Detail Estimated sheet for Guest House (Rate as per set by Budhanilkantha Municipality 2076/77)
SN Description NO Length Breadth Height Quantity Unit Rate Amount Remarks
1 Site Clearance 1 9.50 10.50 99.75 sq.m. 30.00 2,992.50
3 Vertical Post
MS Square hollow pile (4"x4"), 4mm thick 13 3.81 11.73 580.99 Ut. Wt.= 11.73 kg/m
580.99 kg 155.09 90,105.26
4 Truss Rafter
MS Square hollow pile (3"x3"), 3.2mm thick 2 55.63 7.01 779.93 kg 155.09 120,959.75 Ut. Wt.= 7.01 kg/m
5 Purlin
MS Square hollow pile (2"x2"), 2.9mm thick 2 48.63 4.07 395.85 kg 155.09 61,392.10 Ut. Wt.= 4.07 kg/m
2 57.91 4.07 471.39 kg 155.09 73,107.47 Ut. Wt.= 4.07 kg/m
6 Concrete (1:2:4) Pole Jam 12 0.60 0.60 0.91 3.93 cu.m. 13693.50 53,831.90
10 Brick soling
For foundation 12 0.67 0.67 5.33
For rooms 1 9.67 8.00 77.33
82.67 sq.m. 980.66 81,067.89
16 12.5mm thick MPL Board False ceiling 1 8.84 7.31 64.62 sq.m. 1054.00 68,109.90
International Society for Krishna Consciousness of Nepal
Budhanilkantha, Kathmandu
01-4373790
Detail Estimated sheet for Guest House (Rate as per set by Budhanilkantha Municipality 2076/77)
17 Floor Parquetting 1 8.84 7.31 64.62
Reduction for toilet (1) 2.64 1.52 (4.01)
60.61 sq.m. 2367.00 143,458.19