Professional Documents
Culture Documents
This report has been conducted by BOCCA Consulting Ltd and has been checked against our
Quality Operating Procedures.
Issue: C1
Purpose: Tender
info@boccaconsulting.com
Tel: 01708 700 103
www.boccaconsulting.com
CONTENTS
1. INTRODUCTION
2. SCOPE OF WORKS
3. DEVELOPMENT OF ABRIDGED DESIGN INTENT INFORMATION
4. DESIGN CRITERIA
5. MECHANICAL SERVICES
6. PUBLIC HEALTH SERVICES
7. ELECTRICAL SERVICES
1. INTRODUCTION
This particular specification describes the requirements associated with the provision of Mechanical,
Electrical and Public Health services to the new residential development at Portland Drive,
Merstham, Surrey.
The descriptions included in this document describe the extent and nature of the works but do not
attempt to give a full description of the work and moreover do not absolve the contractor from his
responsibility to visit the site and make himself aware of all governing factors which may affect the
content and programme of works and method of construction.
The work undertaken by the Contractor shall comprise the development of the Detailed Design
into a confirmed coordinated and working installation package and the installation of new
Engineering Services systems as described in this document and as detailed in the specifications listed
below.
1. ME&P Drawings
2. Stockwool Architectural Drawings
3. David Dexter Structural Engineering Drawings
4. Utility Undertaker Quotes and technical requirements
5. General Specification for Electrical Services
6. General Specification for Mechanical Services
7. General Specification for Public Health Services
The tenderer shall include for developing the clients design intent information and the information
herein into a design development of the remaining items and working installation scheme and to
supply, install, test, commissioning and demonstration of the engineering services works.
2. SCOPE OF WORKS
This document provides a detailed design specification for the Mechanical, Electrical and Public
Health services installations forming part of the new redevelopment to Portland Drive, Merstham,
Surrey RH1 3JA.
The project consists of creation of 33 new residential houses, 17 new residential apartments within a
single block, landlords facilities and areas.
The Mechanical, Electrical and Public Health services installation to the development are new
throughout and shall be developed into an installation scheme by the contractor.
The works associated with the Mechanical, Electrical and Public Health services are as follows:
i. Arrangement of new gas meter positions for the new apartments, including new
gas connections to heating and hot water boilers from new meter positions in the
gas meter cupboard to the apartments.
viii. Arrangement of new Cold-water services for the new apartments and landlords
service including new meters and new boosted main service through the building.
xxi. New LV Services distribution panel and connection from UKPN service head
within Block 1.
xxii. New submain distribution services to Landlords and Apartments within Block 1.
xxix. Landlords Access Control system including entrance panels, apartments handsets
and interconnecting cabling through risers within Block 1.
The design information provided in the me&p tender documentation defines the Client design intent
requirements.
The information provided contains a Full Specification, which sets the design intent of the M, E and
PH services to be installed. It shall be incumbent upon the Contractor to develop this detailed design
into their own co-ordinated installation drawings, setting out dimensions together with all necessary
technical information necessary to facilitate the M & E and PH installations as described.
The Contractor's coordination duties shall include a review of all design intent drawings, technical
submittals of plant, setting out details, builders work details, fixing and support details, layout of
services routes, co-ordination with the building elements and between services, supply, delivery,
positioning and fixing of all equipment and materials, all labour for installation, supervision and
inspection, specialist labour and all necessary instruments and attendance for testing and
commissioning, provision of operating and maintenance manuals and record drawings and training of
Client staff.
The Contractor will be required to produce fully dimensioned working drawings and to provide
sufficient working details when requested to ensure that the designs are in line with the Specification
and the requirements of the client.
The Contractor shall submit all information for the proposed installation in a timely manner as
agreed at the post tender interviews to ensure that sufficient time is allowed for the Consultants
review and comment and prior to the commencement of the installation work. Any installation
made without prior acceptance shall be made at the Contractor's risk and shall be altered or
amended as necessary to meet (or their appointed representatives) requirements at no additional
cost to the Contract.
The Contractor's coordination shall also include all elements of the design i.e. final connection to
plant, builders work details, design of supports and fixings with due regard to any services outside
the ME and PH services scope of works, which requires support from bracketry provided by the
Contractor.
In addition to the items listed in the scope of works, the Contractor shall be required to fully co-
ordinate all the services on site defined in this and the associated specifications and drawings. In
particular, it shall be the responsibility of the Contractor to fully co-ordinate the Electrical,
Mechanical, Public Health and other services including builder's work. All items of plant shall be
technical reviewed by the design team prior to ordering by the Contractor. To assist this process
the Contractor shall submit full technical details of each plant to confirm that the specification has
been interpreted correctly.
The working drawings shall be completed in a timely fashion to accord with the overall program. A
drawing and technical submittal program shall be prepared and issued to the client team for
approval.
