Professional Documents
Culture Documents
No part of this publication may be reproduced by any means without prior written permission from the Secretary General, IRC.
The responsibility of the contents and the opinions expressed in Journal of the Indian Roads Congress is exclusively of the author(s) concerned. IRC and the
Editor disclaim responsibility and liability for any statements or opinion, originality of contents and of any copyright violations by the authors. The opinion
expressed in the papers and contents published in the Journal of the Indian Roads Congress do not necessarily represent the views of the Editor or IRC.
Printed at: M/s India Offset Press, New Delhi-110 064 `20
(All Rights Reserved. No part of this Publication shall be reproduced, translated or
transmitted in any from or by any means without the permission of the
Indian Roads Congress)
ABSTRACT
Road accidents and associated fatalities in India have risen over the years and has reached a condition
where approximately 17 lives are lost in an hour. Accident statistics identified driver's fault as the major
contributor towards accidents on Indian roads. This study checks whether driver behaviour could feature
as the main reason behind accidents at unsignalized intersections in India. A comparison is drawn between
critical gaps on the basis of data collected at unsignalized intersections from India and USA. Maximum
likelihood method was used in the estimation of critical gaps. Critical gaps of cars at an intersection in
India were compared with those of a similar intersection in USA and with the values given in Highway
Capacity Manual (HCM). Further, critical gaps for motorized two-wheelers were also estimated. It was
found that at intersections of similar geometry, critical gap of cars for various movements in India were
much less than in USA and this difference was in the range of 20-31%. Critical gaps of cars executing
different movements at Indian intersections were consistently lower (up to 57%) than the base values
given in HCM. Motorized two-wheelers, which were involved in majority of accidents at intersections,
had even lesser critical gaps than cars. Lesser critical gap of Indian drivers in comparison to their
western counterparts indicates their aggressive and risk taking behaviour, which often leads to road
accidents. Thus, it is not very surprising to have drivers’ fault as the major reason for accidents in Indian
intersections.
associated drivers fault as the main reason behind in India unsafe for traffic operations. As shown in
these accidents1. The current research is an attempt Fig. 1, unsignalized intersections have contributed to
to understand the behavioural aspects involved in the 79% of the total accidents that occurred at intersections
traffic operation at unsignalized intersections and their during 20151.
potential towards the occurrence of accidents.
2. ACCIDENT SCENARIO IN INDIA
Being a signatory of the Brasilia declaration, India
had pledged to reduce the number of road accidents
and fatalities by 50% by the year 2020. However,
the recent road accident statistics1 revealed a 2.5%
increase in the number of accidents from 2014 to 2015,
with 4.6% increase in the number of accident fatalities
and 1.4% increase in number of injured. Number of
accidents related fatalities reported in 2015 rose to
an alarming figure of 17 fatalities per hour. Drivers’
fault was claimed to contribute towards majority of
accidents (77.1 %) that occurred on Indian roads and
Fig. 1. Accidents at Indian Intersections Based on
62.2% of these resulted from over-speeding. Fault of Type of Control
drivers towards accidents is further supported by the
fact that adverse weather conditions has only led to 3. CRITICAL GAP
32.3% of the total accidents. Traffic operations at a TWSC intersection occur
Based on the comparison provided by NHSTA2, many through gap acceptance process and a vehicle in the
developed countries including USA are placed higher non-priority stream should wait for suitable gaps
when it comes to the number of persons killed per in the major traffic stream to complete the desired
100,000 population. According to this report, there manoeuvre. Gap is the time interval between two
has been a continuous reduction in fatalities related successive vehicles measured from the rear end of the
to road accidents in USA from 2006. In 2014, the leader to the front end of the follower across a line
number of accident fatalities reported in USA was of reference. The minimum gap between consecutive
32,675, which was 0.7% less than the previous year. vehicles in the major traffic stream which is acceptable
Fatalities per 100,000 population was 10 in US as to a minor street driver is termed as the critical gap.
against 11 in India3. This parameter is found to be dependent on the speed
In India, about 49% of the total accidents on Indian of major street traffic, time of the day, intersection
roads occurred at intersections (1) where different geometry, gradient of approach, type of subject
traffic streams compete for the same road space. While movement and delay5, 6, while it is independent of
the access to the conflict area is cyclically allocated the flow in conflicting streams7, 8. Normally, a driver
through traffic signals at signalized intersections, would reject all gaps which are less than the critical
unsignalized intersections operate through a set of gap and will accept the rest.
priorities assigned to different movements. Due to Since critical gap is a parameter which cannot be
loose regulatory system, priority rules are not strictly measured in the field, researchers have employed
followed on Indian roads and right of way is allocated different techniques to ascertain the mean critical
through mutual consent. Movements of higher gap of drivers executing a particular movement at a
priority are often forced to slow down and headways TWSC intersection. The list of techniques employed
between major street vehicles are often modified due to arrive at critical gap value dates back to the 50’s
to the forceful entry of minor street vehicles4. The when Raff9 introduced the concept of critical lags.
lack of movement priorities and failure of drivers to Over the years, methods based on different theoretical
abide by the rules has made unsignalized intersection considerations were proposed by researchers with the
Table 3 shows the comparison of critical gaps of cars at intersections. Except for the correction to intersection
different intersections against the base value of critical geometry, all adjustments to base value of critical
gap given in HCM12. The percentage differences in the gap provided in HCM are positive and hence these
value of critical gap from HCM are given in parentheses. differences might increase further while considering
The mean critical gaps for different movements are much the final critical gap. This comparison provides further
lower than those given in HCM at all of the selected evidence for aggressiveness of Indian drivers.
Table 3. Comparison of Critical Gaps for Cars in India and US
At 4-legged intersections (Intersection 2 and 5), critical Table 4. Critical Gap of Motorized Two-wheelers at
gap of through movement was higher than that of right Selected Intersection
turn from minor indicating that through movements
had the least priority at Indian intersections. Field Critical gap (s)
observations also showed the same as through
movements were found to be comparatively difficult Location Right Right
Through
Turn from Turn from
to execute than right turn from minor. Critical gap for on Minor
Major Minor
motorized two-wheelers were found to be still lower
than those given in Table 3. Aggressive nature of two-
Intersection-2 3.29 3.38 4.36
wheelers at unsignalized intersections in India was
observed by other researchers also16. Critical gap of Intersection-3 2.71 2.97 -
two-wheelers executing various movements at the
selected intersections are given in Table 4. Smaller Intersection-4 2.23 3.14 -
size and better acceleration capability enable these
drivers to accept smaller gaps, but quite often put Intersection-5 2.32 2.68 2.78
them at the verge of accidents.
ABSTRACT/SYNOPSIS
Mortality and morbidity resulting from road traffic accidents is regarded as a major and pervasive public
health problem worldwide. In India itself, 413 precious lives are lost in road accidents every day, which amounts
to 3% of the GDP. On hilly and high rainfall regions lack of skid resistance and visibility forms a major cause
for road accidents. To mitigate such accidents it is highly desired to improve the drainability, skid resistance
and visibility while driving a motor vehicle. Open Graded Friction Courses (OGFCs) are a special type of
bituminous surfacings designed for high air void contents for quick drainage of rainwater, high skid resistance
and improved visibility, especially under wet weather conditions. Additional benefits offered by OGFCs
include: reduced potential for hydroplaning, reduced splash/spray, improved visibility of pavement markings,
reduced glare and pavement noise. This paper discusses in detail the different design and performance related
aspects of OGFC to acquaint the highway professionals of the country with this technology. The benefits
offered by OGFC, mix design, performance, construction practices, and worldwide applications are discussed
and imperatives are provided for its use towards enhancing the road safety in hilly and high rainfall regions
of the country. Paper also discusses the common challenges associated with OGFCs. To improve road safety in
heavy rainfall and hilly regions it is high time for India to gain experience with OGFC through construction
and monitoring of sections. Experience gained from field sections will provide an excellent opportunity to
formulate, and then continually refine and upgrade OGFC specifications and guidelines for India.
deaths in the country (MoRTH, 2016). Wet weather applications of OGFC are discussed and imperatives
conditions result in the lack of skid resistance and lack are provided for its use towards improving the road
of visibility, and significantly influence the occurrence safety aspects in hilly regions of the country prone
of road accidents (Singh, 2017). The problem is to heavy rainfall.
especially relevant in hilly regions where sharp curves
3. DESIGN OF OGFC MIXES
and steep gradients are a common road feature. Lack
of skid resistance on these curves is a major cause of Similar to other bituminous mixes, the selection of
road accidents. appropriate materials (aggregates, binders, additives)
and proportioning of individual components is the
In the situations discussed above, it is notable that the
key to high performance and service life of OGFC
accumulation of rainwater on the pavement surface
mixes. The OGFC mix design involves four main
causes the skid resistance to decrease, and further
steps:
compromises driver’s visibility due to presence of
1. Selection of Materials
water film and splash and spray of water by vehicles.
It is highly important to prevent accumulation of 2. Selection of Aggregate Gradation
water on the pavement surface in order to mitigate 3. Determination of Optimum Binder Content
such accidents. This can be achieved by adopting 4. Mixture Performance Evaluation
special types of pavement surfacings that offer high 3.1 Selection of Materials
permeability and subsequent quick drainage of water.
Materials needed for OGFC mix include aggregates
Making the pavement permeable is a novel and a non-
(coarse, fine, filler), asphalt binder, and stabilising
conventional paradigm from the traditional concept of
additives (fibres). Since OGFC is used as a wearing
having a waterproof pavement surface. Open Graded
course on high-speed high-trafficked facilities, it is
Friction Courses (OGFCs) are a particular type of Hot
desirable that the aggregates are angular and should
Mix Asphalt (HMA) mixes that contain only a small
possess high resistance to abrasion, crushing, and
portion of fine aggregate, creating a pavement with a
polishing. The aggregate should have at least 95
relatively large percentage of air voids. The presence
percent one-fractured face and 90 percent two-
of the larger percentage of internal air voids provides
fractured face. Fractured faces ensure high internal
OGFC a relatively high porous structure which helps
friction between the aggregates. Flaky and elongated
in quick and effective removal of surface water from
particles are also generally limited to 10 percent and
the pavement (Kandhal and Mallick, 1998; Kandhal,
20 percent corresponding to the maximum to minimum
2002; Alvarez et al., 2011; Choudhary et al., 2017).
dimension ratios of 5:1 and 3:1, respectively. Note
It improves drainage by allowing water to drain
that the ratio of 3:1 is commonly used in India. Fine
vertically into the porous layer and then flow laterally
aggregate should have a low clay content or high sand-
within the porous layer until it exits the pavement
equivalent value of more than 45 percent. It is also
through a daylighted edge. The absence of water
quite common to use hydrated lime to impart strong
from the surface in wet weather conditions increases
resistance against water damage (stripping).
the skid resistance and reduces splash and spray. The
presence of the air voids also help in absorbing the A minimum binder content is needed to ensure
noise generated from the tire-pavement interaction thick film over the aggregates to reduce aging,
and leads to quieter pavements. As a wearing course, disintegration, stripping, and ravelling. An upper
a thin layer of OGFC (20 to 50 mm) is generally limit on binder content assures a minimum air
placed over a conventional impermeable pavement void content, reduces tyre-pavement noise, and
surface. inhibits binder runoff (draindown) during mixing,
transportation and laying of the mix. To meet these
2. RESEARCH OBJECTIVE requirements, research and experience has shown
The objective of this paper is to present a general that the unmodified binders may not be suitable for
overview of OGFCs to acquaint the highway OGFC mixes. The general tendency in recent years
professionals of the country with this technology. has been to use modified binders. It is believed
The mix design, performance, construction that modified binders increase the life of OGFC by
practices, advantages offered and worldwide improving the cohesion and adhesion of the mixes
and by forming thicker films around the aggregates Gmb = bulk density of compacted OGFC mix;
that controls draindown and embrittlement due to PCA = proportion of coarse aggregate in the mix
aging. In comparison to typical asphalt film thickness (percent). Different trial aggregate gradations (gap-
of 4-6 micron achieved in dense-graded mixtures, an graded) are selected and evaluated for stone-on-stone
OGFC requires 8-11 micron asphalt film thickness on contact criterion. Finally selected gradation should
an average (FHWA, 1990). Binders recommended for meet the stone-on-stone criterion and provide high
OGFC are two performance grades stiffer than the air voids. Various agencies have prescribed different
ones normally used under a given environment and gradation bands for OGFC mixes. Table 1 shows
traffic condition (Kandhal, 2002). recommended gradation bands by some agencies.
