Field Density of Soil

(Sand Replacement Method)


Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:-1 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1463 1480 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5701 5702 5701
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4174 4180 4193
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1167 1162 1148
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.830 1.859 1.807
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.649 1.660 1.643
(vii) Relative Compaction (Yd/MDD)x100 % 99.93 100.62 99.56
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:- 2 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1353 1370 1321
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5601 5602 5601
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4164 4160 4183
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1077 1082 1058
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.834 1.848 1.823
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.652 1.650 1.657
(vii) Relative Compaction (Yd/MDD)x100 % 100.14 100.02 100.43
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:-3 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:- 4 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1353 1370 1321
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5601 5602 5601
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4164 4160 4183
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1077 1082 1058
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.834 1.848 1.823
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.652 1.650 1.657
(vii) Relative Compaction (Yd/MDD)x100 % 100.14 100.02 100.43
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:- 5 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:- 6 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:-7 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:-8 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1463 1480 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5701 5702 5701
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4174 4180 4193
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1167 1162 1148
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.830 1.859 1.807
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.649 1.660 1.643
(vii) Relative Compaction (Yd/MDD)x100 % 99.93 100.62 99.56
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:- 9 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1353 1370 1321
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5601 5602 5601
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4164 4160 4183
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1077 1082 1058
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.834 1.848 1.823
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.652 1.650 1.657
(vii) Relative Compaction (Yd/MDD)x100 % 100.14 100.02 100.43
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:-10 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:- 11 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1353 1370 1321
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5601 5602 5601
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4164 4160 4183
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1077 1082 1058
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.834 1.848 1.823
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.652 1.650 1.657
(vii) Relative Compaction (Yd/MDD)x100 % 100.14 100.02 100.43
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:- 12 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:- 13 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:-14 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:- 15 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1353 1370 1321
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5601 5602 5601
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4164 4160 4183
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1077 1082 1058
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.834 1.848 1.823
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.652 1.650 1.657
(vii) Relative Compaction (Yd/MDD)x100 % 100.14 100.02 100.43
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:- 16 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:- 17 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:-18 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:-19 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1463 1480 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5701 5702 5701
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4174 4180 4193
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1167 1162 1148
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.830 1.859 1.807
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.649 1.660 1.643
(vii) Relative Compaction (Yd/MDD)x100 % 99.93 100.62 99.56
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:- 20 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1353 1370 1321
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5601 5602 5601
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4164 4160 4183
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1077 1082 1058
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.834 1.848 1.823
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.652 1.650 1.657
(vii) Relative Compaction (Yd/MDD)x100 % 100.14 100.02 100.43
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:-21 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:- 22 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1353 1370 1321
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5601 5602 5601
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4164 4160 4183
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1077 1082 1058
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.834 1.848 1.823
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.652 1.650 1.657
(vii) Relative Compaction (Yd/MDD)x100 % 100.14 100.02 100.43
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:- 23 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:- 24 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- Village Side

Thickness of Layer:-25 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- River Side

Thickness of Layer:- 1 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- River Side

Thickness of Layer:-2 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- River Side

Thickness of Layer:-3 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1463 1480 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5701 5702 5701
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4174 4180 4193
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1167 1162 1148
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.830 1.859 1.807
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.649 1.660 1.643
(vii) Relative Compaction (Yd/MDD)x100 % 99.93 100.62 99.56
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- River Side

Thickness of Layer:- 4 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1353 1370 1321
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5601 5602 5601
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4164 4160 4183
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1077 1082 1058
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.834 1.848 1.823
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.652 1.650 1.657
(vii) Relative Compaction (Yd/MDD)x100 % 100.14 100.02 100.43
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- River Side

Thickness of Layer:-5 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- River Side

Thickness of Layer:- 6 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1353 1370 1321
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5601 5602 5601
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4164 4160 4183
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1077 1082 1058
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.834 1.848 1.823
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.652 1.650 1.657
(vii) Relative Compaction (Yd/MDD)x100 % 100.14 100.02 100.43
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- River Side

Thickness of Layer:- 7 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- River Side

Thickness of Layer:- 8 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- River Side

Thickness of Layer:-9 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- River Side

Thickness of Layer:- 10 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1353 1370 1321
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5601 5602 5601
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4164 4160 4183
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1077 1082 1058
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.834 1.848 1.823
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.652 1.650 1.657
(vii) Relative Compaction (Yd/MDD)x100 % 100.14 100.02 100.43
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- River Side

Thickness of Layer:- 11 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- River Side

Thickness of Layer:- 12 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- River Side

Thickness of Layer:13 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- River Side

Thickness of Layer:-14 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1463 1480 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5701 5702 5701
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4174 4180 4193
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1167 1162 1148
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.830 1.859 1.807
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.649 1.660 1.643
(vii) Relative Compaction (Yd/MDD)x100 % 99.93 100.62 99.56
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- River Side

Thickness of Layer:- 15 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1353 1370 1321
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5601 5602 5601
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4164 4160 4183
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1077 1082 1058
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.834 1.848 1.823
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.652 1.650 1.657
(vii) Relative Compaction (Yd/MDD)x100 % 100.14 100.02 100.43
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- River Side

Thickness of Layer:-16 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- River Side

Thickness of Layer:- 17 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1353 1370 1321
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5601 5602 5601
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4164 4160 4183
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1077 1082 1058
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.834 1.848 1.823
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.652 1.650 1.657
(vii) Relative Compaction (Yd/MDD)x100 % 100.14 100.02 100.43
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- River Side

Thickness of Layer:- 18 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- River Side

Thickness of Layer:- 19 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.
Field Density of Soil
(Sand Replacement Method)
Road/Section Details:-C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

Location of Test Point:- River Side

Thickness of Layer:-20 Date of Testing:-

M.D.D. of Soil:- 1.65 O.M.C. of Soil:- 13.40


A Calibration 1 2 3
(i) Wt. of Sand in Cone in gm W2 360 360 360
(ii) Volume of Calibrating Cylinder in cc V 1177.50 1177.50 1177.50
(iii) Wt. of Sand + Cylinder before pouring in gm W1 6271 6272 6271
(iv) Wt. of Sand + Cylinder after pouring in gm W3 4192 4193 4192
Wt. of Sand filled in Calibrating Cylender in gm
(v) 1719 1719 1719
(Wa=W1-W2-W3)
(vi) Bulk Density of Sand Ys=(Wa/V) gm/cc 1.460 1.460 1.460
B Determination of Soil Density
(i) Wt. of wet Soil frome Hole in gm Ww 1453 1470 1421
(ii) Wt. of Sand + Cylinder before pouring in gm W1 5691 5692 5691
(iii) Wt. of Sand + Cylinder after pouring in gm W4 4173 4178 4190
(iv) Wt. of Sand in Hole in gm (Wb=W1-W4-W2) 1158 1154 1141
(v) Bulk Density of Soil Yb=(Ww/Wb) x Ys gm/cc 1.832 1.860 1.818
(vi) Moisture Content w in % 11 12 10
(vii) Dry Density of Soil Yd=(Yb/(1+w)) 1.650 1.660 1.653
(vii) Relative Compaction (Yd/MDD)x100 % 100.01 100.63 100.17
Note:- 1- Average of three tests per km each layer.
2- Density should not be less than 99% of proctor density.

J.E. A.E.