operation Principle
Reset Conditions Reset Conditions
50 BF Protection integrated to BusBar protections 50 BF Protection integrated to BusBar protections
Setting guide - Example Setting guide - Example
● Reduction of the Total Fault Clearance time in case of a Circuit Breaker ● Reduction of the Total Fault Clearance time in case of a Circuit Breaker
Failure Failure
● Re-Trip order (second circuit) to the Circuit Breaker Coil (same or second) ● Re-Trip order (second circuit) to the Circuit Breaker Coil (same or second)
● Current Supervision through the Circuit Breaker ● Current Supervision through the Circuit Breaker
● In case of Fault Clearance Failure, issue of a back trip order to all adjacent ● In case of Fault Clearance Failure, issue of a back trip order to all adjacent
Circuit Breakers Circuit Breakers
● Operation must occur before second stage tripping time of remote distance ● Operation must occur before second stage tripping time of remote distance
protections protections
● Supervision of Circuit Breaker Status contacts is possible as option ● Supervision of Circuit Breaker Status contacts is possible as option
Schneider Electric - Infrastructure Business 4 Schneider Electric - Infrastructure Business 4
Breaker Failure Protection Breaker Failure Protection
● For Reliable Power System operation the protective scheme ● For Reliable Power System operation the protective scheme
must be dependable must be dependable
● Speed ● Speed
● Maintain System Stability ● Maintain System Stability
● Discrimination ● Discrimination
● Minimise the Plant Isolated ● Minimise the Plant Isolated
● Reliability
R li bilit ● Reliability
R li bilit
● Operates infrequently ● Operates infrequently
● Duplicate :- ● Duplicate :-
●Protective Relays ●Protective Relays
●Trip Coils ●Trip Coils
●DC Supplies ●DC Supplies
●Instrument Transformers ●Instrument Transformers
● Clear the faulted Apparatus with ● Clear the faulted Apparatus with
●Minimum Time Delay ●Minimum Time Delay
●Minimum Disruption to the Power System ●Minimum Disruption to the Power System
● Backup Protection Exists in Two Forms ● Backup Protection Exists in Two Forms
●Local Backup ●Local Backup
●Remote Backup ●Remote Backup
Remote Backup
p - Distance Remote Backup
p - Distance
Z3 Z3
Z2 Z2
Z1 Z1
● Advantages ● Advantages
● Not affected by adverse conditions at the local station ● Not affected by adverse conditions at the local station
● Backup for both relays and circuit breakers ● Backup for both relays and circuit breakers
● Disadvantages ● Disadvantages
● Time
Ti delayed
d l d tto maintain
i t i di
discrimination
i i ti ● Time
Ti delayed
d l d tto maintain
i t i di
discrimination
i i ti
● Sensitivity is affected by fault infeeds at remote busbars ● Sensitivity is affected by fault infeeds at remote busbars
● Wide spread disruption ● Wide spread disruption
Main Main
50BF 50BF
● Disadvantages ● Disadvantages
● May be Affected by Local Conditions ● May be Affected by Local Conditions
● “Accidental
“A id t l O Operation”
ti ” - Unwanted
U t dSSystem
t Disruption
Di ti ● “Accidental
“A id t l O Operation”
ti ” - Unwanted
U t dSSystem
t Disruption
Di ti
● Security ● Security
● No Unwanted Operation ● No Unwanted Operation
● Dependability ● Dependability
● Guaranteed Operation in Case of Fault ● Guaranteed Operation in Case of Fault
Local Backup
p Local Backup
p
● Two Main Types ● Two Main Types
● Relay Backup ● Relay Backup
●Provision of Main 1 and Main 2 Protection Relays ●Provision of Main 1 and Main 2 Protection Relays
● Breaker Backup ● Breaker Backup
●HV Breakers are Expensive and are not duplicated ●HV Breakers are Expensive and are not duplicated
●Two Independent Trip Coils but a Common operating Mechanism ●Two Independent Trip Coils but a Common operating Mechanism
●Possible Point of Failure ●Possible Point of Failure
Fault in one feeder without breaker Fault in one feeder without breaker
failure failure
21 21 21 21 21 21 21 21
D1 D2 D3 D4 D1 D2 D3 D4
D5 D6 D7 D5 D6 D7
G 21 21 21
G 21 21 21
1 Fault appearance
1. 1 Fault appearance
1.
2. Activation of MAIN zone 1 2. Activation of MAIN zone 1
(D1 and D2) (D1 and D2)
3 Activation of
3. 21 21 21 21 21 3 Activation of
3. 21 21 21 21 21
downstream BACK-UP downstream BACK-UP
zones 2, 3 and 4 (D4, D8, D8 D9 D10 D11 D12 zones 2, 3 and 4 (D4, D8, D8 D9 D10 D11 D12
D9, D10, D11 and D12) D9, D10, D11 and D12)
4 T
4. Tripping
i i order
d to
t D1 & D2 4 T
4. Tripping
i i order
d to
t D1 & D2
5. D2 = Breaker Failure 5. D2 = Breaker Failure
Fault clearance time too long, with high Fault clearance time too long, with high
6. Tripping order with remote
relays to D4,
D4 D8,
D8 D9
G risks of network instability,
instability caused by G 6. Tripping order with remote
relays to D4,
D4 D8,
D8 D9
G risks of network instability,
instability caused by G
(and D11 ?) (and D12 ?) the loss of most of interconnections. (and D11 ?) (and D12 ?) the loss of most of interconnections.