The following shall be used to determine loads and base duties for the purpose of selecting mechanical
services plant and equipment.
The new and existing building fabric values are to be confirmed by the contractor to suit insulation
levels necessary to achieve compliance under AD Part L1A.
4.3 Lighting
The design of the cooling system shall allow for heat gain due to artificial lighting of 15W/m2. (Based
on quantity of wall lights, picture lights, chandeliers, etc.).
The design of the comfort cooling system shall allow for heat gain due to internal equipment (e.g. TV
etc) of 15W/m2.
Infiltration Rates:
Please note infiltration rates stated above are as recommended by CIBSE in calculation of heat
losses. The contractor shall make suitable allowance with consideration given to the existing and
final build specifications.
Air Changes
The Building Services Design and selection of equipment shall be in accordance with any Acoustic
Planning Conditions provided by the clients team.
Heat output per person shall be assumed as being 80W (sensible) and 60W (latent) @ 22°C.
The following shall be used to determine loads and base duties for the purpose of selecting electrical services
plant and equipment.
BS7671 AD Part P
Code of practice for earthing BS7430
The following shall be used to determine loads and base duties for the purpose of selecting Public Health
services plant and equipment.
4.13 Drainage
Above ground soil waste and ventilating system – designed to BSEN 12056:2:200 and BS5572 sized
using the discharge unit method.
5. MECHANICAL SERVICES
General
The Contractor shall prepare working drawings and supply and install and set to work the
mechanical engineering services to the development as set out below:
Gas Services
Block 1:
Individual gas supplies shall be taken to each apartment from the SGN installed incoming main within
the ground floor gas meter cupboard.
Connections from the meters for each of the apartments shall be taken to each of the apartments
via an installation of corrugated stainless steel semi-rigid gas piping (CSST) through builders work
risers and ceiling voids as shown on the drawings. Builders work risers and gas meter rooms will be
ventilated to atmosphere - the Contractor shall, through landlords ceiling voids, install the CSST
within a polyethylene flexible sleeve which shall be ventilated at the riser and at the apartment.
The gas services shall terminate in a stop cock at the entry to each apartment, directly below the
heating boiler.
Houses:
Individual gas supplies shall be terminated into a gas meter recessed box external to each house by
SGN.
Connections from the meters into each of the houses shall be taken to each of the apartments via an
installation of yellow MDPE pipework through builders work ducts as shown on the drawings.
The gas services shall terminate in a stop cock at the entry to each apartment, directly below the
heating boiler. Gas services shall be taken to each boiler in every dwelling and to hob positions in
the houses, conducted in screwed steel pipework, terminating in a gas isolator at each position of
use.
Space heating shall be provided to each of the dwellings via an installation of wall mounted high
efficiency gas fired boilers, located, in the main, within a dedicated kitchen cupboard at high level.
As shown on the drawings, the gas-fired boilers will be either combination type units or system
boilers with connections to separate hot water generators.
The boiler shall deliver heat to wall mounted radiators within the dwellings and will produce either
heat for hot water services or hot water services direct, as described later.
A concentric flue shall manage both the combustion air to, and the gases away from each of the boilers,
in the main directly to atmosphere locally, taking the gases away in accordance with British Standards
and local authority requirements.
The heating installations shall consist of all interconnecting pipework, circulating pumps, insulation of
pipework, expansion vessels, draw off points, isolating valves etc so as to leave a complete system.
The heating pipework services shall be distributed through the dwellings in ceiling voids and within
partitions and casements to give a fully flush installation; it shall be conducted in copper of the
appropriate sizes, shall be jointed with capillary solder joints, supported at regular intervals and
insulated throughout their installation within the apartments. All pipework to be secured and fixed to
the structure.
Radiator tails shall enter the valves from behind with radiator tail covers covering the tails exits from
the partitions.
All pipework to be laid at a gradient to allow ease of drainage and venting of the system with air vents
at all high points of the system and BS2879 type drain cocks at all low points.
All pipework not within the occupied space or unheated areas shall be insulated so that the overall
efficiency shall not be less than as stated in the Domestic Heating Compliance Guide in accordance
with the Building Regulations section L1A and British Standard 5422.
To protect the system water an inline magnetic filter shall be installed to the return leg of the heating
system pipework. This unit shall be as Worcester Bosch Greenstar System Filter 22Ø; the water
system shall be dosed with a system inhibitor, such as Sentinel, post commissioning.
The main heating controls shall be provided via a hall way located thermostat, with TRVs being fitted
to each radiator (except those in the same space as the thermostat, which shall be fitted with a pair
of lockshields) providing room / zone controls.
Boilers-
Heating Controls -
Radiators -
Manufacturer: Stelrad
Model: Aqua Slimline Towel Rail in Chrome
Extract Ventilation
Extract ventilation shall be provided to each of the dwellings via a number of different systems
depending on dwelling type.