Certain inorganic and organic fibre additives are also Fig. 1 shows the OGFC gradation recommended by
added in the attempt to control binder draindown. ASTM D7064.
For example, cellulose fibres (a type of organic fibre)
3.3 Determination of Optimum Binder Content
derived from paper reduce binder drain down by
(OBC)
absorbing and stiffening the binder. The non-fibre
components of the cellulose fibre act as additional OGFC mixes are prepared with the selected
filler and further obviate the drainage of binder from aggregate gradation at four to five binder contents in
the mix. Fibres are typically used in proportions of increments of 0.5 percent. Uncompacted specimens
0.2–0.5 percent by weight of the mix with 0.3 percent are also subjected to binder draindown test and
being the most common dosage. theoretical maximum specific gravity determination.
3.2 Selection of Aggregate Gradation For compacted specimens, a compaction effort of
50 gyrations or 50 blows of Marshall compactor on
OGFC gradations are predominantly gap-graded
each face is usually used. The compacted specimens
(single particle sized) to allow for higher percentages
are then subjected and evaluated for bulk density,
of air voids by eliminating the fine material. Selection
abrasion loss in unaged and aged conditions, and
of aggregate gradation for OGFC mix is based on
fulfilment of stone-on-stone criterion. The criterion permeability. The OBC is selected based on the
ensures that the traffic loads are borne by the coarse outcomes of the results of these tests. Each of the
granular skeleton through their interconnected contact test methods is discussed briefly in the following
points to provide resistance against permanent sections.
deformation and disintegration. The stone-on-stone
requirement is met when voids in coarse aggregate
(defined as the fraction retained on 4.75 mm sieve)
in compacted OGFC mix (referred as VCAmix) are
less than voids in the coarse aggregates found by dry
rodded test (referred as VCAdrc). Dry rodded test is
conducted on coarse aggregates as per AASHTO T19
to determine the dry rodded density. The VCAdrc is
then calculated using Eq. (1):
(1)
[ ] (2)
Fig. 1 Recommended OGFC gradation (ASTM D7064)
Binder draindown test: The test consists of placing a Gmb of OGFC specimens using the water-displacement
loose mix in a wire basket over a plate of known weight. method is not suitable as it is difficult to correctly
This assembly is then placed in a forced air draft oven determine the saturated surface dry weight. The vacuum
for 1 hour at 15 °C above the mixing temperature. After 1 method or dimensional analysis are the alternative
hour, the weight of assembly is measured. Draindown is methods recommended for calculating the Gmb. A
calculated (in percent) from the ratio of weight of drained minimum requirement of air voids in the range of 15 to
material to the weight of original material. ASTM D6390 25 percent is followed in different countries.
specifies the procedure for performing the draindown Durability evaluation using Cantabro abrasion test:
test on an uncompacted OGFC specimen. Fig. 2 shows The test is conducted on a compacted OGFC specimen by
an OGFC binder draindown test under progress. subjecting it to abrasion testing in Los Angeles machine
Air voids content: Bulk density of the compacted OGFC without the charge of steel balls where it is rotated
specimen (Gmb) and theoretical maximum specific gravity different number of revolutions (usually 300) at a rate of
(Gmm) are the two inputs required to compute the air void 30–33 rpm. Abraded specimen is then removed, cleaned
content (Eq. 3): and weighed. The difference (loss) in the weights is then
Gmm Gmb used to calculate percent abrasion loss. High air void
Air Voids (%) x 100 (3) content makes OGFC vulnerable to increased aging that
Gmm
may lead to ravelling. To determine the effect of ageing
test is then performed on aged OGFC specimens also.
Hence in OGFC mix design, the durability is evaluated
after subjecting the specimens to an accelerated aging
protocol. The accelerated aging procedure usually
consists of placing the specimens at 60°C for 7 days in a
forced air-draft oven. Cantabro test is then performed on
these aged specimens at ambient temperatures (usually
25°C). Fig. 3 shows an OGFC specimen before and after
Cantabro abrasion test.
Permeability test: Some specifications place
permeability as an optional test in OGFC mix design
to evaluate the functional performance of OGFC
related to its drainability. Falling head concept based
on Darcy’s Law is generally used for determination of
Fig. 2 OGFC Binder Draindown Test the one-dimensional hydraulic conductivity coefficient
Gmm is computed as per the guidelines of ASTM D2041 (or permeability) on saturated OGFC specimens. A
(Rice specific gravity procedure) or using ASTM D6752 minimum requirement of permeability for these mixes
(automatic vacuum sealing method). Determination of is 100 m/day.
the tire and road. When this occurs, the vehicle will not Reduction in tyre noise makes driving more pleasant and
respond to braking or steering by the driver and this may less tiring (Nicholls, 1998). The noise reduction relative
be extremely hazardous. As OGFC surface provides to dense bituminous mixes is generally of the order of 3
adequate drainage through interconnected air voids, no dBA (dry conditions) to 8 dBA (wet conditions), where
continuous film of water is available to break the bond 4 dBA reduction in noise level is comparable to a 50
between the tire and pavement surface. Additionally, the percent reduction in noise pollution as the decibel scale
higher macrotexture provided at the pavement surface by is logarithmic. OGFC is accepted as the most effective
OGFC layers creates small channels for dissipation of noise reducing road surfacing (Nicholls, 1998).
water as vehicles pass over the pavement. Fig. 6 shows
6. OGFC IMPLEMENTATION IN THE WORLD
the formation of ‘sheet’ of water on a dense-graded
surface during a rainfall event. On carriageways without OGFCs have been in the use since the 1950s (Kandhal,
a median (common feature in hilly regions), the situation 2002; Lavin, 2003) as surface layers in countries like the
causes headlight glare at night. US, Japan, the UK, Malaysia, Australia, South Africa,
Europe, and New Zealand (Qureshi et al., 2015). Various
US states (such as Oregon, Washington, California,
Nevada, Arizona, Florida, etc.) have been using OGFC
since the 1970s for its excellent performance for safety,
drainage, and durability. The Netherlands started to use
OGFCs in the early 1980s, and by 1990 more than 80
percent of their road network was paved with OGFC. It
has also been the preferred choice for airport pavements
in Switzerland since 1972 (Qureshi et al., 2015). In the
UK, the main reason for widespread use of OGFC was to
prevent hydroplaning on airfield runways and to reduce
traffic noise on roadways. Austria promoted the use of
Fig. 6 Presence of a ‘Sheet’ of Water in Wet Weather
OGFC to reduce the disturbances caused by traffic noise
Condition in areas where residential spaces lay in proximity to the
main highways. OGFC usage in France and Italy has
5.6 Increased Road Safety proved to be highly durable on heavily trafficked road
Use of OGFC enhances safety on highways through sections. Recycling of OGFCs has also been successfully
aforementioned advantages of improved wet-weather attempted, as reported in studies from Italy and the
skid resistance, reduction in glare, and reduction in Netherlands (Nicholls, 1998). OGFC is used on either a
hydroplaning, splash and spray. A Japanese study flexible or a rigid pavement during reconstruction or as
conducted by Association of Japan Highway in 1996 an overlay.
showed that the wet weather accidents could be decreased
7. IMPERATIVES FOR THE USE OF OGFC IN
by 80% with use of OGFC surface compared with dense-
INDIA
graded pavement. A road accident study conducted in
France showed 52 occurrences of accidents on a highway OGFC has been successfully implemented across the
during 1979–1985. After placement of an OGFC on the globe in a range of climatic regions ranging from hot
same section of the highway, no accident was reported to cold and dry to wet. Hilly regions of the North East
during 1985–1999 (Putman, 2012). India receive high intensity rainfall throughout the year.
Roads in hilly regions are at much greater risk of road
5.7 Reduction in Tire-Pavement Noise accidents on account of wet weather, challenging terrain,
Movement of vehicle tyres forces away the air in front lack of skid resistance on sharp curves, and vehicle
of the contact area between tyre and pavement, while it hydroplaning (a phenomenon in which a sheet of water
sucks the air behind the contact area. High frequency builds up between the pavement surface and the vehicle
noise is generated from this air pumping action. The noise tire, making it difficult to steer and apply brakes). These
reduction potential of OGFC surfaces is predominantly factors escalate further at night due to headlight glare
due to high total air void content that enables sound from the vehicles approaching from the opposite lane.
absorption and thus minimizes tire-pavement noise. Use of OGFCs will maximise the pavement macro-
texture/skid resistance, and will reduce splash, spray, OGFC permeability (Pattanaik et al., 2017; Suresha et
and risk of hydroplaning. The authors believe that the al., 2010).
advantages offered by OGFC are sufficient to adopt Stripping: Apparently, the OGFC layer does not seal
them as road surfacings especially in rainy and hilly the underlying dense layer against moisture intrusion,
regions of India, such as the North Eastern states making the layer prone to moisture induced damages.
(Assam, Arunachal Pradesh, Tripura, Sikkim, Nagaland, This is dealt with use of an anti-stripping agent (e.g.
Mizoram, Manipur, and Meghalaya), parts of Himachal hydrated lime) and checking the designed mix for
Pradesh, Uttarakhand, Jammu and Kashmir, etc. stripping tendency through tensile strength ratio (TSR)
8. CHALLENGES AND THEIR RESOLUTION testing.
In the early decades of OGFC implementation (1960s 9. CONCLUSIONS
and 1970s), the mixtures were designed using empirical Open graded friction course (OGFC) is an HMA mix
methods using unmodified binders. The use of unmodified specially designed to have high air void contents for
binders resulted in poor OGFC performance and many quick drainage of water from the pavement. Key benefits
agencies prohibited its use (Abadie, 2013). However, of OGFC are: improved skid resistance, reduced potential
lessons were learnt and significant improvements were
for hydroplaning, improved wet weather friction,
made in selection of materials and gradations for OGFC
improved road safety, reduced splash/spray, reduced
during the 1990s. A vast majority of agencies reporting
pavement noise levels, reduced glare, and improved
good performance of OGFCs use modified binders and
visibility of pavement markings. The objective of this
comparatively coarser gradations (Kandhal and Mallick,
paper was to present an overview of OGFCs and covered
1999).