Schneider Electric - Infrastructure Business 20 Schneider Electric - Infrastructure Business 20
Fault in one feeder with breaker failure Fault in one feeder with breaker failure
21 21 21 21 21 21 21 21
50BF 50BF 50BF 50BF 50BF 50BF 50BF 50BF
D1 D2 D3 D4 D1 D2 D3 D4
D5 D6 D7 D5 D6 D7
G 21 21 21 G 21 21 21
50BF 50BF 50BF 50BF 50BF 50BF
In In
Circuit Circuit
Breaker Breaker
CB interrupting time CB interrupting time
PR reset time PR reset time
In In
Protective Protective
Relay Relay
Tripping time CBF Tripping time CBF
set in the PR (*) reset set in the PR (*) reset
time time
Breaker Breaker
Failure Failure
Device CB Fail timer Device CB Fail timer
Fault Activation Tripping order CB opened Fault Activation Tripping order CB opened
appearance off the
th CBF sendd to
t the
th CB appearance off the
th CBF sendd to
t the
th CB
(*) : includes the activation of the tripping output contact (*) : includes the activation of the tripping output contact
Schneider Electric - Infrastructure Business 22 Schneider Electric - Infrastructure Business 22
Objective Objective
Operation Principle Operation Principle
At the end of this timer, the At the end of this timer, the
corresponding threshold is not corresponding threshold is not
reached again in the negative reached again in the negative
area => The algorithm detects a area => The algorithm detects a
fault current clearance fault current clearance
13 ms 13 ms
13 ms 13 ms
13 ms 13 ms
13 ms 13 ms
Objective Objective
Operation Principle Operation Principle
Reset Conditions Reset Conditions
50 BF PProtection
t ti integrated
i t t d to
t BusBar
B B 50 BF PProtection
t ti integrated
i t t d to
t BusBar
B B
protections protections
Setting guide - Example Setting guide - Example
Central Central
Unit Back Trip Unit Back Trip
CB CB
Failure(3) Order (4) Failure(3) Order (4)
– Tbf2 – Tbf2
BB1 BB2 BB1 BB2
Trip signal Tpabc: Tripping signal from 87BB Trip signal Tpabc: Tripping signal from 87BB
Local Local
from CU & Circuit from CU & Circuit
I>BB Breaker I>BB Breaker
Optional Optional
I< & tBF1 Local Retrip I< & tBF1 Local Retrip
Setting
ggguide - Example
p Setting
ggguide - Example
p
Setting
g Guide Example
p Setting
g Guide Example
p
CB Trip CB Trip
+ 50BF + 50BF
Initiation Initiation
20ms 20ms
CB max fault CB max fault
Main clearance time Security Main clearance time Security
Protection (50ms *) margin Protection (50ms *) margin
Aux. (50ms **) Aux. (50ms **)
Contact 10ms Contact 10ms
50BF ‘’Retrip’’
‘’R t i ’’ 50BF ‘’Retrip’’
‘’R t i ’’
‘’Re trip’’ timer tBF1 (100ms) Security Margin ‘’Re trip’’ timer tBF1 (100ms) Security Margin
(130ms) (130ms)
Adjacent 50BF Adjacent 50BF
Protection – Protection –
Trip Order 50BF Back Trip Trip Order 50BF Back Trip
timer tBF2 (200ms) timer tBF2 (200ms)
Be Careful : Be Careful :
No auxiliary relays (Master Trip,…) between the Trip Order given by the Main Protection No auxiliary relays (Master Trip,…) between the Trip Order given by the Main Protection
and the 50BF Relay Initiation and the 50BF Relay Initiation
* Example : * Example :
CB Opening Time = 2 cycles + arc clearance CB Opening Time = 2 cycles + arc clearance
time = 10 ms (at 50Hz) time = 10 ms (at 50Hz)
** Example
p : ** Example
p :
The security margin includes the time to receive the CB ‘’open position’’ status ‘’ (if The security margin includes the time to receive the CB ‘’open position’’ status ‘’ (if
used) + the drop off time of the 50BF relay + a pure Security margin. used) + the drop off time of the 50BF relay + a pure Security margin.
Schneider Electric - Infrastructure Business 32 Schneider Electric - Infrastructure Business 32
Setting
g Guide Example
p Setting
g Guide Example
p
The fault is typically cleared The fault is typically cleared
after : after :
(worst case) (worst case)
* Example : * Example :
Security Margin Increased if the Security Margin Increased if the
50BF Protection directly operates 50BF Protection directly operates
the CB coil, and not through any the CB coil, and not through any
master trip contacts (auxiliary master trip contacts (auxiliary
relay) relay)
Setting
g Guide Example
p The fault is cleared by the adjacent CB,
typically after : (worst case) Setting
g Guide Example
p The fault is cleared by the adjacent CB,
typically after : (worst case)
20ms (main protection) 20ms (main protection)
[+ 10ms (auxiliary relay used for [+ 10ms (auxiliary relay used for
initiation)] initiation)]
+200ms
200ms (tBF2) +200ms
200ms (tBF2)
+ 30ms (intertrip) + 30ms (intertrip)
+ 20ms (auxiliary relay at remote end) + 20ms (auxiliary relay at remote end)
CB Trip + 50ms (Circuit Breaker) CB Trip + 50ms (Circuit Breaker)
+ 50BF = 330ms + 50BF = 330ms
Initiation Initiation
20
20ms 20
20ms
Main Main
Protection Protection
CB – max fault CB – max fault
clearance time clearance time
50BF ‘’Retrip’’ 30ms 20ms (50ms) 50BF ‘’Retrip’’ 30ms 20ms (50ms)
Re trip
‘’Re trip’’ Timer tBF1 (100ms) Re trip
‘’Re trip’’ Timer tBF1 (100ms)
Inter-trip * Inter-trip *
Adjacent 50BF Adjacent 50BF
Protection – Protection –
Trip Order 50BF Back Trip timer tBF2 (200ms) Trip Order 50BF Back Trip timer tBF2 (200ms)
Note : Note :
St ti time
Starting ti off the
th 50BF protection
t ti nott considered
id d (3 tto 5 ms d depending
di St ti time
Starting ti off the
th 50BF protection
t ti nott considered
id d (3 tto 5 ms d depending
di
on the filtering logic applied to the 50BF protection logical inputs) on the filtering logic applied to the 50BF protection logical inputs)
●Typical in UK 400kV and 275kV Networks ●Typical in UK 400kV and 275kV Networks
● For a current setting less than full load ● For a current setting less than full load
● Inhibit the BF relay during normal operating conditions ● Inhibit the BF relay during normal operating conditions
● Using Static Relays control the DC Supply ● Using Static Relays control the DC Supply
● Resistor is used to reduce switching overvoltages due to ● Resistor is used to reduce switching overvoltages due to
large inductive loads large inductive loads
● Main CB opens first, the resistor reduces the current to a low ● Main CB opens first, the resistor reduces the current to a low
level,. Aux CB is opened 1 - 2 cycles later level,. Aux CB is opened 1 - 2 cycles later
● BF relay should not remain operated by resistor current ● BF relay should not remain operated by resistor current
● Is > 2 x Ir ● Is > 2 x Ir
● The minimum fault level takes priority.
priority Timer Setting can be ● The minimum fault level takes priority.