Block 1:
All fans shall be soffit mounted / recessed in the ceiling void and ducted to atmosphere using 204 x
60 or 110 x 54 PVC ductwork. Collapsible fire collars shall be installed as shown on the drawings /
to the BCO's approval / sign off.
Background Ventilators and Recirculation kitchen cooker hoods will be specified by the architect.
Relays shall be installed to allow facilitate boost control by light switches into each served space
(with exception to kitchens). These shall be free-issued by the mechanical contractor to the
electrical contractor for their installation and wiring.
Extract breakout to atmosphere shall be either Titon Hi-speed air bricks or connections to tile
grilles (as specified by the architects).
Houses:
Ventilation to the houses shall be provided by local intermittent extract fans with integral humidistat
sensors and light switch control for boost extract.
All fans shall be either wall / soffit mounted / recessed in the ceiling void and ducted to atmosphere
using 204 x 60 or 110 x 54 PVC ductwork. Collapsible fire collars shall be installed as shown on the
drawings / to the BCO's approval / sign off.
Extract Fans will be as Greenwood Airvac Samika, type and orientation as shown on the drawings.
Extract to Atmosphere Grilles, Background Ventilators and extract kitchen cooker hoods will be
specified by the architect.
All pipework systems shall be insulated and taped throughout their complete installation.
The contractor shall provide Class O Armaflex thermal insulation and identification to all domestic
hot and cold water services in accordance with the following:
Class O Armaflex pipe insulation black in colour, having a class 1 fire rating BS476: Part 7:1987 (surface
spread of flame test) and a Fire Propagation index to BS476 Pa 6 (1989) test with values of 1 less than
12 and less than 6 to comply with the Class O specification as defined in the Building Regulations
Approved Document B Appendix A para A12. Lengths to be close butted. All butt joints longitudinal
seams and joins at fittings shall be sealed with Armaflex 520 or Armaflex NONFLAM adhesive to
provide an unbroken vapour barrier. The adhesive shall be used in accordance with the published
Technical Information sheets. Apply a thin uniform layer to both surfaces to be joined, allow an “open
time” of 2-3 minutes dependent upon ambient conditions – to allow the solvents to evaporate, press
together the surfaces to be joined using firm pressure, allow to cure for 36 hours for the bond to
reach maximum strength and resistance to water vapour.
In addition, all valves and other fittings shall be insulated with purpose made sections fabricated on site
in accordance with the Armaflex Installation Manual from Armacell (latest edition) and other technical
literature. Valve covers shall fully protect flanges and bonnet with only the wheels and stem exposed
and shall be sealed with Armaflex adhesive to prevent ingress of water and water vapour.
The Contractor shall provide Class O Armaflex thermal insulation and identification to all domestic
hot and cold-water services and rainwater pipes in accordance with the following.
15 13
22 19
28 19
Pipe OD in mm Thickness of Insulation in mm
All equipment equal and approved.
All systems shall be commissioned in line with the respective standards/ manufacturers
recommendations and offered to the consultant and client team for witnessing / sign off before
handover.
General
The Contractor shall prepare working drawings and supply and install and set to work the public
health engineering services to the development as set out below:
Block 1:
Landlords Boosted Cold Water services shall be provided to Block 1via the installation of a new
cold-water storage tank and pump set located within a dedicated plantroom at ground floor level. A
new rising BCWS shall be installed from the plantroom to the central landlords riser where the
BCWS shall rise vertically to high level third floor where it shall terminate in the installation of an
hydraulic arrestor.
The new BCWS will serve the residential section of the building; new connections shall be provided
in the form of a manifold on each level for 3 or 5 no. supplies on each level with connections being
taken into each of the new residential units via Southern Water approved meters.
The new BCWS installation shall be conducted in copper and shall be thermally insulated and be
provided with neoprene inserts to brackets manufactured by Flamco or equal and approved
to achieve continuous vapour seal of the thermal insulation.
The incoming main water services from Southern Water shall be extended to the new tank set. The
BCWS tank and pump set shall have an actual capacity of 2140l; specification details are as shown on
the drawings.
The tank and pump set shall be as manufactured by KGN Pillinger, their model EV-1-8/2PH3HME09.
They have prepared a quotation for the project, reference KP41673.
The incoming BCWS to each of the apartments shall be routed and suspended through the
apartment to the heating enclosure, indicated as housing the boiler, where it shall terminate into
mains stop cock at 1500mm AFFL, suitably labelled with an engraved trafflodyte circular tag and
stainless-steel chain, marked to its use.
A mains cold water service shall also be provided to the landlords service within the block 1as
shown on the drawings. This shall consist of 2 external bib taps for irrigation and a bib tap for the
bin store wash down – these connections shall be served via a dedicated Cat 5 Booster Unit as
manufactured by KGN Pillinger, as their unit CAT5/CAB Washdown Booster Set. The Cat 5
booster unit will be located within the ground floor bin store.