OGFC mix design, performance, construction practices,
Ravelling/Disintegration: Interconnected voids of and imperatives for its widespread use towards improving
OGFC help water to drain quickly but also accelerate the the road safety aspects in hilly regions of the country
aging process as air can pass through the structure. As a prone to heavy rainfall. A good design and construction
result, OGFC may show signs of revelling and shoving, practice is the key to enhanced performance of OGFCs.
especially at locations with heavy turning movements Experience gained in other countries indicated that the
such as intersections and ramp terminals (FHWA, 1990). durability of OGFCs is good enough as a surface course
In 1999, a survey of US Departments of Transportation on heavy traffic areas, and the service life is comparable
(DOTs) indicated that the agencies that reported good to the conventional dense-graded asphalt concrete. The
durability of OGFC mixes had used modified asphalt cost of OGFC may be slightly higher than conventional
binders (Kandhal and Mallick, 1999). Use of modified dense-graded surfacing, likely due to the requirement of
binders increases the resistance to disintegration, aging high quality coarse aggregate, modified binder, and other
and stripping by forming thicker asphalt films over the additives. However, it must also be understood that many
aggregates. Nielsen (2006) reported that most countries advantages offered by OGFC, such as improvement in
employing OGFCs preferred modified binders for better road safety and driving comfort, are rather difficult to be
mix durability while avoiding binder draindown. Now- quantified financially.
a-days, most of the OGFC mixtures are fabricated with
It is high time for India to gain experience with OGFC
these binders produced by addition of polymers or crumb
that will entail joint efforts from both academia and
rubber from waste tyres.
the industry. Field sections of OGFC can be laid and
Clogging: As pavement life pursues, entry of dirt and monitored for evaluation of their short-term and long-
debris may choke the OGFC layer and eventually reduce term performance. Dedicated research efforts and
its permeability. Clogging can be easily addressed with experience gained from field sections will provide an
recent advancements made in this direction. De-clogging excellent opportunity to develop and continually refine
operations constitute an essential component of general and upgrade OGFC specifications and guidelines for
maintenance activities for OGFCs. Cleaning of OGFC India.
can be performed with a fire hose, high pressure cleaner,
or a specially manufactured equipment vehicle (Kandhal, Acknowledgements
2002). It must, however, be recognised that de-clogging The authors gratefully acknowledge the financial support
procedures may not completely restore the original by Department of Science and Technology, Govt. of
India. The authors express sincere thanks to Prof. Prithvi 12. FHWA (1990). Open Graded Friction Courses, Technical
S. Kandhal (Associate Director Emeritus, National Advisory T 5040.31, Federal Highway Administration.
Center for Asphalt Technology, Alabama, USA) for his Accessed from: https://www.fhwa.dot.gov/pavement/
thoughtful inputs, encouragement and help. t504031.cfm
13. Kandhal, P. S. (2002). Design, Construction and
References Maintenance of Open-Graded Asphalt Friction Courses,
1. AASHTO T 19M/T 19 (2009). Standard Method of National Asphalt Pavement Association, Information
Test for Bulk Density (“Unit Weight”) and Voids in Series 115.
Aggregate, American Association of State Highway and 14. Kandhal, P. S., and Mallick, R. B. (1998). Open Graded
Transportation Officials. Friction Course: State of the Practice, Transportation
2. AASHTO T 283 (2014). Standard Method of Test for Research Board, Transportation Research Circular.
Resistance of Compacted Asphalt Mixtures to Moisture- 15. Kandhal, P. S., and Mallick, R. B. (1999). Design of
Induced Damage, American Association of State New-Generation Open-Graded Friction Courses. NCAT
Highway and Transportation Officials.
Report 99-3.
3. Abadie, C. (2013). Evaluation of Open Graded Friction
16. Lavin, P. (2003). Asphalt Pavements, Spon Press,
Course (OGFC) Mixtures. FHWA/LA.13/513, Louisiana
London.
Department of Transportation and Development,
Louisiana, USA. 17. MoRTH (2016). Road Accidents in India – 2016,
Transport Research Wing, Ministry of Road Transport
4. Alvarez, A. E., Martin, A. E., and Estakhri, C. (2011).
and Highways, Government of India, 2016.
A Review of Mix Design and Evaluation Research for
Permeable Friction Course Mixtures. Construction and 18. Nicholls, J. C. (1998). Asphalt Surfacings, E & FN Spon,
Building Materials, 25(3), 1159-1166. Cambridge University Press, London.
5. Alvarez, A. E., Martin, A. E., Estakhri, C. K., Button, 19. Nielsen, C.B. (2006). Durability of Porous Asphalt-
J. W., Glover, C. J., and Jung, S. H. (2006). Synthesis International Experience. Technical Note 41.
of Current Practice on the Design, Construction, and Copenhagen, Denmark: Danish Road Institute (DRI):
Maintenance of Porous Friction Courses, Report No. 2006.
FHWA/TX-06/0-5262-1, Texas Transportation Institute, 20. Pattanaik, M.L., Choudhary, R., and Kumar, B. (2017).
Texas, USA. Clogging Evaluation of Open Graded Friction Course
6. ASTM D2041 / D2041M-11 (2011). Standard Test Mixes with EAF Steel Slag and Modified Binders,
Method for Theoretical Maximum Specific Gravity Construction and Building Materials, 159, 220-233.
and Density of Bituminous Paving Mixtures, ASTM 21. Putman, B. J. (2012). Evaluation of Open-Graded
International, West Conshohocken, PA, 2011. Friction Courses: Construction, Maintenance, and
7. ASTM D6390-11 (2017). Standard Test Method Performance, Report No. FHWA-SC-12-04, South
for Determination of Draindown Characteristics in Carolina Department of Transportation, South Carolina,
Uncompacted Asphalt Mixtures, ASTM International, USA.
West Conshohocken, PA, 2017. 22. Qureshi, N. A., Khurshid, M. B., and Watson, D. (2015).
8. ASTM D6752 / D6752M (2017). Standard Test Method Evaluation of Premature Failures of Open-Graded
for Bulk Specific Gravity and Density of Compacted Friction Course Pavements in Alabama. Canadian
Asphalt Mixtures Using Automatic Vacuum Sealing Journal of Civil Engineering, 42(12), 1104-1113.
Method, ASTM International, West Conshohocken, PA, 23. Singh, S. K. (2017). Road Traffic Accidents in India:
2017. Issues and Challenges, Transportation Research
9. ASTM D7064 / D7064M-08 (2013). Standard Practice Procedia, 25, 4708-4719.
for Open-Graded Friction Course (OGFC) Mix Design, 24. Stanard, C., Candaele, R., Charbeneau, R. J., and Barrett,
ASTM International, West Conshohocken, PA, 2013. M. E. (2007). State of the Practice Permeable Friction
10. Choudhary, R., Chattopadhyay, D., Kumar, A., and Courses, Report No. FHWA/TX-08/0-5220-1, Centre for
Julaganti, A. (2017). Use of Industrial Wastes as Filler in Transportation Research, University of Texas at Austin,
Open-Graded Friction Courses, Baltic Journal of Road Texas, USA.
and Bridge Engineering, 12(2), 106-116. 25. Suresha, S. N., Varghese, G., and Ravi Shankar, A.
11. Cooley Jr, L. A., Brumfield, J. W., Mallick, R. B., U. (2010). Laboratory and Theoretical Evaluation of
Mogawer, W. S., Partl, M. N., Poulikakos, L. D., and Clogging Behaviour of Porous Friction Course Mixes.
Hicks, G. (2009). Construction and maintenance practices International Journal of Pavement Engineering, 11(1),
for permeable friction courses, NCHRP Report No. 64. 61-70.
ABSTRACT
Maharashtra has tradition of constructing Bridge Cum Bandhara (BCB), where bridges are used for dual
purpose i.e. crossing the river and also to create limited water storage. They are popular as they can serve dual
purpose of crossing as well as a water storage structure. Such structures have been used to tap post monsoon
flow to create storage not exceeding 3.50 m.
There is urgent need of time to save and utilize the after monsoon water that would have been flown away. In
most part of the state the steams run dry only a short period after the end of monsoon. In many areas artificial
water is supplied by tankers just after monsoon. It is urgent need of time to plan and extend the purpose of
bridges infrastructure to harness the water. New projects as well as existing bridges can be extended to tap
the water with suitable necessary arrangements. Administrative reforms shall be planned to elevate the water
availability of arid areas. The Bridge cum Bandhara (BCB) can be a water storage structure can be used
for ground water recharge, irrigation, and drinking or industry purpose. Because of percolation of water to
ground below, it acts like a reservoir where evaporation loss is minimal.
To create awareness and ease of construction for such structures, simple and ready to use standard type plan
for BCB are prepared by PWD Maharashtra. It can be used for the site condition for bridge site where rock
is available at shallow depth. The Type plan can be used for new bridge projects as well as to convert existing
bridge into water harnessing structures.
1. INTRODUCTION that would have been flown away from the area with
Bridges cum Bandhara is a dual purpose bridge structure, suitable retaining structure. The nalla is being crossed
which fulfils both the requirements such as crossing as at many places during its course by fast growing road
well as water retaining motive. In most parts of the state, infrastructural network. The bridge crossing on the
the streams run dry after only a short period after the end stream can be suitable point to tap and save the water
of monsoon. which can be used when it is required.
The water table is getting lower and lower due to large BCB structures have been used to tap post monsoon flow
numbers of bore wells being dug and exploited. Also to create storage not exceeding 3.50 m. They are ideal
drinking water for cattle becomes scarce. structure for following situations.
There is persistent demand from people’s representatives a. To tap post monsoon flow to create storage up to
for taking up Bridge cum Bandhara works on large scale. 3.5 m. The storage is created by fixing needles/
gates between bandhara piers to tap last flow.
There is urgent need of time to save and retain the water
b. Stored water is used for drinking and irrigation.
1
Secretary ( Roads), PWD Govt of Maharashtra and Vice President, Indian Roads Congress, New Delhi
2
Professor, VNIT Nagpur. Email: rkingle@rediffmail.com
3
Superintending Engineer, Designs Circle (Bridges), PWD, GOM. Email: bhongess@gmail.com
4
Executive Engineer, Designs Division (Bridges), PWD Aurangabad.
5
Assistant Engineer, PW Region Aurangabad, GOM.
c. It enhances the ground water which then is available b. Converting existing bridge into Bridge cum
for irrigation as well as for drinking water. Bandhara when rock is buried
d. Surplus percolated water out of irrigation activity c. When rock is exposed with storage up to 3.5 m
again joins the river which is tapped and reused for d. When rock is buried with maximum depth of 5 m
irrigation. with storage up to 3.5 m
e. Such stored water can be used for artificial e. No rock but storage up to 2.5 m
recharging the nearby bore wells as well as open
well to augment ground water.
The water is stored within the river banks hence does not
require additional land acquisition and hence the scheme
can be popular.