priority Timer Setting can be
increased to compensate for resistor contact separation increased to compensate for resistor contact separation
● At least 250kV but less than 400kV ● At least 250kV but less than 400kV
●250ms ●250ms
● more than 100kV but less than 250kV ● more than 100kV but less than 250kV
●430ms ●430ms
Back Trip on Double Bus Systems Back Trip on Double Bus Systems
● Alternative for generator CB during switch off operation ● Alternative for generator CB during switch off operation
● Use of an under-voltage criteria, measured across the CB poles ● Use of an under-voltage criteria, measured across the CB poles
Revision
Re ision B Revision
Re ision B
Last Issue: May 2012 Last Issue: May 2012
Summary
y Summary
y
Schneider Electric - Energy Automation – Technical Institute 2 Schneider Electric - Energy Automation – Technical Institute 2
Stabilityy Issues and definitions Stability
y Issues and definitions
Schneider Electric - Energy Automation – Technical Institute 3 Schneider Electric - Energy Automation – Technical Institute 3
● An electrical energy network is a complex structure system, made of a ● An electrical energy network is a complex structure system, made of a
certain amount of production units, interconnected through transmission certain amount of production units, interconnected through transmission
and distribution grids and distribution grids
● This system is normally in a given equilibrium state: it is said in ● This system is normally in a given equilibrium state: it is said in
synchronous operation synchronous operation
● In particular
particular, fundamental equilibrium between production and ● In particular
particular, fundamental equilibrium between production and
consumption must be ensured in terms of : consumption must be ensured in terms of :
● ACTIVE POWER (linked to the network frequency) ● ACTIVE POWER (linked to the network frequency)
● REACTIVE POWER (linked to the network voltage map) ● REACTIVE POWER (linked to the network voltage map)
Schneider Electric - Energy Automation – Technical Institute 4 Schneider Electric - Energy Automation – Technical Institute 4
Problem: stabilityy issues Problem: stabilityy issues
An electrical network in equilibrium state, i.e. in a given An electrical network in equilibrium state, i.e. in a given
steady state, is permanently subject to disturbances of any steady state, is permanently subject to disturbances of any
kind kind
Schneider Electric - Energy Automation – Technical Institute 5 Schneider Electric - Energy Automation – Technical Institute 5
● Network parameters that can be affected (energy quality): ● Network parameters that can be affected (energy quality):
P Power P Power
U Voltage U Voltage
F Frequency F Frequency
Schneider Electric - Energy Automation – Technical Institute 6 Schneider Electric - Energy Automation – Technical Institute 6
Problem: stabilityy issues Problem: stabilityy issues
● The basic questions to be answered by network stability studies are the ● The basic questions to be answered by network stability studies are the
following: following:
●what happens during a disturbance (voltage and frequency drift, ●what happens during a disturbance (voltage and frequency drift,
protections tripping, …)? protections tripping, …)?
●what will be the new operation point after
f the disturbance has ●what will be the new operation point after
f the disturbance has
disappeared? disappeared?
Schneider Electric - Energy Automation – Technical Institute 7 Schneider Electric - Energy Automation – Technical Institute 7
●Synchronous
Synchronous operation ●Synchronous
Synchronous operation
A synchronous machine connected to other synchronous machines through A synchronous machine connected to other synchronous machines through
electrical network is said in synchronous operation with the rest of the electrical network is said in synchronous operation with the rest of the
network if its electrical speed is equal to the network’s
network s voltage frequency at network if its electrical speed is equal to the network’s
network s voltage frequency at
connection node, or to other machines’ electrical speed connection node, or to other machines’ electrical speed
An electric network is said in synchronous operation if all connected An electric network is said in synchronous operation if all connected
machines are in synchronous operation with the network and between machines are in synchronous operation with the network and between
together together
Schneider Electric - Energy Automation – Technical Institute 8 Schneider Electric - Energy Automation – Technical Institute 8
Definitions and terminology
gy Definitions and terminology
gy
●Static stability,
stability or small-signal
small signal stability ●Static stability,
stability or small-signal
small signal stability
An electric network is said in static stability conditions if, after a small An electric network is said in static stability conditions if, after a small
disturbance, it reaches a new steady state very close to initial steady state disturbance, it reaches a new steady state very close to initial steady state
A smallll di
disturbance
t b iis a di
disturbance
t b ffor which
hi h lilinearization
i ti off th
the system’s
t ’ A smallll di
disturbance
t b iis a di
disturbance
t b ffor which
hi h lilinearization
i ti off th
the system’s
t ’
equations is still justified equations is still justified
Schneider Electric - Energy Automation – Technical Institute 9 Schneider Electric - Energy Automation – Technical Institute 9
Schneider Electric - Energy Automation – Technical Institute 10 Schneider Electric - Energy Automation – Technical Institute 10
Different kinds of stabilityy Different kinds of stabilityy
ELECTRICAL NETWORKS’ STABILITY ELECTRICAL NETWORKS’ STABILITY
Ability to keep the system in equilibrium conditions Ability to keep the system in equilibrium conditions
Equilibrium between opposite forces Equilibrium between opposite forces
Transient Mid and long Large voltage Transient Mid and long Large voltage
stability terms stability disturbances stability terms stability disturbances
Large disturb.
disturb Large disturb.
disturb
Schneider Electric - Energy Automation – Technical Institute 12 Schneider Electric - Energy Automation – Technical Institute 12
Transient stabilityy Transient stabilityy
● Machine internal angle transient stability: ● Machine internal angle transient stability:
●large disturbances ●large disturbances
●fast dynamics (first aperiodical oscillations) ●fast dynamics (first aperiodical oscillations)
●typical study duration of few seconds ●typical study duration of few seconds
● Voltage
V lt transient
t i t stability
t bilit : ● Voltage
V lt transient
t i t stability
t bilit :
●large voltage disturbances ●large voltage disturbances
p , loads dynamics,
●events like operations, y , on load tap-changers,
p g , etc. p , loads dynamics,
●events like operations, y , on load tap-changers,
p g , etc.