Houses:
Individual water supplies shall be taken into each house form a pavement located Southern Water
meter directly outside each house.
Connections from the meters into each of the houses shall be taken to each of the apartments via an
installation of blue MDPE pipework through builders work ducts as shown on the drawings.
The water services shall terminate in a stop cock at the entry to each house, directly adjacent the
hot water heater.
Hot and Cold-water services shall be provided within the dwellings as shown on the drawings; they
shall be installed and tested in accordance with BS 6700:1997, Water Regulations and to the
satisfaction of the Statutory Water Authority.
The cold-water service from the stop cock shall then provide cold water connections to the boiler
and water using appliances and sanitary ware as shown on the drawings.
As described in the mechanical section, hot water is either provided direct, in apartments, using a
combination boiler, and in houses, a system boiler providing heat to a hot water generator.
The hot water generators shall be as Worcester Bosch, as their model Grenstore SC Cylinders.
Capacities shall be as shown on the drawings.
The hot and cold water services shall be distributed through the dwellings in ceiling voids and within
partitions / casements to give a fully flush installation. They shall be conducted in copper of the
appropriate sizes, shall be jointed with capillary solder joints, supported at regular intervals and
insulated throughout their installation within the apartments.
Servicing valves shall be provided on all connections to sanitary ware and fitments.
Stop cocks shall only be installed on the incoming cold-water mains to the dwellings. All other
isolation shall be by means of quarter turn level action ball valves with the exception of the point of
use servicing valves to the draw off points.
Thermostatic mixing valves (point of use) shall be provided to the baths to limit the maximum supply
temperature where not provided as part of the sanitary ware fitments.
The mixing valves shall carry the valve designation to TMV2. The valve shall be provided with unions
at each connector, isolating ball valves, integral strainers, check valve and flushing / test point.
During flushing the valve shall be removed and replaced with a dummy valve. Commissioning of the
valve shall be carried out in accordance with the Manufacturer’s recommendations.
The thermostatic mixing valves shall be set to 46oC to provide mixed water temperature to the
baths.
Each WWP overflow from the WC’s shall be provided with integral warning pipe, which forms part
of the siphon to the satisfaction of the Statutory Water Authority.
Double check valves shall be provided to the showers and shower bath mixers to comply with the
Water Regulations and Statutory Water Authority requirements.
The installation shall be installed and tested in accordance with the Employers Requirements BS EN
12056-2:2000 and Building Regulations.
Primary ventilated soil and waste systems shall be provided to take the foul waste water discharges
from the sanitary ware, fitments, condensate drains pressure / temperature relief lines, and air
conditioning units.
The soil vent pipes and waste vent pipes shall connect to the underground drainage as shown on the
drawings.
Anti siphon pipework shall be provided to prevent trap seal loss and noise production and shall be
routed to the soil and waste vent pipes for termination to atmosphere.
The soil and waste vent pipes within the dwellingss shall be supported by stand alone unistrut system
which shall be mechanically fixed to the floor and soffit. Pipe brackets shall not be fixed to the
partition walls or cavity walls. This support system shall be provided to provide acoustic transmittal.
The stacks shall also be acoustically insulated to comply with Part E of the Building Regulations.
The washing machine shall be provided with trapped standpipes and installed in accordance with the
Manufacturers recommendations.
The dishwasher waste shall be routed to connect directly to the sink traps via a waste hose.
For the full text for Materials and Workmanship reference shall be made to General Specification for
Public Health Services.
Materials for the new internal branch, soil, waste, anti-syphon and condense pipework shall be
unplasticised or modified unplasticised PVC to BS 4514:1983 with solvent weld cement joints
manufactured by Polypipe their 'Terrain Acoustic dB12' Range.
Proprietary intumescent fire stops shall be provided to the unplasticised or modified unplasticised
PVC pipework 50Ømm and above at each and every penetration through floor/roof construction
and compartmentation walls etc.
The unistrut pipe support system shall be manufactured by unistrut metal framing systems.
All waste fittings shall be provided with 75mm UPVC two piece tubular deep seal traps
manufactured by McAlpine Plumbing Products connected directly to the appliance and the discharge
waste pipework.
Waste non-return valves taking the discharge of condensate and pressure / temperature relief lines
from the boilers shall be manufactured by Hepworth Products Ltd – Type Hepvo.
The washing machine waste shall be a trapped stand pipe manufactured by McAlpine plumbing
products.
Automatic air admittance valves shall be manufactured by Marley Plumbing and Drainage Products.
The proprietary WC pan connectors shall be the same manufacturer as the pipework and fittings.
The proprietary intumescent fire stops shall be installed strictly in accordance with the
Manufacturer’s recommendations and shall comply with the current Building Regulations and the
Building Control Officer.