2. Evolution of suitable type Plans
for Bridge cum bandhara (BCB).
Various parts of Maharashtra state like Aurangabad,
Jalna, Solapur, Latur, Beed and few districts from
Vidharbha region etc are in drought prone area due to
scanty rainfall. The rivers and Nallas in these regions get
dried after rain is over in 6 to 12 hours. There is need
to provide water to people for farming and their cattle’s
with available water resources. PWD Maharashtra have Fig. 1 Typical Bridge cum Bandhara
constructed many bridges on number of rivers/nallas and 2.2 The Followings are Main Objectives of the
infrastructure many bridges are under construction. If Construction of Bridge cum Bandhara.
the utility of these structure is extended to harness the
monsoon water, that will be a great social contribution 2.2.1 Water retaining structure
for the department. The primary aim of BCB is to store the after monsoon
Currently the domain of authority of storage of water flow of water and to use is for long time. This requires
is solely belongs to Irrigation and Water Resource some special site conditions such as availability of non-
Department. Further there is lack of availability of ready porous rock / soil, impervious banks.
to use guidelines / drawing that can be easily implemented The water is stored when there is availability of water and
by field officers from PWD department. it is utilised according to the need of people particularly
Field officers are unaware of the suitable site for bridge in the most arid months of March to May.
cum bandhara. Therefore it is decided to prepare 2.2.2 Ground Water recharge structure
guidelines and standard drawings for the reference of When there is pervious soil / sandy soil / fissured rock
field officer. This will create awareness among field is available at bridge site the retaining structure can be
officers to construct the water harvesting structure. used for ground water recharge. This will contribute to
This structure can be used to utilise the store water so elevate the ground water availability of entire area in the
also it will raise the depleted ground water storage by vicinity. This water can ultimately utilised by the society
providing ground water recharge. The reports referred in vicinity.
in the reference (1, 2) can be used as guidelines for
Ground water can also be enhanced by recharging the
construction of Bridge cum Bandhara. A typical Bridge
bore wells with necessary arrangement as stated earlier.
cum bandhara is shown in Fig. 1.
One of the most benefit of bridge cum bandhara is the 3. Measures to taken for
structure requires no additional land acquisition and implementation of BCB
the approaches of bridge structure can utilised to retain infrastructure.
water in the vicinity. To overcome the water scarcity in the notified water
2.1 Type Plans have been Prepared for Following scares areas following measures shall be adopted by
Situations. implementing authorities.
a. Construction new bridge cum bandana when rock is 3.1 For all minor bridges where rock is exposed or
exposed and storage targeted up to 3.5 m rock is available up to 3.00 m below bed the BCB shall
j. More serious problem noticed was theft of MS d. The stability of Bandhara weir is checked for
gates and selling in scrap market, which is putting overturning, sliding, maximum / minimum pressure
whole department’s staff under problem for following conditions.
It was suggested to go for FRP material and have many i. No water no gates
fold advantages over the existing material. ii. Earthquake force with Water upto 1.5 m
Durable. heights with gates
Cost effective iii. Water up to full storage level with gates
Longer life. iv. No gates and flood at HFL
Prevention from loss & theft
Chemically resistance 5. Following parameters are
considered while preparing the
Light weight.
standard type plans for BCB
Easy to operate and store.
a. Storage depth from 1.5 m to 3.0 m
In recent years the Glass reinforced Plastics is catching
the most of the areas where it has replaced MS material b. Depth of foundation from 1 m to 4 mc.
due to above advantages. c. Velocity of water at bandhara pier top 3.0 m/
FRP is fiber reinforced plastics. Mixture of Glass Fiber sec and 4.5 m/sec at RTL (for submersible
materials and Resin which gives high strength laminate bridges).
and having advantages such as light weight, Stronger in d. Clear span between bandhara piers is from
impact strength, chemically resistance, ease in placing 2.0 m to 3.0 m
and removing and can be moulded in any shape and e. Span of main bridge considered 5.0 m &
colour. 10.0 m
Proper rubber gasket between two needles /gates
6. Loading conditions
horizontally at interface of needle/gate and interlocking
between two needles /gates insures proper fitment and a. All possible loading as per IRC:6-2017
desired water tightness. b. Triangular uplift at the base for Gate closed
Last but not the least there is acute need to work together condition.
to construct BCB by Irrigation department and P.W.D. c. 100% Buoyancy effect.
Two departments cannot work separately and joint work d. 20° variation in moving water.
will help the State to improve on the situation of water
7. Geo-technical studies to design the foundation
storage.
of the structure and various other parameters also are
4. Evolution of suitable type Plans required to be carried out. The average cost norms for
for Bridge cum bandhara (BCB). water storage structures of the irrigation department of
The type plans are evolve through rigours analysis and the concerned state need to be taken into consideration
calculations. Many institutions have work to develop the while proposing a bandhara based scheme. It has been
ready to use drawings on this issue. The guidance and observed that the cost of Bandhara is 1.25 to 1.50 Lakhs
support of Shri P. L. Bongirwar, Retired Secretary, PWD, per running meter depending upon the type of foundation
GOM and Dr R.K. Ingle, Professor, VNIT, Nagpur has and the depth of storage if the slope is 1:500 or less and
helped lot in development of policy for BCB. this fits into the norms of Maharashtra government for
PWD Designs Circle prepared type plan for a situation minor irrigation.
where impervious rock available at shallow depth. 8. Apart from constructing a totally new BCB, there
a. The type plan can be used for new proposal and to is ample scope of converting the existing bridges into a
convert existing bridge into a BCB. BCB provided the site meets various criteria as outlined
b. The type plans are prepare for various depths of in the report. At present there are various defunct
foundations, water velocity, water storage height etc. bridges (Fig. 2)/culverts available on highways due to
c. The pier and weir is designed for a maximum construction of new bridges. Most of these bridges are of
storage depth of 3.0 m above the bed level for the smaller spans with masonry/PCC piles. Such abandoned/
assumed depth of foundation up to 4.0 m bellow the defunct bridges can also be used for being converted into
bed level. bandhara.
ABSTRACT
Indian Roads Congress (IRC) design guideline for concrete pavement recommends Pavement Quality Concrete
(PQC) layer over a roller compacted concrete designated as Dry Lean Concrete (DLC) with a bond breaking layer
of 125 micron thick plastic sheet at the interface of DLC and PQC. IRC 58 also includes the design of bonded
concrete pavement in which the top high strength concrete slab is bonded to the Lean Concrete (LC) base. The
stresses in bonded or unbonded pavements are analysed considering that the edges of the DLC base and PQC slab
are in the same vertical plane. In Portland Cement Association (PCA) design method also, similar assumption
is made. However in actual construction the base extends beyond the concrete slab for the convenience of the
construction and stresses will be different for such conditions. The solutions for stresses in concrete pavements
with extended bases are not available, both for bonded and unbonded concrete pavements and the designer does
not have any idea of the margin of safety due to the extended DLC. In this paper, the stresses in a concrete
pavement with and without extended DLC/LC bases are computed by Finite Element Method (FEM) considering
both axle loads and temperature gradients across the depth of the concrete slab and Dry Lean Concrete (DLC).
Computation shows that the maximum flexural stresses in concrete pavements are reduced when extended DLC/
LC base is provided and thickness of PQC can be reduced or the life of the pavement will be greater for the same
thickness.
2. 3D FE Modelling of concrete pavement: Finite element analysis was carried out to study the
Huang (1993) used equivalent flexural stiffness concept effect of extended DLC layer in pavement system. A
for the analysis of stresses in a two layer concrete layer pavement system is considered with a subgrade
bonded pavements. The same concept is suggested of 5% CBR, and thickness of granular subbase, DLC
both in IRC:58-2011 & 2015 but this concept is not and PQC are taken as 150 mm,200 mm, and 200 mm for
applicable for finding interface stresses in bonded analysis. The extended widths of DLC/LC were taken
concrete pavements. Suryateja et.al (2017) explained as s 0.25, 0.5 and 0.75 m for the stress computation.
the usage of Finite Element Method for the analysis Using IRC:58 charts, effective K-value for a system of
of bonded concrete pavements. The 3D FE model of sub grade and subbase was found out to be 100 MPa/m.
the slab was created in ANSYS 15.0, which is used to Properties of materials considered for analysis taken
model the combination of load and temperature effects from IRC:58-2015 are shown in Table 1. Rectangular
on the above-mentioned extended base condition. The tire imprints of size 240 mm x160 mm corresponding
panel dimension is 3.5 m x4.5 m. The FE mesh and the to a single wheel load with different tyre pressures
modeled pavement geometry are shown in Fig. 2. were considered for the application of wheel loads of
different magnitudes on the slab. Two different critical
positions as specified in IRC:58 were considered for
the analysis of Top down and Bottom-up cracking.
Table 1: Properties considered for PQC and LC layers
Table 3: Stresses Due to Change in Width of Extended LC Base in Unbonded Concrete Pavements
Fig. 3 Stresses in Bottom Layer with Change in Extended Base Width Fig. 4 Stresses in Bottom Layer with Change in Extended Base Width
@ 0°C Temperature Differential (Bonded Concrete Pavements) @ 9°C Temperature Differential (Bonded Concrete Pavements)
Dr. Ambika Behl1 Dr. Siksha Swaroopa Kar2 M.N. Nagabhushan3 Prof. Satish Chandra4 Manoj Shukla5
ABSTRACT
The asphalt paving industry is constantly exploring technological improvements that will enhance the material’s
performance, increase construction efficiency, conserve resources, and advance environmental stewardship.
There is a need for immediate attention towards the implementation of sustainable and environment friendly
pavement construction technologies. Recent advances in asphalt technology around the world have made cold
recycling an increasingly popular and cost effective pavement construction and maintenance technique. India
has also started adopting sustainable road construction technologies like warm mix asphalt, cold mix asphalt
and recycling of asphalt pavements. This paper presents the feasibility of producing high quality cold recycled
asphalt using foam bitumen for a heavily trafficked national highway of India. Foam bitumen stabilization was
used to rehabilitate the existing base layers of pavements incorporating thick asphalt layers, resulting in higher
percentages of Reclaimed Asphalt Pavement (RAP) in the mix. Energy conservation and reduction in GHG
emissions were also monitored during the construction phase.