●protections and control systems coordination ●protections and control systems coordination
Schneider Electric - Energy Automation – Technical Institute 13 Schneider Electric - Energy Automation – Technical Institute 13
Static stability
y Static stabilityy
● Concerns small disturbances, for which electric parameters variations ● Concerns small disturbances, for which electric parameters variations
are slow and continuous. Linearization of network’s model equations is are slow and continuous. Linearization of network’s model equations is
then jjustified ((in p
particular,, the time variable does not occur)) then jjustified ((in p
particular,, the time variable does not occur))
Schneider Electric - Energy Automation – Technical Institute 14 Schneider Electric - Energy Automation – Technical Institute 14
Loss of angle
g static stability
y Loss of angle
g static stability
y
t t
disturbance duration disturbance duration
Schneider Electric - Energy Automation – Technical Institute 15 Schneider Electric - Energy Automation – Technical Institute 15
Loss of angle
g static stability
y Loss of angle
g static stability
y
t t
disturbance duration disturbance duration
Schneider Electric - Energy Automation – Technical Institute 16 Schneider Electric - Energy Automation – Technical Institute 16
Conservation of angle
g static stability
y Conservation of angle
g static stability
y
● Damping and synchronizing torque coefficients are all positive ● Damping and synchronizing torque coefficients are all positive
● Internal angle is subjected to a damped oscillation and reaches a final ● Internal angle is subjected to a damped oscillation and reaches a final
value (generally different from initial value) that corresponds to a new value (generally different from initial value) that corresponds to a new
equilibrium equilibrium
t t
disturbance duration disturbance duration
Schneider Electric - Energy Automation – Technical Institute 17 Schneider Electric - Energy Automation – Technical Institute 17
Ø/E ZF = Z2 + Z0 Ø/E ZF = Z2 + Z0
Ø/Ø ZF = Z2 Ø/Ø ZF = Z2
Ø/Ø/E ZF = Z2 . Z0 Ø/Ø/E ZF = Z2 . Z0
Z2 + Z0 Z2 + Z0
3Ø ZF = 0 (short circuit) 3Ø ZF = 0 (short circuit)
Healthy ZF = (open circuit) Healthy ZF = (open circuit)
Schneider Electric - Energy Automation – Technical Institute 18 Schneider Electric - Energy Automation – Technical Institute 18
Stabilityy Limits and Theory
y Stability
y Limits and Theory
y
Schneider Electric - Energy Automation – Technical Institute 19 Schneider Electric - Energy Automation – Technical Institute 19
Schneider Electric - Energy Automation – Technical Institute 20 Schneider Electric - Energy Automation – Technical Institute 20
Generator and rotating
g fields Generator and rotating
g fields
INDUCED INDUCED
(stator) (stator)
MAGNETIC MAGNETIC
FIELD FIELD
Driving
g and resistant torques
q Driving
g and resistant torques
q
Schneider Electric - Energy Automation – Technical Institute 22 Schneider Electric - Energy Automation – Technical Institute 22
Rotating
g masses equation
q Rotating
g masses equation
q
● Acceleration or deceleration of the rotating masses is linked to the ● Acceleration or deceleration of the rotating masses is linked to the
difference between electrical torque (braking torque) and mechanical difference between electrical torque (braking torque) and mechanical
masses inertia constant J
torque (driving torque) through the rotating masses’ masses inertia constant J
torque (driving torque) through the rotating masses’
(kg.m²) (kg.m²)
Will the internal angle stabilize into a normal and Will the internal angle stabilize into a normal and
synchronous
h ti ?
operation? synchronous
h ti ?
operation?
Schneider Electric - Energy Automation – Technical Institute 23 Schneider Electric - Energy Automation – Technical Institute 23
f / P coupling
p g f / P coupling
p g
● The fundamental rotating masses equation can be written as follows: ● The fundamental rotating masses equation can be written as follows:
J · (2/p)² · (f0 + f(t)) · ∂f/∂t = Pm(t) - Pe(t) J · (2/p)² · (f0 + f(t)) · ∂f/∂t = Pm(t) - Pe(t)
the proportionality relation is linked to the group the proportionality relation is linked to the group
‘turbine+generator’ construction (inertia, ...) ‘turbine+generator’ construction (inertia, ...)
Schneider Electric - Energy Automation – Technical Institute 24 Schneider Electric - Energy Automation – Technical Institute 24
The link with internal angle
g The link with internal angle
g
Mechanical power delivered to the generator: Pm Mechanical power delivered to the generator: Pm
Electrical power delivered by the generator : Pe Electrical power delivered by the generator : Pe
Schneider Electric - Energy Automation – Technical Institute 25 Schneider Electric - Energy Automation – Technical Institute 25
Transmittable p
powers Transmittable p
powers
Schneider Electric - Energy Automation – Technical Institute 26 Schneider Electric - Energy Automation – Technical Institute 26
Apparent
pp p
power transmitted Apparent
pp p
power transmitted
G I R G I R
jXTI jXTI
ZT = RT + jXT ZT = RT + jXT
E VR RTI E VR RTI
The apparent power transmitted to infinite network (node R) is: The apparent power transmitted to infinite network (node R) is:
Schneider Electric - Energy Automation – Technical Institute 27 Schneider Electric - Energy Automation – Technical Institute 27
If the network resistance is neglected beside its reactance (RT << XT): If the network resistance is neglected beside its reactance (RT << XT):
● ZT = jXT ● ZT = jXT
● = /2 ● = /2
then the active power transmitted to the infinite network (node R) is: then the active power transmitted to the infinite network (node R) is:
E VS VL VR E VS VL VR
If instead of fix E (constant excitation), one fixes VS (voltage regulation), If instead of fix E (constant excitation), one fixes VS (voltage regulation),
then the maximal transmitted active power from S towards R becomes: then the maximal transmitted active power from S towards R becomes:
Schneider Electric - Energy Automation – Technical Institute 29 Schneider Electric - Energy Automation – Technical Institute 29
Transmittable active p
power Transmittable active p
power
G S L R G S L R
I I
Xd Xt Rt Xl Rl Xd Xt Rt Xl Rl
E VS VL VR E VS VL VR
P’’max = (VR · VL) / Xl > P’max > Pmax P’’max = (VR · VL) / Xl > P’max > Pmax
Voltage regulators action (excitation systems) allows then stable operation of the machine Voltage regulators action (excitation systems) allows then stable operation of the machine
in a zone where it is not « naturally » stable in a zone where it is not « naturally » stable