The Contractor shall test and commission the soil, waste and ventilating pipework in accordance
with BS EN 12056-2: 2000 and Section 4.2 of the Standard Specification for Public Health Services.
A magnetic water conditioner shall be provided to each of the dwellings and the landlords supply as
LifeScience WK1 unit.
info@lifescience.co.uk
A Dry Permanent rising main is to be installed to enable the Fire and Rescue service to connect to a
water supply at different levels of the building via brigade connections to BS5041.
The dry riser main shall be installed in accordance with the requirements of BS5306 Part 1 1976
(Latest Amendment).
The dry riser system will consist of a 4" galvanised pipe to BS1387 with an enclosed outlet valve
(landing valve) and hydrant tee on each floor of the building. The dry riser will have a two-way inlet
breeching valve with an integral drain valve at ground floor level, built into the front entrance
elevation. An air release valve is situated at the highest point in the riser to allow the automatic
discharge of air as the riser fills and to aid draining down.
The components of the system shall be procured through Delta Fire, equal or approved, consisting
of, but not limited to, the following:
1) Copper alloy 65mm wedge gate vale to BS 5041, Part 2 and BS 5154, with 65mm female
instantaneous hose coupling to BS 336 and loose outlet blank cap and chain.
2) Landing valve boxes, shall be manufacturedn to BS 5041, Part 4, from 2mm thick corrosion
resistant material; finishes to be as Interior designers / Architects Drawings with wired glass lockable
door (2 keys) identified on inside of glass in red letters 75mm high "FIREMAIN OUTLET - DRY
RISER". Finished in stainless steel.
3) Two way or four way inlet branching, to suit mains specified to BS 5041, Part 3, with each inlet
having a non-return valve to BS 5154, a 65mm male instantaneous hose coupling to BS 336 and
loose outlet blank cap and chain.
4) Inlet branching boxes, 2mm thick corrosion resistant metal construction to BS 5041, Part 5, with
wired glass lockable doors, (2 keys) identified on inside of glass in red letters 75mm high "FIRE
BRIGADE - DRY RISER INLET", complete with 25mm drain valves (padlocked), drain valve notices
and high point air release valves. Finished in stainless steel.
The contractor shall provide a price for fixing of the sanitary ware. Refer the architects drawings for
the appropriate schedule.
For all text for materials and workmanship reference shall be made to the General
Specification of Public Health Engineering Services.
The contractor shall provide Class O Armaflex thermal insulation and identification to all domestic
hot and cold water services in accordance with the following:
Class O Armaflex pipe insulation black in colour, having a class 1 fire rating BS476: Part 7:1987 (surface
spread of flame test) and a Fire Propagation index to BS476 Pa 6 (1989) test with values of 1 less than
12 and less than 6 to comply with the Class O specification as defined in the Building Regulations
Approved Document B Appendix A para A12. Lengths to be close butted. All butt joints longitudinal
seams and joins at fittings shall be sealed with Armaflex 520 or Armaflex NONFLAM adhesive to
provide an unbroken vapour barrier. The adhesive shall be used in accordance with the published
Technical Information sheets. Apply a thin uniform layer to both surfaces to be joined, allow an “open
time” of 2-3 minutes dependent upon ambient conditions – to allow the solvents to evaporate, press
together the surfaces to be joined using firm pressure, allow to cure for 36 hours for the bond to
reach maximum strength and resistance to water vapour.
In addition, all valves and other fittings shall be insulated with purpose made sections fabricated on site
in accordance with the Armaflex Installation Manual from Armacell (latest edition) and other technical
literature. Valve covers shall fully protect flanges and bonnet with only the wheels and stem exposed
and shall be sealed with Armaflex adhesive to prevent ingress of water and water vapour.
The Contractor shall provide Class O Armaflex thermal insulation and identification to all domestic
hot and cold water services and rainwater pipes in –accordance with the following.
15 13
22 19
28 19
Pipe OD in mm Thickness of Insulation in mm
7. ELECTRICAL SERVICES
The Contractor shall complete the abridged design and supply and install and set to work the
mechanical engineering services to the development as set out below:
LV Services
Block 1:
A new 200A TP&N Service shall be bought into Block 1 by UKPN, the local DNO.
From this service head the private works shall be installed such that the building owner / operator
can act as a BNO (Building Network Operator).
Houses:
Individual electrical supplies shall be taken into a recessed meter enclosure outside each house
where the service will terminate into a 100A BS1361 Fused cutout, ready for an energy supplier
installed meter.
Connections from the metered side of the meter into each of the houses shall be taken to each of
the houses via an installation of 25mm² 3C SWA/PVC/PVC cable through builders work ducts as
shown on the drawings.
The electrical service shall terminate in an isolator integral to the consumer unit of the house
served.
As shown on the drawings the existing UKPN Service head arrangement is to be located within a
riser cupboard at ground floor within Block 1.