1. Introduction pollutants such as particulate matter, nitrogen oxides,
Rapid growth in industrial development and economy in carbon dioxides and sulphur dioxides. Many of the diesel
last two decades has demanded up gradation of existing engine emissions have been identified as carcinogenic,
road network in the country. A good road network is and harmful to the human health, even at occupational
a vital infrastructure requirement for rapid economic and environmental levels of exposure. For a lead of
growth. There is a huge road network in the country but 200 km (which is common in north India), it will
it is still inadequate to meet the accessibility and mobility require 18 million liters of diesel in transportation alone
requirements. Severe distresses that occurred in existing (Veeraraghvan and Mallick, 2010). Therefore, a serious
road network required that the bearing capacity of the attempt has to be made to develop and adopt alternative
existing pavements should be increased. technologies for road construction and maintenance to
reduce consumption of fuel and aggregates. Recycling
The conventional method of providing bituminous
of existing bituminous pavement materials to produce
surfacing on flexible pavements requires significant
new pavement material results in considerable savings
amount of materials and energy. Therefore, in order to
of material, money and energy.
reduce consumption of fuel and aggregates, pavement
recycling technology may be adopted for Indian roads One of the most energy efficient mechanisms for
(Reddy et al., 2013). Also, there is a problem of the rehabilitation of an asphalt pavement is cold in place
scarcity of aggregates, which forces truck delivery recycling (CIR). It involves recycling of asphalt
of materials from long distance. The use of diesel pavement without application of heat during the recycling
for running these trucks contributes to emission of process. CIR is carried out on site and generally uses
1
Sr. Scientist, Flexible Pavement Division, Email: behl.ambika@gmail.com
2
Scientist, Flexible Pavement Division
CSIR-Central Road Research Institute,
3
Sr. Principal. Scientist, Flexible Pavement Division
New Delhi
4
Director
5
Principal. Scientist, Flexible Pavement Division
100 percent of the RAP (reclaimed asphalt pavement). affect the strength and durability of foamed bitumen
Bitumen stabilized materials (BSMs) incorporating treated materials, such as binder content, active filler
bitumen emulsion or foamed bitumen, have been used type and content, aggregate composition and gradation,
globally over the last two decades to provide base layers moisture content, compaction effort, and curing regime
for many thousands of kilometers of road pavements (Fu et al., 2008; Fu et al., 2009; Jitareekul& Thom, 2009;
(Oluwaseyi, 2010 and Kandhal, 2011). The BSM Nataatmadja 2001; Marquis, 2003, Kar et al., 2017).
technology using foam bitumen is primarily applied on This paper presents the feasibility of producing high
rehabilitation projects using recycled materials in the quality cold recycled asphalt using foam bitumen for a
existing pavement. Foamed stabilization technique needs heavily trafficked national highway in India.
less binder and water compared with other types of cold
mixing, therefore, the cost of transportation and asphalt 2. NH-2 REHABILITATION PROGRAM
binder are reduced (Khalid, 2013 and Kar et al., 2018). The subject project road passes through many important
Foamed bitumen is a mixture of very hot bitumen and cities/towns of historical, tourist, and commercial
water. It is produced by injecting water into hot bitumen interest on national highway number 2 (NH-2). The
(160–180°C) which is supported by air. The volume of section of the project road is part of national highway
water is between 2–5% of the volume of bitumen. When which connects Delhi, the national capital to Kolkata.
the water contacts the hot bitumen, it rapidly changes to The project road is about 85 kms in length. The road
steam and the volume of bitumen expands many times. section developed heavy distresses/defects and the
In this stage the foamed bitumen is produced, it contains pavement was deteriorated severely and showing signs
thousands of bitumen bubbles and then is ready to be of distress and premature failure, especially in the form
mixed with an aggregate (Thom, N., 2008).Many factors of severe rutting, cracks and deformation. Photo 1, 2 and
3 shows the condition of the distressed pavement.
3. FIELD INVESTIGATIONS Based on field and laboratory testing results of the sub-
Field investigations like: test pit observations, coring grade and the planned traffic design, if the pavement had
of bituminous mixes, classified traffic volume survey, to be reconstructed, the conventional pavement design of
collection of milled material were taken up during the whole pavement would be as follows:
August 2016. Test pits were excavated right up to the Layer Specification Thickness,mm,
subgrade level to examine the construction quality of 185 msa
constituent pavement layers including the earthwork/
Granular Sub Base (GSB)+ Granular 450
subgrade. In-situ field densities of Subgrade soil,
Base (WMM)
Granular sub base (GSB) and Granular base course
(Wet Mix Macadam) were determined by sand Dense Bituminous Macadam (DBM) 185
replacement method, as per IS standard test procedure. Bituminous Concrete (BC) 50
As regards the field densities of Dense Bituminous 4. RAP MIX DESIGN USING FOAM BITUMEN
Macadam (DBM) and Bituminous Concrete (BC)
With the aim of recycling the existing pavement layers
layers, a number of cores, from different locations, in
and at the same time strengthening the aged and distressed
addition to the bituminous materials (chunks) collected
pavement, Cold in situ recycling using foamed bitumen
from various test pits, were sampled for the purpose of
approach was considered. The milled (RAP) material
detailed laboratory evaluation. The thickness of each
was evaluated in CRRI laboratory for RAP mix design.
constituent pavement layers was measured at various
locations. Cores, chunk material and RAP material Bitumen and Foam Characterization
were evaluated in detail in laboratory at CSIR-CRRI, VG-30 grade bitumen was used and its physical properties
New Delhi are presented in Table 1.
Table 1 Physical Properties of the Bitumen VG30
60°C for 24 hours and then placed in an environmental VG-30 asphalt binder in mix design. 1% cement OPC
chamber maintained at 25°C for two hours. Then tensile 43 grade was added to improve the stability and better
strength of each specimen is determined by the tensile dispersion of foamed bitumen in fine particles of the mix.
splitting test. The Tensile Strength Ratio (TSR) of
5. PAVEMENT DESIGN
specimen is computed by equation (2).
The design traffic in terms of Cumulative Standard Axles
( ) (2) (CSA) was worked out by considering the commercial
traffic and their Vehicle Damage Factor (VDF), for a
Where, Twet is average indirect tensile strength of convenient design life duly accounting for the anticipated
conditioned specimens and Tdry is indirect tensile strength traffic growth. In the present case, the cumulative
of unconditioned specimen. standard axles have been worked out for 15 years design
Table 3 shows the Tensile Strength Ratio at different life by assuming an annual growth rate of commercial
binder contents. Maximum TSR value is obtained at vehicles as 5%. IITPave software was used to carry
2.25% foamed binder content. out the pavement design as per IRC:37-2012 with 90%
reliability performance.
Table 3 Tensile Strength Ratio Values
The value of resilient modulus of BSM ranges from
Sample Tensile Strength Ratio, % 600-1200 MPa as per Sec 7.3.3 of IRC:37-2012 and it is
No 2.0% 2.25% 3.0% recommended to use the value of 600 MPa for structural
Foamed Foamed Foamed design purpose. BSM is sensitive to moisture, a safer
Binder Binder Binder value of 600 MPa is to be adopted for structural design
Content Content Content as per the code. However, in the present study, as per
1 73.8 77.4 69.4 the values given in table 4, in laboratory much higher
2 70.1 75.2 71.4 values of Resilient modulus were achieved. Keeping
3 74.3 76.5 66.3 in view the satisfactory values of TSR (tensile strength
ratio) obtained from test results, which is indicative
Resilient Modulus Test of a good moisture resistance property of BSM mix, a
This test is used to analyze the pavement response for the mid value of resilient modulus 800 MPa is assumed for
repeated traffic loading by measuring the indirect tensile BSM layer for structural design purpose. The stiffness
strength modulus according to ASTM D7369 (2011). The modulus obtained in laboratory for the BSM at 35C and
test is performed on Universal Testing Machine (UTM- 2.25% foamed binder content is 1444 MPa. Considering
16). Specimens prepared at their optimum binder content an average wet ITS value of 306 KPa, however, a
were loaded by diametrical force in pulse loading. Test conservative value of 800 MPa is considered safe in the
parameters were; Haversine Load Pulse, condition pulse pavement design under the adopted design parameters
count of 5, pulse width of 250 ms, peak loading force of (i.e., 2.25% binder and 6% OMC).
500N and poisons ratio of 0.35. The crust composition is given in Table 5.
Table 4 shows the Resilient Modulus at 25ºC and 35ºC Table 5: Crust Composition with 800 MPa E Value for
for different binder content. It can be seen from table 4.7 BSM layer
that maximum MR values are obtained at 2.25% foamed
binder content at both the temperatures. Layer Specification Thickness,mm185
msa, 15 years
Table 4 Resilient Modulus Values
Granular Sub Base (GSB)+ 450
Foam Binder Content 2.0% 2.25% 2.5% Granular Base (WMM)
Testing Temperature 25°C 35°C 25°C 35°C 25°C 35°C Foam Bitumen Stabilized Base 175
Resilient Modulus, MPa 1552 1034 2577 1444 2319 1550 (BSM) (recycled layer)
(Average of 3 tests)
Dense Bituminous Macadam 70
Coefficient of Variation 7% 5% 6% 3% 7% 4%
(DBM)
The final recommendation for RAP mix design was for Bituminous Concrete (BC) 50
2.25% foam bitumen and 6% optimum moisture content.
Optimum foaming characteristics were achieved at 6. CONSTRUCTION PROJECT
temperature of 180°C and foaming water content of Project evaluation was the first step in the construction
5%. This combination for foaming was selected for the process. Necessary comprehensive site investigation
was conducted in order to check and qualify the quality use during overlay. The existing DBM layer was to be
and quantity of RAP that will be processed for recycling recycled using foam bitumen. Photo 4 shows the surface
procedure. Laboratory investigation of the asphalt after milling. Fresh crusher dust was spread over the
foaming characteristics, mix design and pavement design milled surface (as per the gradation requirement) Photo 5
were completed prior to start of the construction. and then spreading of cement was done Photo 6. Photo
Wirtgen milling machine was used for milling top 40 mm 7 shows the homogeneously spread fresh aggregate and
layer of BC and transported to hot mix plant for further cement.
Photo 4 Surface after Milling Photo 5 Crusher Dust Spread over Milled Surface
Photo 6 Spreading of Cement Photo 7 Surface after Spread of Cement on Fresh Aggregate
WR240 machine Photo 8 was used for recycling at then gets mixed with the pulverised pavement material.
NH2 project. The foam mixing recycler is coupled Immediately following this recycler was Hamm roller to
with a bitumen supply tank and water supply tank. The compact the recycled base Photo 9. After grading and
recycler pushes the tanker. Heated bitumen at 180°C profiling of the recycled base layer Photo 10, steel drum
is transported from hot mix plant to construction site roller was used to seal the top layer. The compaction was
through a temperature controlled tank. Hot bitumen then followed with curing process prior to overlay. The
and water gets injected in to the recycler and foaming recycled surface is cured for 48-72 hours by sprinkling
takes place through spray bars. The foamed bitumen of water at an interval of 6-7 hours.
Photo 11 shows the view of recycled surface before overlay and photo 12 shows the view after the overlay.
Photo 11 Recycled Surface Before Overlay Photo 12 Recycled Road After Overlay
7. GHG EMISSIONS: THE GREEN BENEFIT • The boundary is restricted to the region above
the granular sub base. Also, any kind of
The most significant contribution of cold in situ recycling
is significant reduction in transportation of materials as embankment shoulders or road furniture such
well as reduction in requirement of fresh aggregate and as toll plazas, markers, sign boards, rails etc are
bitumen. excluded.
The case study comprises of 85 km of a 4 lane highway • The focus is on the process carried out in the
with a lane width of 3.5 m. construction of the road and the material used for
making the layers of the road.
Assessment of Carbon Dioxide Emission
Road construction is a large project consisting of • Emissions from material transport are not
various strata and process that are carried out. It is considered for both conventional and current
simply not possible that every aspect of the road design.
construction to be included in the project, nor is it • Any road furniture is excluded and hence no
desirable. calculations for the Greenhouse emissions from the
For this particular study, scope of the work is defined as process carried out during the production of such
follows and is shown in Fig. 3. materials are made.
rap design Conventional Design transport and onsite impacts have not been analyzed.
