INSPECTION AND TEST PLAN

Date:

 Project: Al Fattan Crystal Towers Consultant: Tabanlioglu Page No: 1 of 1


Inspection
Parameter to be Inspection Control Method / Format/ Authority
Item Activity/Description Acceptance Criteria
verified Frequency Reference Records
SECL TA
Material
Reinforcement Bar Tensile Strength Every batch As per Structural Specification Mill Test Certificate MIR

Compressive strength
A As per Each Grade Mix
RCP
One Time during 2000 Coul.
Concrete Water Absorption Lab Reports Design
Trial Mix 2.5 %
Water Permeability
0.30 Ml/M2/S Approval
ISAT

Diameters & No. of Bars Each Section As per Structural Drawings Structural Drawings

Spacing Each Section ± 25mm Structural Drawings


B Reinforcement work IR
Lap Length / Anchorage
Each Section Min. 50 dia. Structural Drawings
Length

Cover Each Section Min. 2 no. Cover blocks per m2 Structural Specification

C Shuttering Material Surface Finish Each Section - Structural Specification -

MEP Fixtures Each Section - Approved Shop Drawings IR

Structural Drawings/
Dimensions Each Section ± 3mm
Specification
Structural Drawings/
D Shuttering Works Verticality Each Section ± 3mm IR
Specification

Level Each Section ± 3mm Structural Drawings

Stability Each Section Rigid Approved Shop Drawings

Surfaces Preparation
E Cleanliness Each Section Free from waste / foreign materials - -
before Concreting
INSPECTION AND TEST PLAN
Date:

 Project: Al Fattan Crystal Towers Consultant: Tabanlioglu Page No: 1 of 1


Inspection
Parameter to be Inspection Control Method / Format/ Authority
Item Activity/Description Acceptance Criteria
verified Frequency Reference Records
SECL TA
Mix Proportion (Concrete Each truck on Delivery
As per Specification Structural Specification
Grade) Arrival Order

Each truck on
Workability (Slump test) As per Approved Mix Design Structural Specification -
Arrival
F Concrete
Each truck on
Temperature Max. 32°C Structural Specification -
Arrival
Compression Strength Cube test
Each location Not less than the specified values Structural Specification
(Cube test at 7 & 28 days) results
Delivery less than 2 hours from As per Approved Method Delivery
Concrete Duration Each truck
batching time Statement Tickets

Compaction Each Section Usage of vibrator in all areas Structural Specification -


G Placing
Finish Level Each Section Uniform & ± 4mm Structural Specification -

Protection from direct Fully covered with hessian cloth and


Each Section Structural Specification -
sunlight polythene

Watering for 7 days or use of


Curing Each Section Structural Specification -
approved curing compound

LEGEND : LA - LOCAL AUTHORITY H - HOLD W- WITNESS INSPECTION S - SURVEILLANCE INSPECTION R - REVIEW A - PPROVAL