Schneider Electric - Energy Automation – Technical Institute 30 Schneider Electric - Energy Automation – Technical Institute 30
Static stability
y limit Static stability
y limit
0 0 /2
/2 ’
0 0 0 /2
/2 ’
0
Schneider Electric - Energy Automation – Technical Institute 31 Schneider Electric - Energy Automation – Technical Institute 31
Areas equality
q y theorem Areas equality
q y theorem
b final situation: Pméca = Pm1 b final situation: Pméca = Pm1
a initial situation: Pméca = Pm0 a initial situation: Pméca = Pm0
-> new equilibrium point: = 1 -> new equilibrium point: = 1
0 0 1 /2 m
/2 L 0 0 1 /2 m
/2 L
Schneider Electric - Energy Automation – Technical Institute 32 Schneider Electric - Energy Automation – Technical Institute 32
Short circuits and stabilityy Short circuits and stability
y
Schneider Electric - Energy Automation – Technical Institute 33 Schneider Electric - Energy Automation – Technical Institute 33
Short-circuit Short-circuit
Pm Pm
G G
Pe Pe
initial state initial state
PMax PMax
Pm Pm
PMax PMax
Pm Pm
e e
0 /2
/ 0 /2
/
Schneider Electric - Energy Automation – Technical Institute 34 Schneider Electric - Energy Automation – Technical Institute 34
Short-circuit Short-circuit
Pm Pm
G G
Pe Pe
occurrence of a short-circuit occurrence of a short-circuit
PMax PMax
Pm Pm
PMax PMax
Pm Pm
e e
0 /2
/ 0 /2
/
Schneider Electric - Energy Automation – Technical Institute 35 Schneider Electric - Energy Automation – Technical Institute 35
Short-circuit Short-circuit
Pm Pm
G G
Pe Pe
acceleration phase acceleration phase
PMax PMax
Pm Pm
PMax PMax
Pm Pm
e e
0 /2
/ 0 /2
/
Schneider Electric - Energy Automation – Technical Institute 36 Schneider Electric - Energy Automation – Technical Institute 36
Short-circuit Short-circuit
Pm Pm
G G
Pe Pe
line tripping line tripping
PMax PMax
Pm Pm
PMax PMax
Pm Pm
e e
0 /2
/ 0 /2
/
Schneider Electric - Energy Automation – Technical Institute 37 Schneider Electric - Energy Automation – Technical Institute 37
Short-circuit Short-circuit
Pm Pm
G G
Pe Pe
braking phase braking phase
PMax PMax
Pm Pm
PMax PMax
Pm Pm
e e
0 /2
/ 0 /2
/
Schneider Electric - Energy Automation – Technical Institute 38 Schneider Electric - Energy Automation – Technical Institute 38
Influence of the type
yp of short-circuit Influence of the type
yp of short-circuit
Pm Pm
no short-circuit no short-circuit
0 /2
/2 0 /2
/2
Schneider Electric - Energy Automation – Technical Institute 39 Schneider Electric - Energy Automation – Technical Institute 39
G G G G
Pm Pm Pm Pm
PMax
M PMax
M PMax
M PMax
M
Pm Pm Pm Pm
Schneider Electric - Energy Automation – Technical Institute 40 Schneider Electric - Energy Automation – Technical Institute 40
Influence of fault clearing
g time Influence of fault clearing
g time
G G G G
t t t t
Pm Pm Pm Pm
PMax PMax PMax PMax
Pm Pm Pm Pm
0 /2 0 /2
/ 0 /2 0 /2
/
Schneider Electric - Energy Automation – Technical Institute 42 Schneider Electric - Energy Automation – Technical Institute 42
Automatic recloser Automatic recloser
Pm Pm
G G
Pe Pe
initial state initial state
PMax PMax
Pm Pm
PMax PMax
Pm Pm
e e
0 /2
/ 0 /2
/
Schneider Electric - Energy Automation – Technical Institute 43 Schneider Electric - Energy Automation – Technical Institute 43
Pm Pm
G G
Pe Pe
short-circuit short-circuit
PMax PMax
Pm Pm
PMax PMax
Pm Pm
e e
0 /2
/ 0 /2
/
Schneider Electric - Energy Automation – Technical Institute 44 Schneider Electric - Energy Automation – Technical Institute 44
Automatic recloser Automatic recloser
Pm Pm
G G
Pe Pe
trip trip
PMax PMax
Pm Pm
PMax PMax
Pm Pm
e e
0 /2
/ 0 /2
/
Schneider Electric - Energy Automation – Technical Institute 45 Schneider Electric - Energy Automation – Technical Institute 45
Pm Pm
G G
Pe Pe
reclosing reclosing
PMax PMax
Pm Pm
PMax PMax
Pm Pm
e e
0 /2
/ 0 /2
/
Schneider Electric - Energy Automation – Technical Institute 46 Schneider Electric - Energy Automation – Technical Institute 46
Synchro-check
y Synchro-check
y
● The generator and the network are synchronous together ● The generator and the network are synchronous together
G G
Schneider Electric - Energy Automation – Technical Institute 47 Schneider Electric - Energy Automation – Technical Institute 47
Synchro-check
y Synchro-check
y
● Short-circuit: the link between the generator and the network is very ● Short-circuit: the link between the generator and the network is very
weak weak
G G
Pe increase
P i Pe decrease
P d Pe increase
P i Pe decrease
P d
=> F decrease => F increase => F decrease => F increase
Schneider Electric - Energy Automation – Technical Institute 48 Schneider Electric - Energy Automation – Technical Institute 48
Synchro-check
y Synchro-check
y
● Line opening: the generator evolves independently from the network ● Line opening: the generator evolves independently from the network
G G
Schneider Electric - Energy Automation – Technical Institute 49 Schneider Electric - Energy Automation – Technical Institute 49
Synchro-check
y Synchro-check
y
● Reclosing: it is essential to check the synchronism between generator ● Reclosing: it is essential to check the synchronism between generator
and network voltage before allowing line reclosing and network voltage before allowing line reclosing
G G
Schneider Electric - Energy Automation – Technical Institute 50 Schneider Electric - Energy Automation – Technical Institute 50
Synchro-check
y Synchro-check
y
G G
Schneider Electric - Energy Automation – Technical Institute 51 Schneider Electric - Energy Automation – Technical Institute 51
Synchro-check
y Synchro-check
y
G G
synchronism conditions not OK: wait synchronism conditions not OK: wait
Schneider Electric - Energy Automation – Technical Institute 52 Schneider Electric - Energy Automation – Technical Institute 52
Synchro-check
y Synchro-check
y
G G
Schneider Electric - Energy Automation – Technical Institute 53 Schneider Electric - Energy Automation – Technical Institute 53
Autoreclose applications
pp Autoreclose applications
pp
Schneider Electric - Energy Automation – Technical Institute 54 Schneider Electric - Energy Automation – Technical Institute 54
• Most of insulation faults need repair before re-energisation • Most of insulation faults need repair before re-energisation
• Protective relay tripping must therefore be definitive • Protective relay tripping must therefore be definitive
(Lockout with manual reset) (Lockout with manual reset)
Schneider Electric - Energy Automation – Technical Institute 55 Schneider Electric - Energy Automation – Technical Institute 55
In Over Head Line, some insulation fault due to lightning stroke will In Over Head Line, some insulation fault due to lightning stroke will
disappear after current feed interruption. disappear after current feed interruption.
