SIGNATARIES DU CONTRAT
DESCRIPTION DE LA REVISION:
0 FOR APPROVAL
REMPLACE ECHELLE NUMERO SCIN
N° PCQ:
Rades‐56‐YC‐QA‐QD‐SCN‐7117
INSPECTION LEVEL
ITEM REFERENCED ACCEPTAN INSPECTION
ACTIVITY DESCRIPTION VERIFYING SCIN GAMA 3RD PARTY STEG NOTES
NO DOCUMENTS CE CRITERIA FREQUENCY
RECORD LEVEL DATE SIGN LEVEL DATE SIGN LEVEL DATE SIGN LEVEL DATE SIGN
I REVIEW OF DOCUMENTS
Project
Construction /Erection, Drawings, spec Approved
Specification Method of Statements Drawings
1.1 100% Document Control H H R
Erection
procedure
Crane
Advance Declaration and Performance FAT EOMR (End of
confirmation that factory and test Report Manufacturing
1.2 Acceptance test is successful 100% H H R
procedure Report)
SAT Procedure
Approved
Document Control
SAT Procedure
1.3 100% H H APP
N° PCQ:
Rades‐56‐YC‐QA‐QD‐SCN‐7117
INSPECTION LEVEL
ITEM REFERENCED ACCEPTAN INSPECTION
ACTIVITY DESCRIPTION VERIFYING SCIN GAMA 3RD PARTY STEG NOTES
NO DOCUMENTS CE CRITERIA FREQUENCY
RECORD LEVEL DATE SIGN LEVEL DATE SIGN LEVEL DATE SIGN LEVEL DATE SIGN
CONTROL OF
INSPECTION,ME-ASURING
II AND TEST DEVICES
/EQUIPMENT
ISO 9001:2008
2.3 Dimensional measurement Corresponding
Clause 7.6 Calibration
devices Calibration
100% Log H R R
Certificates
Corresponding
ISO 9001:2008
2.4 Electrical measurement devices Calibration
Clause 7.6 Certificates Dispatch List
(Amper meter…)
100% H W/R R
Availability
N° PCQ:
Rades‐56‐YC‐QA‐QD‐SCN‐7117
INSPECTION LEVEL
ITEM DOCUMENTS CRITERE FREQUENCE
DESCRIPTION DE L’ACTIVITE RAPPORT SCIN GAMA 3RD PARTY STEG NOTES
NO DE REFERENCE ACCEPTATION INSPECTION
LEVEL DATE SIGN LEVEL DATE SIGN LEVEL DATE SIGN LEVEL DATE SIGN
Shipment
Notice along IAPP-00-
Material Receiving
with SMC-
Inspection Dispatch List
3.1 Equipment GN-MN 100% H W/R R
Crane
Performance
4.2 Rail axis / Span Length Approved Drawings 100% H
Test Assembly Acc.Form
W W
Procedure
Crane
Dimensional Check (Beam Span,Cross Performance Assembly Acc.Form
5.1 Approved Drawings 100% H W W
Span,Rail Span) Test SM.KF-087
Procedure
Date: 10/12/2018
N° PCQ:
Rades‐56‐YC‐QA‐QD‐SCN‐7117
INSPECTION LEVEL
ITEM REFERENCED ACCEPTAN INSPECTION
ACTIVITY DESCRIPTION VERIFYING SCIN GAMA 3RD PARTY STEG NOTES
NO DOCUMENTS CE CRITERIA FREQUENCY
RECORD LEVEL DATE SIGN LEVEL DATE SIGN LEVEL DATE SIGN LEVEL DATE SIGN
VII
SITE ACCEPTANCE TEST
Crane
7.1 FUNCTIONAL TEST(Limit Performance
Assembly
Switches,Brakes,Speed Performance ) Test Project Spec. 100% H W/R W W
Acc.Form;SM.KF-087
Procedure
7.2
Load Calibration Assembly
Contract Contract 100% W H W W
Acc.Form;SM.KF-087
Crane
GENERAL PERFORMANCE TEST (Lifting Performance
7.3 Project Spec. 100% Assembly H W/R W W
Speeds,Elongation) Test
Acc.Form;SM.KF-087
Procedure
6331 HSE and SAT End of Installation
7.4 Overload Test FEM 1001-8 100% H W/R W W 2
Procedure Report (EOIR)
VIII
PRESERVATION OF CRANES
Painting Painting
8.1 Painting touch-ups 100% Written Declaration H W/R W
Procedure Procedure
IAPP-00-SMC-QA-MN- IAPP-00-SMC-QA-
8.2 Preservation of Equipment 100% Approved Drawwings H W/R W 3
KMT-026 MN-KMT-026
N° PCQ:
Rades‐56‐YC‐QA‐QD‐SCN‐7117
INSPECTION LEVEL
ITEM REFERENCED ACCEPTAN INSPECTION
ACTIVITY DESCRIPTION VERIFYING SCIN GAMA 3RD PARTY STEG NOTES
NO DOCUMENTS CE CRITERIA FREQUENCY
RECORD LEVEL DATE SIGN LEVEL DATE SIGN LEVEL DATE SIGN LEVEL DATE SIGN
NOTES
1‐Site welding is applicable only for Crane Rails.NDE Visual Examination Report
findings will be as per ISO 6520-1
2‐Document Review and Submission of Site Construction Dossier (SCD)
Along with the Photos Enclosed to Relevant Reports.
3‐Maintenance during construction period will be carried
out as per manufacturer’s recommendation and O&M
Manual
LEGENDS
R : REVIEW OF DOCUMENTS
H : HOLD POINT
I : INSPECTION
W: WITNESS POINT FORMS
S: SPOT WITNESS
APP: APPROVAL