BC BC 50mm
The construction equipment and transport of material
50mm
for both the design has not been considered. The
DBM 70mm
saving of CO2 emission using conventional and RAP
185mm
design using foam stabilized material is due to the
BSM 175mm DBM reduction of temperature during mixing and also due
to saving of aggregate and bitumen, which results
BC: Bituminous Concrete in reduction of embodied emission. As mentioned
DBM: Dense Bituminous Concrete
BSM: Bitumen Stabilized Material earlier in this paper, use of foam stabilized technique
enables utilization of 80% of recycled aggregate and
Fig. 3 Scope of Work Presented in the Paper
about 60% less bitumen for construction of pavement.
Analysis through CHANGER Embodied emission and emission due to mixing are
The data collected from the site was analyzed through determined using CHANGER software and details are
CHANGER software. Preconstruction parts, material presented in Table 6.
Table 6 Consolidated results of Emission per km per lane
Aggregate and bitumen saving per km per lane are found process resulted in construction time saving, minimal use
about 833 and 31 tonne, respectively using the foam of virgin aggregates, less transportation of materials and
stabilized mix design in place of conventional design. several other environmental benefits. Huge reduction in
Embodied energy of cement and recycled aggregate carbon emissions can be achieved with the use of RAP
is also taken into consideration for GHG emission technology.
calculations. Approximately 40 tonne equivalent CO2
There are many parameters that influence the
is saved per km per lane construction. For a 85 km
performance of cold recycled mixes including,
and 4 lane road construction project, carbon emission
aggregate origins, aggregate properties, type of binders,
reduction of about 13600 tonne equivalent CO2 will be
binder contents, moisture content, temperature etc.
achieved.
Before construction at site, on the basis of satisfactory
8. CONCLUSIONS laboratory test results, a field trial is recommended
The addition of cement would result in increased to verify the construction quality of the pavement
strength properties of mixes. The Indirect Tensile in a realistic condition. These field trials also benefit
Strength (ITS) and Tensile Strength Ratio (TSR) values the understanding of construction procedure under
of recycled mix were found to be more than satisfactory different traffic, climate, terrain conditions and quality
whereas resilient modulus (MR) values achieved control for cold in-place recycled pavements. After
were significantly higher than the specified values (as construction, it will be beneficial to have a time series
per IRC:37-2012). Cold recycled materials are good field performance so as to find its ability to withstand
opportunity to save money and resources. The recycling the existing traffic condition.
Acknowledgements 7. Kar, S.S., Swamy, A.K., Tiwari, D. and Jain, P.K., 2017.
A Critical, Review on Foam and Emulsion based Cold
The authors are thankful to the team of M/s Wirtgen
Recycled Asphalt Mixes. Indian Highways, 45(8).
India Pvt. Ltd, for their support during the project and
also during the formation of this paper. The research 8. Kar, S. S., Swamy, A. K., Tiwari, D., & Jain, P. K. (2018).
Impact of Recycled Asphalt Pavement on Properties of
sponsoring organization and authors do not endorse
Foamed Bituminous Mixtures. Baltic Journal of Road
any proprietary products or technologies mentioned in
and Bridge Engineering, 13(1), 14-22.
this paper. These appear herein only because they are
9. Nataatmadja, A. (2001). Some Characteristics of Foamed
considered essential to achieve the objective of this paper.
Bitumen Mixes.Transportation Research Record: Journal
References of the Transportation Research Board, 1767(1), 120-125.
1. Fu, P., Jones, D., Harvey, J. T., & Bukhari, S. A. (2008). 10. Mallick, R. B., and Veeraragavan A. (2010). Sustainable
Dry and Soaked Laboratory Tests for Foamed Asphalt Pavements in India-the Time to Start is Now. New
Mixes. Asphalt Paving Technology-Proceedings, 77, 71. Building Materials and Construction World (NBM&CW)
2. Fu, P., Jones, D., Harvey, J. T., &Halles, F. A. (2009). Magazine 16.3: 128-140.
Investigation of the Curing Mechanism of Foamed 11. Marquis B., Bradbury R.L., Colson S., Malick R.B.,
Asphalt Mixes Based on Micromechanics Principles. Nanagiri Y.V., Gould J.S., O’Brien S., Marshall M.,
Journal of Materials in Civil Engineering, 22(1), 29-38. (2003) “Design, Construction and Early Performance of
3. IRC:37-2012. "Tentative Guidelines for the Design Foamed Asphalt Full Depth Reclaimed (FDR) Pavement
Of Flexible Pavements". Indian Roads Congress, in Maine”, 82th Annual Meeting of Transportation
New Delhi. Research Board.
4. IRC:120-2015, "Recommended Practice for Recycling 12. Muppi Reddy, A., Reddy, K. S., & Pandey, B. B. (2013).
of Bituminous Pavements", Indian Roads Congress, Recycling of an Urban Road using Foam Bitumen: An
New Delhi. Indian Experience. In Transportation Research Board
5. Jitareekul, P., & Thom, N. H. (2009). Experimental 92nd Annual Meeting (No. 13-3740).
Study on Deformation of Foamed Bitumen Bound Base 13. Oluwaseyi ‘Lanre, O. (2010). “A Study on the
Materials. In GeoHunan International Conference: Development of Guidelines for the Production of Bitumen
Challenges and Recent Advances in Pavement Emulsion Stabilised Raps for Roads in the Tropics”
Technologies and Transportation Geotechnics. (Doctoral dissertation, University of Northampton).
6. Kandhal P. S. (March 2011). Advances in Bituminous 14. Thom, N., (2008), Principles of Pavement engineering.
Road Construction, NBMCW. London: Thomas Telford Ltd.
the construction. Above technically challenging issues takes around 15 to 20 days from Kolkata to the bridge
are some of the main reason why bridge at Gurupriya Site. In case of any breakdown/regular maintenance; wire
site could not happen since long, rope and all spares to be brought from Kolkata. Pontoons
The bridge site near Janbai on Chitrokonda-Janbai- were fabricated in workshop at Raipur, Chhattisgarh and
Papermetla road is in a remote location touching the shifted in pieces over Trailer and assembled at site. High
border zone of Orissa-Andhra Pradesh and Chhattisgarh Capacity crane was moved from Latehar of Jharkhand
and very much affected by Naxal threats. Very poor state. Crane was moved on its wheel and its counter
accessibility for movement of man and machineries weight was sent through Trailer. A team of 4 members
for construction purpose due to hilly terrain & narrow was sent along with the crane to reach the site safely. It
inaccessible roads from both approaching ends i.e either took about 5 days to reach the site.
from Jeypore side (i.e through state of Odisha) OR from Due to Naxal threats, no material supplier was ready
Visakhapatnam side (i.e from state of Andhra Pradesh). to supply materials at site. District Administration did
The accessibility to Janbai site approach of the bridge not permit to run crusher due to pollution and green
are either through Jeypore-Baipariguda-Govindali- belt issue at Malkangiri, which hampered supply of
Balimela-Chitrkonda route from state of Odisha OR aggregates. No transport facilities are available at site,
through Visakhapatnam-Tahllipelam-Narsingpatnam- therefore, for sending even for small parts/spares also,
Chintapalli-Gudem-Darkonda-Chitrokonda from state of an individual vehicle had to be arranged. Prestressing
Andhra Pradesh. Road conditions were extremely poor wire rope was procured from M/s Usha Martin from their
from Chitrokonda to Janbai. Similarly the only route Ranchi production unit. Each lot took about 15 days to
available to come to Papermetla side approach of the reach the site. Prestressing Jacks and other materials
bridge is from Visakhapatnam of Andhra Pradesh through were procured from Dynamic Prestressing system from
Visakhapatnam-Tahllipelam-Narsingpatnam-Chintapall- Nasik and 30 days lead time was required to reach
Paderu-Muchingiput-umuda-Gandiguda-Jantapai- the materials at site. Steel Girders for the six spans of
Papermetla-Badapada. The road from Muchingput to the bridge were fabricated in workshop at Raipur and
Badapada is earthen kachha road. Besides above, the individual segments were transported through trailer
surrounding areas all along the above three routes are through the Ghat Roads to the bridge site which used to
affected by regular maoist activities and with almost nil/ take 8 to 10 days time. HSFG bolts were procured from
very poor tele network connectivity till today. Ludhiana and dispatched after inspection from the shops
and each lot took about 20 days to reach the site.
3. SITE STRATGIC ISSUES & DIFFICULTIES IN
MOBILIZING MATERIALS, MACHINARY & Similar difficulties were faced during mobilization
HUMAN RESOURCE of manpower: The 17 Km long existing road between
Chitrokonda (i.e the block head quarter) to Janbai
Three challenges that was originally predicted were;
approach of the bridge site is full of jungle and barren
access to reach the bridge site, availability of limited
areas with no tele communication facilities. Due to
working period of only four to five months a year that again
Naxal threat, no staffs were ready to work at bridge site.
only during day time as evening work was considered
Subsequently, the project site office including labour
highly unsafe & risky due to naxalite problems. The
camp were established just adjacent to BSF base camp
amenities like electricity and communication were very
on A1 side approach of Janbai and officials camp near
poor. Though a fair access to the site was made partially
Chitrokonda BSF premise for safety purpose. There
ready around June 2013 after start of construction
is no direct rail/road route from metro like Kolkata to
work for Chitrokonda-Janbai road, there was need for
the project site. Pilling gangs were arranged from West
appropriate planning to mobilize material, plants &
Bengal. Labour was sent to Kolkata from their native
machineries and labour to complete the task considering
place, Kolkata to Vizag via train, then Vizag to Selur via
the natural and man made hinderances.
bus and Selur to Site through Jeep. It took around 36 hrs.
As the area was affected/defamed due to Naxal threats, no for labours to reach the site from their native place.
agency was ready to supply any machinery/equipment to
the site. The area was cut-off from transmission/ mobile 4. TECHNICAL CHALLENGES DURING
network, and thus no operator was ready to work in the CONSTRUCTION OF FOUNDATIONS
Gurupriya bridge site. Piling machineries were shifted The Full Reservoir Level (FRL) of Balimela reservoir
from Kolkata through Bhubaneswar to Janbai via Jeypore is R.L.462 m. Considering vertical clearance to the
route. This route passes through narrow Ghat road. It superstructure, the formation level of bridge has been
Photo 1 Bridge Site in September 2014 The foundation for the bridge are executed with large
After Award of the Work diameter piles (1200 mm & 1500 mm diameter) anchored
Photograph shown at Photo 1 presents the view of inside hard rock. Average depth of pile foundation
the bridge site during September 2014 after award of is about 20 m below ground level with 3.5 m to 7 m
the work to the EPC contractor. The field water level embedment inside hard rock. The piling work in shallow
as witnessed by the department has gone beyond RL water depth zone was done by making local earthen
460 m during 2014, 2015 and 2016 construction period.