The Contractor shall provide a new 200A TP&N Isolator and Ryefield type LV Services Distribution
Panel to provide a supply to the landlord and to each of the apartments. The Contractor shall
include liaison to ensure the works herein comply with the requirements of UKPN who own the
supply to the development, along with working with the respective energy suppliers and the tenants
to facilitate the meter installations.
The LV Services Distribution panels shall be to UKPN Ltd's requirements and facilitate
lockable/sealable front cover, BS88 withdrawable fuse links, and common earth bar, commonly
referred to as a Ryefield Panel.
The contractor shall install plywood meter boards and a network of 150mm square galvanised steel
trunking with all necessary slots and grommets cut ready for the positioning of meters and
termination of the un-switched fused ways and the outgoing submain service cables to each of the
apartments and the landlords.
The outgoing submain cables shall be run on tray work at high level through the common areas and
risers of the building to the apartments in the building. LV Distribution cabling shall be conducted in
XLPE/SWA/LSF cable as shown on the drawings. The supplies shall terminate within double pole
switch disconnectors integral to the Apartment Consumer Units.
The Consumer Units to dwellings shall be as MK Sentry and shall be surface mounted, insulated and
shall be replete with all necessary earth / neutral busbars, shields, and MK protection devices as
scheduled on the typical apartment drawing and developed to suit each apartment.
The landlords consumer unit shall be a Schneider Electric / Merin Gerin, metal and surface mounted
The contractor shall supply and install the complete internal lighting installation throughout the
landlords section of the building as shown on the drawings.
Emergency lighting shall be provided within the main lighting system to a NM/3 system and to meet the
requirements of BS7671 parts 1 & 7.
The complete lighting installation shall be wired from the landlords distribution board and shall be
controlled locally; there shall be key switches adjacent the distribution board for isolation purposes for
maintenance etc.
All internal lighting cabling shall be carried out in either single cored 6491X lsf cabling in trunking /
conduit or multi-core 6242Y flat insulated and LSF sheathed cables with integral core CPC (twin and
earth), run on tray work for multiple runs and the structure for single runs; in all cases, disconnection of
luminaires from the lighting circuit shall be conducted using PCR2000 roses or choc-boxes either fixed
to besa boxes on the side of the cable basket or recessed in building fabrics. All cables in / out of the roses
/ besa boxes will be grometted.
Cables shall be hidden within the building structure and fabric and run clipped to the walls and
mechanically protected by suitable sized metal capping before final finishes are applied. The complete
installation shall be flush.
Galvanised steel back boxes shall be employed throughout, fixed behind the partition face on
pattresses (no drywall self fixing/supporting boxes shall be accepted) with acoustic baffles between
rooms.
The contractor shall supply and install the complete external lighting installation throughout the
development to suit the layouts as shown on the drawings.
The complete lighting installation shall be wired from the Landlords Distribution Boards and shall be
controlled automatically via a time clock, located in a din rail enclosure below the landlords db, with a
remote photocell.
All external lighting cabling shall be carried out in XLPE/SWA/LSF cabling, buried direct with
identification tape thereover.
The contractor shall supply and install electric heating to the common areas of Block 1 which shall
consist of electric panel radiators.
The electric radiator shall be wall mounted and horizontal in its orientation, as Creda Heating - Nobo
Heating NFC4N with integral thermostat control.
The electric radiators shall be wired as single phase and neutral, radial circuit and shall be fed from the
landlords distribution board DB/LL2. Controls shall be via a time clock and contactor controlling the
operation times of the circuit.
The contractor shall supply and install an access control system to the block 1 to provide automation of
access into the building.
The system shall consist of a Apex Video Door entry System as supplied and manufactured by
ENTROTECH LTD. Contact John Cossey of ENTROTECH LTD on 01506 886230 or
johncossey@entrotec.co.uk.
The contractor shall avail themselves of ENTROTEC LTD drawing WIR/SCH 07 18/010V which details
the wiring arrangements for this system to compliment the position shown on the drawings.
The contractor shall supply and install a TV distribution system as set out on the drawings and as
specified in Sky Homes Specification 'Sky Homes Specification for a coaxial Integrated Reception System
New Build MDU' version 3.02 (or the latest edition available before setting to work) dated January
2016.
The system shall consist of all signal collectors, distribution cabling, amplifiers splitters to the main
system and all amplifier / splitters within the apartments.
The system shall allow for interactive systems therefore uplinks will be provided from the future
satellite main position within the apartment.
The signal collectors shall be roof mounted facing BSkyB satellite (SE23). The installing contractor shall
be CAI accredited and shall provided a signal test information as necessary to confirm the systems
operation.
All outlets shall be to match the outlets specified under general small power.
Picture modulators will be provided to allow CCTV signals from the access control system to be
transmitted onto the system to allow the occupiers to monitor the entrances upon receipt of a request
to enter.
New Build Individual Homes' version 2.01 (or the latest edition available before setting to work) dated
January 2003.