Schneider Electric - Energy Automation – Technical Institute 56 Schneider Electric - Energy Automation – Technical Institute 56
1 Pole or 3 Pole Tripping ? 1 Pole or 3 Pole Tripping ?
Schneider Electric - Energy Automation – Technical Institute 57 Schneider Electric - Energy Automation – Technical Institute 57
Schneider Electric - Energy Automation – Technical Institute 58 Schneider Electric - Energy Automation – Technical Institute 58
1 pole or 3 pole tripping? 1 pole or 3 pole tripping?
Why 1 pole tripping on transmission network ? Why 1 pole tripping on transmission network ?
• 1 pole tripping maintain electrical link between power stations • 1 pole tripping maintain electrical link between power stations
which is helpful to maintain stability : which is helpful to maintain stability :
• If after a fault the 3 poles are opened, electrical link will disappear • If after a fault the 3 poles are opened, electrical link will disappear
• Most of insulation fault are 1 phase because • Most of insulation fault are 1 phase because
the large distance between phases and ground. the large distance between phases and ground.
• Power system stability requirement is above material • Power system stability requirement is above material
1 3 1 3
cost increase (Non distributed energy may cost a lot) 2
cost increase (Non distributed energy may cost a lot) 2
Schneider Electric - Energy Automation – Technical Institute 59 Schneider Electric - Energy Automation – Technical Institute 59
Therefore in transmission network single pole tripping is provided ... Therefore in transmission network single pole tripping is provided ...
Schneider Electric - Energy Automation – Technical Institute 60 Schneider Electric - Energy Automation – Technical Institute 60
Single phase tripping in HV network. Single phase tripping in HV network.
why
h ? why
h ?
•In Distribution network, the network is meshed and not directly •In Distribution network, the network is meshed and not directly
connected to power plant. No risk to loose one line connected to power plant. No risk to loose one line
•The number of single line fault is lower than in •The number of single line fault is lower than in
transmission network transmission network
•Cost reduction of primary equipment and wiring simplicity •Cost reduction of primary equipment and wiring simplicity
is more important 1 2 3 is more important 1 2 3
60 % 20 % 20 % 60 % 20 % 20 %
Schneider Electric - Energy Automation – Technical Institute 61 Schneider Electric - Energy Automation – Technical Institute 61
•The tripping mode for distribution network is therefore •The tripping mode for distribution network is therefore
always
a ays 3 pphases,
ases, always
a ays 3 pphases,
ases,
… followed by
y a three p
phase reclosing
g … followed byy a three p
phase reclosing
g
Schneider Electric - Energy Automation – Technical Institute 62 Schneider Electric - Energy Automation – Technical Institute 62
Dead time to be coordinated with : Dead time to be coordinated with :
Minimum de-energisation time Minimum de-energisation time
Circuit breaker operationg mechanism and chamber cooling Circuit breaker operationg mechanism and chamber cooling
Schneider Electric - Energy Automation – Technical Institute 63 Schneider Electric - Energy Automation – Technical Institute 63
Schneider Electric - Energy Automation – Technical Institute 64 Schneider Electric - Energy Automation – Technical Institute 64
Choice of Scheme (1)
( ) Choice of Scheme (1)
( )
High Speed Auto-Reclose High Speed Auto-Reclose
2. 3Ø A/R. 2. 3Ø A/R.
Schneider Electric - Energy Automation – Technical Institute 65 Schneider Electric - Energy Automation – Technical Institute 65
2. Power swings due to fault and tripping 2. Power swings due to fault and tripping
allowed to decay allowed to decay
Less shock to system than with high speed Less shock to system than with high speed
A/R A/R
Schneider Electric - Energy Automation – Technical Institute 66 Schneider Electric - Energy Automation – Technical Institute 66
1 Phase Auto-Reclose Factors 1 Phase Auto-Reclose Factors
R
Requiring
ii C Consideration
id ti R
Requiring
ii C Consideration
id ti
1
1. S
Separate
t control
t l off circuit
i it breaker
b k poles.
l 1
1. S
Separate
t control
t l off circuit
i it breaker
b k poles.
l
2. Protection must provide phase selection. 2. Protection must provide phase selection.
3. Mutual coupling can prolong arcing and require de- 3. Mutual coupling can prolong arcing and require de-
g time.
ionising g time.
ionising
5
5. More complex and expensive than 3Ø A/R 5
5. More complex and expensive than 3Ø A/R
Schneider Electric - Energy Automation – Technical Institute 67 Schneider Electric - Energy Automation – Technical Institute 67
High
g Speed
p Auto-Reclose ((H.S.A.R.)) ((1)) High
g Speed
p Auto-Reclose ((H.S.A.R.)) ((1))
Protection Protection
High speed < 2 cycles High speed < 2 cycles
Fast clearance at each line end. Fast clearance at each line end.
Phase comparison Phase comparison
Distance schemes with signalling Distance schemes with signalling
Distance scheme with zone 1 extension Distance scheme with zone 1 extension
Direct intertrip Direct intertrip
Schneider Electric - Energy Automation – Technical Institute 68 Schneider Electric - Energy Automation – Technical Institute 68
High
g Speed
p Auto-Reclose ((H.S.A.R.)) ((2)) High
g Speed
p Auto-Reclose ((H.S.A.R.)) ((2))
Same dead time at each line end. Same dead time at each line end.
Schneider Electric - Energy Automation – Technical Institute 69 Schneider Electric - Energy Automation – Technical Institute 69
Delayed
y Auto-Reclosing
g (D.A.R.)
( ) ((1)) Delayed
y Auto-Reclosing
g (D.A.R.)