Photographs shown at Photo 2 and 3 explains how islands as shown in Photo 4.
transportation of heavy construction machineries and The piling work in deep channel zones are done over
construction materials were made over floating pontoons floating pontoons with the help of steel liner, which were
during the construction period.
provided through the standing water to the starting of
The construction activities for foundation work were rock zone. This is one of the critical activities of the
carefully planned as per the gradual water spread and
corresponding water depth at any particular location by project which had consumed lot of time due to difficulties
segregating the construction activities for shallow water in maintaining balance over the floating pontoon while
zone and deep channel zone. driving the chisels as shown in Photo 5.
Fig 3 Shuttering Arrangement with Sacrificial Base for Deep Water Pile Cap
Above proposals alongwith supported design and In situ casting and subsequent stressing of PSC girders
methodology were examined & reviewed critically and for the spans close to the deep water zone were made
proved to be acceptable for construction considering the from a staging platform placed on a designed truss
site condition . The earth filled island for any particular system over pile caps.. As shown in the construction
span in the shallow zones over an area of 40 m X 9 m photograph Photo 11 for the span P17-P18, there were
was stabilised by driving wooden piles with proper three inter connected plane truss over which tubular
compaction as shown in Photo 8 to support the induced staging were erected to facilitate required casting height.
dead load of concrete girders before stressing. Other The segments and joints of the trusses were made with
slope strengthening measures using sand bags as pitching typical splice plate connected with high tensile nut &
elements to the temporary earthen islands was also made bolt system so that the segments can be opened for re-use
besides laying of 150 thick PCC bed over the compacted in another span. This type of staging was first attempted
bullah pile system to avoid any failure of the temporary over span P17-P18 and the work was successfully carried
out. However, the arrangement took considerable amount in-house fabrication factory and transported to the bridge
of time for erection of the truss over the pile cap and the site.
tubular staging over the truss system . Removal of such
truss system segment wise & re-fixation in another span
inside deep water zone also took considerable amount of
time, which compelled to look after other alternatives.
facilitating lifting by typical winch-pulley-roller system. than 14 m were erected over temporary earthen island
Photo 12 to 15 explains the sequential activities starting with design staging platform. The temporary earthfill
from site assembly of steel girders with connection of island at this location was strengthened by combination
their flange & web splice plates, tightening of HSFG of bullah piles and steel piles driven deep inside the bed
bolts by mechanical torque wrench of required capacity, level besides sacrificial concrete capping arrangement to
placement of assembled girder over floating pontoons prevent any collapse of the tall towers due to underneath
by mechanical crane, transportation of girder on floating seepage failure. Assembling of the individual box
pontoons by tug boats to the required location and finally segments were made at the bearing level over temporary
lifting of girders from floating pontoons with help of steel towers after matching the splice holes for the
designed pulley & roller system. HSFG bolts. Thereafter the fully assembled box girders
were laterally moved one by one with help of designed
41 m Long Steel Girder errection in deep channel rollers from down stream side pedestal to up stream side
zone from floating pontoon-I, November 2018 pedestal followed by fixation of cross girders The site
photographs showing launching of box-type steel girders
of 60 m length over the last span on P12A-P14 is shown
in Photo 12. The compulsion to change the execution
methodology due to unexpected abnormal drawn down
of reservoir water level has resulted some delay in the
work for this last span of the bridge.
7. QUALITY ASSURANCE & DUE DELIGENCE safety of the bridge. As a part of audit by CRRI, two
THIRD PARTY TESTS representative span of the bridge namely span P2-P3
Various quality assurance tests were performed during (PSC girder with RC deck superstructure) and P12-P12A
the construction phase after finalizing the methodology (Steel composite super structure) were load tested under
and schedule in advance. All tests after completion of the full design load test. Before load test visual inspection
project were conducted for issue of completion certificate of full span had been done properly. Expansion
to the contractor as per the EPC agreement condition. joints checked to insure for their proper functioning.
Finally a third-party quality audit was also conducted Scaffolding erected for fixing the instruments such
by the Bridge and Structures Division of Central Road as displacement transducers, temperature and strain
Research Institute (CRRI) who has certified the structural gauges.
Check for Deflection at various points due to test vehicle
Fig. 4 Discretization of Girder System Showing Critical Nodes and Sequential Loading Pattern of the Test Vehicles.
Fig. 4 explains the discretization of girder system in to and strain value continued for next 24 hours at an
finite elements and nodes. The sequential positioning of interval of one hour. After completion of 24 hours the
test vehicle loading pattern in longitudinal and transverse above procedure was repeated for unloading of load and
axis for analytical evaluation of deflection under test deflection, temperature and strain values were recorded.
load as per equivalent absolute maximum bending Afresh. Total 27 numbers of LVDT and 9 numbers of strain
moment concept and the corresponding deflection at gauges were fixed at the critical locations of the girders as
critical nodes are shown in Fig. 5. The load was applied shown in the Fig. 7 to record & measure the displacements
by adding loaded trucks of known weight. The test load and rotations in the three girder integral system.
is applied in stages of 55T, 85T and 115T (100% design Fig. 8 shows the schematic arrangement of test load and
equivalent load) as shown in Fig. 6. Fig. 9 demonstrates the load deflection graphs as per the
The deflections are measured at every stage of loading data recorded through four numbers of LVDTs placed near
and after one hour of loading. The recording of deflection the mid span, The test spans were constantly monitored
Fig. 5 Sequential Loading Along Longitudinal Axis with Fig. 6 Theoretical Deflection Values at Critical Nodes for the
Transverse Critical Position Outer and Inner Girder
for any structural distress at every stage of loading. From spans satisfy the required recovery of deflection
the load test results it is clear that both the representative more than 85% as per IRC:SP:51-2015 specification.
Fig. 7 Location of LVDTs & Strain Gauges for Load Testing of Full Span
Fig. 9 Load Deflection Curve for the LVDTs Placed at Mid Span of Girders
Photo 18 Completion Photograph Of Gurupriya Bridge with Water at Full Reservoir Level of 462 m During September 2018
8. CONCLUSION
the estimate considering the ground realities. In a
The planning for construction of the high level bridge competitive bidding process, M/s Royal Infraconstru
near Balimela reservoir was started in 1982, but it could Ltd from Kolkatta was awarded with the work, who
not take off due to technical challenges, remote location could finally complete the bridge within a span of three
and inaccessibility, and foremost, the menace of naxals/ and half years under BSF protection. Two companies of
left wing extremism. After several attempts, the State BSF were deployed on each side of the bridge to provide
Government could finally start the work in 2014 and security cover to the personnel and machineries during
the bridge was constructed within a short span of three the construction. The BSF security arrangement will
and half years due to dedicated micro managemet at remain in place for some more days near the bridge site.
each stage of work . The bridge has become a landmark The entire bridge has been illuminated and brought under
engineering feat in the State considering the natural CCTV surveillance to detect any attempt of sabotage by
features and technical challenges posed by the site. The naxals. The bridge will bring all-round transformation
present bridge structure as shown in the completion in the worst LWE-affected region by facilitating fast-
photograph Photo 18 inside Balimela reservoir basin paced development through improved connectivity,
has 22 spans standing on the water depth of an average health, education, electrification and access to public
20 m with the deep channel zone extending to a depth of services. It will boost economic activities and create
around 28 m. better livelihood opportunities for the people.
At the time of the beginning of construction of the One of the lesson learned in this project is to assess the
Gurupriya bridge, there were many skeptics who constructability issues that may arise from time to time
believed it was impossible to try and build a bridge due to fluctuating water depth, which practically guides
that can span across the Balimela reservoir. One of the the execution methodology and provide the basis for
nation’s leading engineering firms Gammon India tried actual construction time period in such a remotely located
their efforts during 2006-2008 but could not progress naxal disturbing zone. All items of works including the
due to remote site condition with naxal threats besides required machineries and associated logistics that can be
abnormal fluctuation in water depth for three consecutive safely deployed in such site scenario should be worked
years. State Govt’s initiative for making the bridge out at the planning stage and cost estimate as per ground
with help of Garden Reach Ship Builders, Kolkatta realities should be prepared.
and Bharat Earth Movers Ltd, Bangalore also could
not materialised Subsequently the project was included 9. ACKNOWLEDGEMENT
under the LWE (Left Wing Extremism) scheme of The authors wish to record their appreciation and sincere
Govt of India. During 2010. However multiple bidding thanks to the team of Scientists from Bridge and Structure
attempts made on behalf of Government of India could Division of Central Road Research Institute (CRRI) New
not yield any success ill 2013. As the State Govt. was Delhi for their suggestions during 3rd party quality audit
desperate for giving all-weather connectivity to the in documenting the work as a case study example. Special
remote and un connected 151 habitations for bringing thanks are extended to the Authority Engineer team from
the people to the main stream and also to free the area ARCHITECHNO Consultant Pvt Ltd, Bhubaneswar led
from LWE activists, it was finally decided to initiate by Er. Rajesh Roy Choudhury, Managing Director and
fresh bidding attempt with Engineering, Procurement Er Ashok Basa, Director Technical for their technical
and Construction (EPC) contract provisions by recasting guidance during supervision of the project.
ABSTRACT
Premature pavement distresses primarily in terms of moderate to severe fatigue cracking were observed on
a four-laning, 50-km national highway project. This paper describes in detail the systematic sampling and
testing plan which was executed to determine the specific cause(s) of the premature pavement distresses.
In general, good construction quality control and quality assurance of various pavement courses was not
exercised, which led generally to the development of premature “bottom up” fatigue cracking on the project.
Remedial measures to rehabilitate this distressed national highway project have been described in detail based
on the category, severity, and extent of the distresses. General recommendations have also been made to avoid
such pitfalls on other major highway projects.
1. INTRODUCTION (c) obtain samples of all pavement layers; (d) test all
After four-laning of a 50-km national highway was samples in an independent laboratory; (e) analyze the test
completed, premature pavement distresses were observed data and draw conclusions; and (f) recommend remedial
on it during the first monsoon. The following pavement measures considering the type, severity, and extent of
distresses were observed: open surface texture; raveling; specific pavement distress.
hungry surface; alligator cracks; and potholes. By far, 3. PROJECT DESCRIPTION AND DETAILS
fatigue cracking was the primary distress ranging from
3.1 Project Description
moderate cracking (one to two cracks in wheel path) to
severe cracking (alligator cracks in the wheel path or Four-laning of this project was completed on a Design,
block cracks across the lane). Build, Finance, Operate and Transfer (Toll) basis. The
concession period of this project is 20 years excluding
Further successive deterioration of pavement occurred the construction period.
during the second and third monsoons. Several areas of
severe alligator cracks also developed shallow and deep 3.2 Pavement Design
potholes which required extensive patching. The pavement design life adopted for bituminous layers
It was decided to investigate the specific cause(s) of was 10 years of stage construction option and the
premature pavement distresses on the entire project by underlying base and subbase layers were designed for
full operation period of 20 years. Both the bituminous
systematic sampling and testing so that suitable remedial
and granular layers design life period was adopted as per
measures could be recommended.