The system shall consist of all distribution cabling, amplifiers splitters within the houses.
The system shall allow for interactive systems therefore uplinks will be provided from the future
satellite main position within the house.
The future signal collector position shall be roof mounted facing BSkyB satellite (SE23). The installing
contractor shall be CAI accredited and shall provide a signal test information as necessary to confirm
the systems operation.
All outlets shall be to match the outlets specified under general small power.
Small power shall be provided throughout the dwellings to supply power to general purpose small
power outlets, mechanical services installations, and kitchen appliances, which shall be controlled in a
grid switch manner.
Small power within the dwellings shall consist of recessed wall 13A rated, three pin DP switched and
shuttered with dual earth terminals, 1 or 2 gang socket outlets and switched or non switched fused
connection units with or without neon indicators complying with BS1363.
All internal small power cabling shall be carried out in multi-core 6242Y flat insulated and sheathed
cables with integral core CPC (twin and earth). Cables shall be hidden within the building structure
and fabric; the complete installation shall be flush.
Galvanised steel back boxes shall be employed throughout, fixed behind the partition face on
pattresses (no drywall self fixing/supporting boxes shall be accepted) with acoustic baffles between
rooms.
The contractor shall supply and install the complete internal lighting installation throughout the
apartments to suit the layouts as shown on the drawings.
Pattresses shall be provided behind all switch ways and recessed lights. Galvanised steel back boxes shall
be employed throughout, fixed behind the partition face on pattresses (no drywall self fixing/supporting
boxes shall be accepted) with acoustic baffles between rooms.
Click in connectors shall be provided for every lighting connection as 'Click Flow' 16A Push in
Connectors to allow ease of disconnection for servicing and for isolation of control gear/lamps etc
during insulation resistance testing.
All internal lighting cabling shall be carried out in multi-core 6242Y flat insulated and sheathed cables
with integral core CPC (twin and earth).
Cables shall be hidden within the building structure and fabric. The complete installation shall be flush.
The contractor shall supply and install in the scheduled locations a "dual fuel" towel rail, consisting of
the towel rail, electric heating element and all associated plumbing, work, etc.
The contractor shall carry out the complete electrical works associated with these items, consisting
of fused connection unit, flex outlet, together with protective devices, cables and cable containment
etc as deemed necessary so as to tender the installation a whole operative.
Each towel rail shall be wired a single phase and neutral radial circuit.
The supply shall consist of a flush, wall-mounted, switched fused connection unit, (fused at 13A) with
neon located outside the bathroom/WC in a subtle hidden location. The fused connection unit shall
be engraved with the words "TOWEL RAIL".
Final connection to each towel rail shall be made using a flush wall mounted, flex outlet located directly
below the bottom to the towel rail leg.
Final connection wiring between flex outlet and the tower rail shall be carried out using three core
(CU), UK (CMA) reference: 318TQ, heat resistant flexible cable with integral CPC.
3 pole fan isolators shall be installed for al intermittent extract fans in houses, and 13A SFCU’s for all
CMVEs in apartments.
Relays shall be installed to allow facilitate boost control by light switches into each served space
(with exception to kitchens). These shall be free-issued by the mechanical contractor to the
electrical contractor for their installation and wiring.
The contractor shall supply and installed mains powered fire detection and alarm system as shown on
the drawings. Equipment shall be as manufactured by messr's Aico.
Aico Ltd
Mile End Business Park
Maesbury Road
Oswestry
Shropshire
SY10 8NN
Tel: 01691 664100
Fax: 01691 664111
e-mail: enquiries@aico.co.uk
Alarm Power
/Back-up: Mains Powered with Lithium Back-up (Grade D)
Alarms are powered from the mains power supply but will automatically
switch to Lithium cell back-up if the mains power fails. The Lithium cells will
last the life of the alarm (10yrs) and are completely tamperproof.
Alarm
Interconnection: Hard-wired Interconnection
Cabling is installed between every alarm to provide the link between them. If
an alarm is triggered, it will send a signal down this cabling and all other
alarms will sound. Consideration should be taken on the disruption
generated when installing the cabling.
Alarm Controller
The contractor shall supply, install and liaise with BT and Virgin Media to provide a complete Comm
/ Telephony system within the building.
The groundworks contractor, through the CMs management, will install all of the sitewide duct etc,
and the electrical contractor the private side of the wiring installation, along with coordinating their
works with the BT representative. The same applies for Virgin Media.
BT:
BT will be delivering ‘Fibre to Premises (FTTP) product’ to the development. This will include all site
wide services, duct infrastructure and installations to Houses and Apartments. The electrical
contractor will be responsible for the following works:
Block 1:
From the BT installed Incoming Fibre Joint box within the ground floor riser cupboard, run BT free
issued ‘EZ bend Cable’ to each apartment, terminating into a ONT position within the apartment.