( ) ((1))
Protection Protection
High speed not critical for system stability High speed not critical for system stability
desirable to limit fault damage desirable to limit fault damage
improves probability of successful A/R improves probability of successful A/R
Schneider Electric - Energy Automation – Technical Institute 70 Schneider Electric - Energy Automation – Technical Institute 70
Delayed
y Auto-Reclosing
g (D.A.R.)
( ) ((2)) Delayed
y Auto-Reclosing
g (D.A.R.)
( ) ((2))
Schneider Electric - Energy Automation – Technical Institute 71 Schneider Electric - Energy Automation – Technical Institute 71
● CB drive of the circuit breaker (400kV (GIS) – Example. ● CB drive of the circuit breaker (400kV (GIS) – Example.
Schneider Electric - Energy Automation – Technical Institute 72 Schneider Electric - Energy Automation – Technical Institute 72
Voltage checks in coupling Voltage checks in coupling
mode mode
Schneider Electric - Energy Automation – Technical Institute 73 Schneider Electric - Energy Automation – Technical Institute 73
Vectorial Vectorial
difference difference
Magnitude difference Magnitude difference
Angle difference Angle difference
Frequency difference Frequency difference
Frequency Frequency
Schneider Electric - Energy Automation – Technical Institute 74 Schneider Electric - Energy Automation – Technical Institute 74
7.3 Trip Circuit Supervision 7.3 Trip Circuit Supervision
Trip Circuit Supervision Trip Circuit Supervision
Issue A1 Issue A1
Last Release : March 2011 Last Release : March 2011
Schneider Electric - Energy Automation – 09/2010 2 Schneider Electric - Energy Automation – 09/2010 2
Trip Circuit Supervision Trip Circuit Supervision
operating principle operating principle
Supervision Supervision
current current
Mechanical Mechanical
Command Command
Schneider Electric - Energy Automation – 09/2010 3 Schneider Electric - Energy Automation – 09/2010 3
Disappearance Disappearance
of supervision of supervision
current current
mechanical mechanical
Tripping circuit Command Tripping circuit Command
interruption interruption
Schneider Electric - Energy Automation – 09/2010 4 Schneider Electric - Energy Automation – 09/2010 4
Trip Circuit Supervision Trip Circuit Supervision
operating principle operating principle
Alarm Alarm
mechanical mechanical
Command Command
Schneider Electric - Energy Automation – 09/2010 5 Schneider Electric - Energy Automation – 09/2010 5
Applications Applications
Schneider Electric - Energy Automation – 09/2010 6 Schneider Electric - Energy Automation – 09/2010 6
Trip Circuit Supervision Trip Circuit Supervision
Applications Applications
• Improve
I the
th security
it andd availality
il lit off th
the ttripping
i i circuit
i it b
by a • Improve
I the
th security
it andd availality
il lit off th
the ttripping
i i circuit
i it b
by a
permanent continuity control. permanent continuity control.
• In case of circuit interruption
interruption, an alarm is generated • In case of circuit interruption
interruption, an alarm is generated
• Without this control, the interrupted circuit will only be detected after a • Without this control, the interrupted circuit will only be detected after a
fault without correct clearance. fault without correct clearance.
Schneider Electric - Energy Automation – 09/2010 7 Schneider Electric - Energy Automation – 09/2010 7
Schneider Electric - Energy Automation – 09/2010 8 Schneider Electric - Energy Automation – 09/2010 8
Trip Circuit Supervision Trip Circuit Supervision
Applications Applications
• Will allow a reduction of cyclic maintenance costs • Will allow a reduction of cyclic maintenance costs
• Will allow a more important delay between real circuit breaker tests. • Will allow a more important delay between real circuit breaker tests.
These tests become only required for the mechanical part control of These tests become only required for the mechanical part control of
the CB the CB
Schneider Electric - Energy Automation – 09/2010 9 Schneider Electric - Energy Automation – 09/2010 9
Schneider Electric - Energy Automation – 09/2010 10 Schneider Electric - Energy Automation – 09/2010 10
Comparison Comparison
of different existing schemes of different existing schemes
Schneider Electric - Energy Automation – 09/2010 11 Schneider Electric - Energy Automation – 09/2010 11
Relay
elay
elay
Advantages Advantages
Re
Re
2 cables only between 2 cables only between
relay and circuit breaker relay and circuit breaker
- - - -
Disadvantages
g Disadvantages
g
Circcuit Breaker
Circcuit Breaker
Circcuit Breaker
Circcuit Breaker
No trip circuit control if No trip circuit control if
CB open CB open
2a
2a
2a
2a
52
52
52
52
Contct position Contct position
when when
equipment equipment
energised energised
Schneider Electric - Energy Automation – 09/2010 12 Schneider Electric - Energy Automation – 09/2010 12
Trip Circuit Supervision - Scheme n° 2 Trip Circuit Supervision - Scheme n° 2
+ + + +
Relay
Relay
Relay
Relay
Advantages Advantages
2 cables only between 2 cables only between
relay and circuit breaker. relay and circuit breaker.
Disadvantages
g Disadvantages
g
ker
ker
ker
ker
Circuit Break
Circuit Break
Circuit Break
Circuit Break
(1) (1)
No trip circuit control if No trip circuit control if
CB open CB open
52b
52b
52b
52b
52a
52a
52a
52a
Requires additional Requires additional
resistance into the CB resistance into the CB
Contct position control box (1) Contct position control box (1)
when when
equipment equipment
energised (1) Avoid a Battery short circuit when the CB is already open but trip energised (1) Avoid a Battery short circuit when the CB is already open but trip
order still present. order still present.
Schneider Electric - Energy Automation – 09/2010 13 Schneider Electric - Energy Automation – 09/2010 13
elay
elay
elay
Advantages Advantages
Re
Re
Re
Re
The trip coil is controlled The trip coil is controlled
whatever the CB position whatever the CB position
- - - -
Circcuit Breaker
Circcuit Breaker
Circcuit Breaker
relay and CB. relay and CB.
52b
52b
52b
52b
2a
2a
2a
2a
Tripping cable between Tripping cable between
52
52
52
52
5
5
5
5
relay and CB not relay and CB not
controlled if CB open controlled if CB open
Contct position Contct position
when when
equipment equipment
energised energised
Schneider Electric - Energy Automation – 09/2010 14 Schneider Electric - Energy Automation – 09/2010 14
Trip Circuit Supervision - Scheme n° 4 Trip Circuit Supervision - Scheme n° 4
+ + + +
Relay
Relay
Relay
Relay
Advantages Advantages
The trip coil is controlled The trip coil is controlled
whatever the CB position whatever the CB position
- - - -
(1) Al
Alarm Al
Alarm (1) Al
Alarm Al
Alarm
Disadvantages Disadvantages
ker
ker
ker
ker
Requires 3 wires between Requires 3 wires between
Circuit Break
Circuit Break
Circuit Break
Circuit Break
relay and CB. relay and CB.
52a
52a
52a
52a
Tripping cable between Tripping cable between
relay and CB not relay and CB not
controlled whatever the controlled whatever the
Contct position
CB position (1) - only the Contct position
CB position (1) - only the
when coil is controlled when coil is controlled
equipment equipment
energised (1) if interrupted, the current value becomes identical of the current circulation when CB is energised (1) if interrupted, the current value becomes identical of the current circulation when CB is
open. open.
Schneider Electric - Energy Automation – 09/2010 15 Schneider Electric - Energy Automation – 09/2010 15
elay
elay
elay
Advantages Advantages
Re
Re
Re
Re
The trip coil is controlled The trip coil is controlled
whatever the CB position whatever the CB position
- - - -
Circcuit Breaker
Circcuit Breaker
Circcuit Breaker
relay and CB. relay and CB.
2a
2a
2a
52
52
52
52
relay and CB not relay and CB not
controlled whatever the controlled whatever the
Contct position
CB position (1) - only the Contct position
CB position (1) - only the
when coil is controlled
controlled. when coil is controlled
controlled.
equipment equipment
energised energised
Schneider Electric - Energy Automation – 09/2010 16 Schneider Electric - Energy Automation – 09/2010 16
Trip Circuit Supervision - Scheme n° 6 Trip Circuit Supervision - Scheme n° 6
+ + + +
Relay
Relay
Relay
Relay
Advantages Advantages
2 cables only between 2 cables only between
relay and circuit breaker. relay and circuit breaker.
Triping contact Triping contact
CB Tripping coil CB Tripping coil
Logic Input Logic Input
controlled whatever the controlled whatever the
(O t )
(Opto) - - CB position
(O t )
(Opto) - - CB position
Alarm Alarm Tripping cable between Alarm Alarm Tripping cable between
relay and CB controlled relay and CB controlled
whatever the CB position whatever the CB position
eaker
eaker
eaker
eaker
(1) (1)
Circuit Bre
Circuit Bre
Circuit Bre
Circuit Bre
Disadvantages Disadvantages
52b
52b
52b
52b
52a
52a
52a
52a
Requires installation of Requires installation of
additional resistance into additional resistance into
the CB control box (1) the CB control box (1)
Schneider Electric - Energy Automation – 09/2010 18 Schneider Electric - Energy Automation – 09/2010 18
Typical Wiring - Requirements Typical Wiring - Requirements
● Be carefull : ● Be carefull :
● Test Circuit or secondary injection circuits must be inside the supervision ● Test Circuit or secondary injection circuits must be inside the supervision
loop loop
Schneider Electric - Energy Automation – 09/2010 19 Schneider Electric - Energy Automation – 09/2010 19
Schneider Electric - Energy Automation – 09/2010 20 Schneider Electric - Energy Automation – 09/2010 20
Trip Circuit Supervision Trip Circuit Supervision
MiCOM P123 MiCOM P123
Delay timer Delay timer
MiCOM serie 20 : MiCOM serie 20 :
P123 Only P123 Only
Opto Opto
Al
Alarm ttrip
i Al
Alarm ttrip
i
&
ET circuit faulty &
ET circuit faulty
Trip contact Trip contact
energised energised
Trip contact energised =1 if Opto does not Avoid any intempestive Trip contact energised =1 if Opto does not Avoid any intempestive
detect any current alarm in case of detect any current alarm in case of
during TSUP timer permanent trip orders. during TSUP timer permanent trip orders.
Schneider Electric - Energy Automation – 09/2010 21 Schneider Electric - Energy Automation – 09/2010 21
Trip Circuit Supervision with overcurrent Trip Circuit Supervision with overcurrent
relays - scheme 1 relays - scheme 1
+ +
elay
elay
Re
Re
- -
Circuit Breaker
Trip coil Trip coil
52a
52a
Trip coil control Trip coil control
Schneider Electric - Energy Automation – 09/2010 22 Schneider Electric - Energy Automation – 09/2010 22
Trip Circuit Supervision with overcurrent Trip Circuit Supervision with overcurrent
relays - scheme 2 relays - scheme 2
+ +
Relay
Relay
- -
Overcurrent relay Overcurrent relay
Alarme Alarme
Circuitt Breaker
Circuitt Breaker
Trip
p coil Resistance Trip
p coil Resistance
52a
52b
52a
52b
Trip coil and auxiliary contacts control Trip coil and auxiliary contacts control
Schneider Electric - Energy Automation – 09/2010 23 Schneider Electric - Energy Automation – 09/2010 23
Trip Circuit Supervision with overcurrent Trip Circuit Supervision with overcurrent
relays - scheme 6 (optimal) relays - scheme 6 (optimal)
+ +
Relay
Relay
Logical input Logical input
- -
Overcurrent relay Overcurrent relay
Alarme Alarme
Circcuit Breaker
Circcuit Breaker
Resistance Resistance
Trip coil Trip coil
52a
52b
52a
52b
5
5
Trip coil and auxiliary contacts control whatever the CB Trip coil and auxiliary contacts control whatever the CB
position position
Schneider Electric - Energy Automation – 09/2010 24 Schneider Electric - Energy Automation – 09/2010 24
Trip Circuit Supervision Trip Circuit Supervision
Practical Example with MiCOM Practical Example with MiCOM
serie 40 serie 40
Schneider Electric - Energy Automation – 09/2010 25 Schneider Electric - Energy Automation – 09/2010 25
Trip Circuit Supervision with Programmable Trip Circuit Supervision with Programmable
Scheme Logics (Px40 range relay) Scheme Logics (Px40 range relay)
+ +
Relay
Relay
- -
Alarm Alarm
Disjoncteur
Disjoncteur
D
52a
a
52a
a
52b
b
52b
b
Contact Contact
position when position when
equipment equipment
energised energised
Schneider Electric - Energy Automation – 09/2010 26 Schneider Electric - Energy Automation – 09/2010 26