From the Optical termination Position (ONT) position within the main space (shown as BT ONT on
the drawings) the electrical contractor install the ONT and associated Battery back-up unit (BBU)
and provide all associated cable containers, back boxes and outlet plates as required. The electrical
contractor will also run all necessary data cables etc to slave positions as shown on the drawings.
Cableways for the main routes through the landlords risers are shown on the drawings.
Houses:
From the External BT CSP position, run a connectorised fibre cable (free issued by BT to suit the
lengths advised by the electrical contractor) to the Optical termination Position (ONT) position
within the main space (shown as BT ONT on the drawings) and install the ONT and associated
Battery back up unit (BBU) and provide all associated cable containers, back boxes and outlet plates
as required. The electrical contractor will also run all necessary data cables etc to slave positions as
shown on the drawings.
The complete specification is outlined in ‘How to build a fibre Network developer Guide Version 4
– March 2017’ and can be found here:
http://www.ournetwork.openreach.co.uk/resources/site1/General/Downloads/fibre_developer_hand
book.pdf
The electrical contractor shall coordinate the installation of copper PSTN line from the BT installed
master to the lift communication equipment.
Virgin Media:
Virgin Media will be delivering services to the development. This will include all site wide services,
duct infrastructure and installations to Houses and Apartments. The electrical contractor will be
responsible for the following works:
Block 1:
From the Virgin Media installed Incoming Distribution Box located within the ground floor riser
cupboard, run Virgin Media free issued ‘Siamese RG6’ cabling to each apartment, terminating into an
Internal Termination Box (ITB) position within the apartment, along with all Virgin Master Outlets in
the hallway cupboard and slave positions adjacent BT positions, conducted in 2c telephone cables
(procured by Electrical Contractor), and Virgin TV outlets adjacent BT positions, conducted in RG6
coax cable (supplied free by VM).
Cableways for the main routes through the landlords risers are shown on the drawings.
Houses:
From the External Virgin Media External Termination Box (ETB) located on the front of the houses,
run Virgin Media free issued RG6 coax cabling to a Virgin Master Outlets in the main master and
slave positions adjacent BT positions, conducted in 2c telephone cables (procured by Electrical
Contractor), and blank plate covered single gang boxes, ready for Virgin TV outlets, adjacent TV
positions, conducted in RG6 coax cable (supplied free by VM).
The complete specification is outlined in ‘Virgin Media Residential New Build Technical Information
to support your on-site deployment’ and can be found here:
https://keepup.virginmedia.com/content/networkExpansion/doc/virgin_media_new_build_developers
_guide_v1.4.pdf
The contractor shall supply and install a single zone AOV Control Unit and all associated devices as
shown on the drawings. The system shall be wired in FP200 fire resistant cabling.
The system shall be designed in compliance with the European standard EN:12101 and as
manufactured by:
AOV Controls
Custom Electronics Ltd
Unit 4,
Willows Business Centre,
Earthing Installations
The contractor will provide an earthing system comprising of main earthing terminal or bar, circuit
protective conductors, main equipotential bonding conductors and supplementary bonding for
earthing the electrical installation, the general mass of the building and incoming services to the
general mass of the earth.
The installation shall be in accordance with BS 7671, BS 7430 and the Regional Electricity Company's
(REC) requirement for protected multiple earth (PME).
The Electrical Services Contractor shall make all necessary tests both as the installation proceeds
and on completion, to ensure the effectiveness of the earthing installation and its compliance with BS
7671.
In no circumstances are fixings, which are being used for other purposes, to be utilised for an
earthing termination. If an earthing terminal is not provided on the apparatus, the Electrical Services
Contractor shall form an effective earthing terminal by drilling, tapping and installing the necessary
nuts, bolts and washers. All protective conductors shall be connected to earthing terminals by means
of crimped lugs.
Earthing conductors shall have a Green/Yellow sheath. Circuit Protective Conductors (CPC's) -
Shall have LSF insulation with a minimum cross-sectional area detailed in table 54G of BS 7671.
Cable Armouring - May be used as a CPC. Where the armouring has an insufficient CSA, provide an
additional single-core (Cu), CPC cable strapped to the outside of the appropriate armoured cable
using proprietary cable ties.
Conduit and/or trunking - Shall not be used as a protective conductor or earth path. However,
conduit/ trunking shall be fully bonded.
Circuit protective conductor installation shall form a continuous earth fault return path.
A protective conductor within a non-metallic cable containment system shall terminate on each
outlet box. For a final ring circuit, the circuit protective conductor shall be run in the form of a ring
having both ends connected to the associated earth bar or terminal.
All outlet boxes shall incorporate an earthing terminal and a green/yellow LSF conductor, equal in
size to the circuit conductor and shall connect this terminal to its associated accessory.
For all text for materials and workmanship reference shall be made to the General
Specification of Electrical Engineering Services.