Indian Roads Congress IRC:37–2001, “Guidelines for
2. OBJECTIVE Designing Flexible Pavements”.
The objectives of this investigation were (a) prepare a For the entire project road (new construction and
systematic pavement evaluation plan for each section; reconstruction of existing lanes) flexible pavement
(b) conduct a visual inspection of the pavement surface; thickness was adopted in accordance with IRC:37-2001
1. Associate Director Emeritus, National Center for Asphalt Technology (NCAT), Auburn University, USA (currently at Jaipur)
Email: pkandhal@gmail.com
2. Professor of Civil Engineering, Indian Institute of Technology Madras, Chennai, Email: av@iitm.ac.in
and strengthening of the existing two-lane carriageway Bituminous Macadam (DBM) layers was considered as
flexible overlay thickness was adopted in accordance 1700 MPa and the Poisson’s ratio for BC and DBM layer
with IRC:81-1997. The four-lane pavement design was was considered 0.5. The statistical level of reliability
completed using the mechanistic method of pavement used in the design was 80 percent. Design CBR of 15%
design. was considered.
Vehicular movement on the project road indicated that The VDF values adopted in pavement design based on
the traffic pattern was significantly different along the traffic survey for two-axle, three-axle and multi-axle
length of the project. Therefore, this project road was tracks are 1.40, 2.57 and 3.27 respectively for the up
divided into two different homogenous sections as direction and these values were 2.30, 5.69 and 15.10 in
shown in Table 1. the down direction.
Table 1: Homogeneous Section-wise Cumulative Traffic The actual tensile strain values were calculated using in
the FPAVE program as per IRC:37-2001, and the actual
Homogeneous Design Chainage, 10 Year msa
strains were computed using various trial pavement
Section km
LHS RHS structural layer combinations. The tyre pressure used for
1 0+000 to 35+000 70 70 the analysis was 0.56 MPa and standard axle used was
dual type, having a mass of 8160 kg. This resulted in
2 35+000 to 50+000 68 95 consideration of single tyre load of 20,500 N.
The pavement temperature was considered as 35°C. In Pavement thicknesses adopted
accordance with IRC:37-2001, the resilient modulus Tables 2 and 3 show homogeneous section-wise adopted
(Mr) of the Bituminous Concrete (BC) and Dense MSA, CBR and pavement thickness values.
Table 2: Thickness of Pavement Layers (LHS Side)
The thickness of BC ranged from 40 to 50 mm whereas Specifications. The subgrade was constructed using
the DBM consisted of a single layer 100 mm thick. soils with 15% CBR from identified borrow areas. The
3.3 Pavement Construction and Quality Control pavement design was based on the 4-day soaked CBR
at maximum dry density. The construction and quality
General
control tests were carried out as per agreed Project
The pavement layers’ construction was carried out with Quality Plan.
the materials satisfying the “MORTH Specifications for
Granular Subbase (GSB)
Road and Bridge Works (4th Revision)”. The Project
Quality Plan (PQP) was submitted and approved by The construction of GSB was carried out as per Clause
Independent Engineer. The construction activities were 401 of MORTH Specifications (4th Revision). Grading
carried out as per the submitted PQP. The detailed I as per Table 400-1 was used. The construction and
description of various layers of construction is described quality control tests were carried out as per agreed
below: Project Quality Plan.
Subgrade Wet Mix Macadam (WMM)
The construction of subgrade was carried out as per The construction of WMM Layer was carried out as per
the specifications of the clause 305 of the MORTH Clause 406 of MoRTH (4th Revision). The construction
and quality control tests were carried out as per agreed from this test pit. [This was later changed to an
Project Quality Plan. extra 150-mm diameter core because the pits were
Bituminous Layers taking too long. This extra core was brought to the
testing laboratory; warmed at 110 °C; and opened
The BC and DBM layers were constructed in the project to examine stripping, if any.]
as follows:
• Five (5) test pits along the edge of the pavement near
The BC layer was constructed with Polymer Modified shoulder to test the in-situ density of WMM, GSB,
Bitumen Grade PMB-40. The DBM layer was and subgrade and take samples of all three both
constructed with VG-30 Bitumen. The bituminous layers’ for determining in-situ moisture content, optimum
construction was carried out after duly applying the moisture content, optimum dry density; gradation
prime coat and tack coat as per MORTH specifications. and PI in the laboratory. Subgrade samples were
The construction of DBM and BC layers were carried out also used to determine the in-situ CBR values.
as per the clause 507 and 509 of MORTH Specifications. • Two (2) coring right on the crack to examine the
All aggregates met the MORTH requirements. depth of the crack within the pavement (only in
4 PAVEMENT EVALUATION PLAN distressed section).
The pavement evaluation plan consisted of the following Total number of samples to be collected from project
steps: site and pits to be dug in both poor and good sections:
4.1 Review of Mix Designs • 150-mm diameter cores = 6×2 = 12
• 150-mm diameter cores directly on cracks = 2 ×1 =
Hot mix asphalt mix designs of BC and DBM involved
2 (poor sections only)
in the construction of this project were studied in detail
• Edge pits for testing WMM, GSB, and subgrade =
before inspection of the projectroad to ensure Marshall
2×3×5 = 30
Mix Design data met the specifications.
4.2 Sampling Plan
It was proposed to locate a representative “distressed” or
poor section and a relatively “good” section on this project.
These sections were intended to be at least 500 m long;
cores to be obtained in the lane adjacent to the median,
which carries truck traffic; and cores to be obtained in
the wheel track near the median in that lane. This type of
approach for systematic pavement investigation has been
used successfully across the world by the first writer in
the past[1]. Comparison of the test data from relatively
good and poor areas is generally helpful in isolating the
cause(s) of poor performance. Moreover, it also gives the Fig.1. Sampling Plan
general range of pavement test properties on the project 4.3 Testing Plan
being investigated. This approach is highly successful if
only one primary distress type is being investigated, it Full depth cores of BC and DBM were brought to the
may be cracking; rutting; or raveling/potholes. laboratory and evaluated for poke marks (generally
indicate inadequate density) and stripping. Layer
Fig.1 shows the sampling plan for a typical “distressed” thicknesses were measured before sawing to separate
(poor) or “good” section which involves the following: BC and DBM layers. Also, the bond between the two
• Five (5) 150-mm diameter cores to comprise BC asphalt layers was evaluated before sawing. Bulk
and DBM layers (subjectively evaluate the adhesion specific gravity was obtained for BC and DBM layers.
between the two asphalt layers during coring). Cores were then warmed at 110°C or so to crumble them
• One (1) small test pit about 750 mm by 750 mm and evaluate % stripping in the mix, if any. Photograph
in the middle of the 500 m test section in line were taken of some typical stripped mixes. Extraction
with cores to visually examine the condition of test was then conducted on the loose, crumbled mix
in-situ BC and DBM (especially stripping). Also, to determine bitumen content and gradation. Gmm was
obtain samples of BC and DBM for determination measured on the loose mix of BC and DBM obtained
of maximum specific gravity (Gmm) of the mixes from the extra 150 mm diameter core. Gmm was measured
after heating and remixing the loose mix to ensure all with white fines from the WMM had oozed out of the full
aggregate particles are coated with bitumen. depth cracks in Fig. 3.
Total number of Tests Core taken directly on the crack (Fig. 5) showed the
• Measurement of thickness of each asphalt layer in bottom up crack traversing both DBM and BC. That is
full depth cores = 2×2 × 5 = 20 why; fines from the WMM were brought up to the road
• Bulk specific gravity of cores = 2×10 = 20 surface by moisture/water.
• Gmm of loose samples (BC and DBM) obtained from All core samples were brought to the testing
extra cores = 2 ×2 = 4 laboratory and tested. As mentioned earlier, in lieu
• Visual evaluation of stripping in 2 layers of all cores of excavating a 750 mm by 750 mm pit, an extra
= 2×10 = 20 150-mm diameter core was taken which was warmed
• Extractions (bitumen content and gradation) of BC in the laboratory at 110°C opened up, and both BC
and DBM=2×10 = 20 and DBM evaluated for stripping. Table 4 gives the
• WMM Tests (in-situ moisture content; in-situ details of thicknesses, condition of bond between
density; optimum dry density; optimum moisture DBM and BC, and observation of stripping within
content; gradation; and PI = 10 mixes for all cores.
• GSB Tests (in-situ moisture content; in-situ density;
optimum dry density; optimum moisture content;
gradation; and PI = 10
• Subgrade Tests: gradation; moisture content; LL;
PL; PI; in-situ density; and in-situ CBR = 10
4.4 Summary and Tabulation of Test Data
All necessary calculations such as % air voids and %
compaction of WMM and GSB were made. Then, all
test data were tabulated along with JMF values and
specification limits. Mean, standard deviation, and 95%
confidence limits (CL)were calculated for all 5-test data
each for relatively good and poor (distressed) sections and
reported on one sheet for comparison. The meaning of 95%
CL means: if 100 samples (not 5) are taken of the same
material, 95 samples would statistically have the property
within the CL or range. Thicknesses of bituminous courses
and bond between the DBM and BC (yes or no) were also Fig. 2. Typical Fatigue Cracking
reported on one sheet for each section.
5. VISUAL INSPECTION, TEST RESULTS,
CONCLUSIONS, AND RECOMMENDED
REMEDIAL MEASURES
Tentative selection of relatively good and poor areas
was made prior to the field inspection based on details
of distresses noted after the first monsoon since
construction. These areas were then finalized during this
inspection.
Both good and poor areas were selected on normal height
embankments. Although road surface appeared to be dry
and raveled at many places, the predominant distress
on this road is medium to high severity (alligator)
cracking mostly on the wheel tracks of the inside lane
(next to median). Fig. 2 shows typical fatigue cracking
(sometimes in form of block cracking) in the lane. Figs.3 Fig. 3. Close-up View of Fatigue Cracks also Showing White
and 4 show close-ups of the cracks. Note that water laden Stains of Fines Brought up from WMM
In-Situ Air Voids: At the present time, the mean air voids in Grading 1 is also prone to segregation and potholing
good and poor areas are 9.0 and 8.8 percent, respectively. which was also the case on this project[2].
This is unacceptable because at the time of construction
WMM (Table 7)
more than two years ago these values must have been
10% or even more. The DBM was also used by traffic Gradation: Although within the specified MORTH
before laying the BC, which causes some densification. range, the gradation of WMM both in good and poor
MORTH does not allow more than 8% air voids at the areas is on the fine side. The material passing 0.075
time of construction. As discussed in detail in BC above, mm should not exceed 8% as per MORTH. However,
high air voids cause the mix to be brittle (due to aging) it is excessive: 13.4% in good area and 13.7% in poor
and prone to raveling and cracking. Asphalt pavement area. According to Yoder[3], excessive fines interfere
with more than 8% air voids has interconnected voids with the interlocking of aggregate in the WMM and
which allow water intrusion into the pavement during therefore lower its structural strength. Once water gets
rains. That is why, such pavements develop problems into the WMM through cracks in the asphalt courses,
such as potholes during the monsoon. it becomes weaker and weaker and does not provide
As a rule, DBM Grading 1 which was used on in this adequate support to the overlying asphalt courses. Fines
section is generally more permeable than DBM Grading from the WMM have been brought to the road surface as
2 and therefore should not have been used at all. DBM mentioned earlier (Fig. 3).
Table 4. Condition of Cores
MORTH Good Area Poor Area
Spec. or
Test Property Location no. Std. Location no. Std. 95%
Project Mean 95% CL Mean
Spec. 1 2 3 4 5 Dev. 1 2 3 4 5 6 Dev. CL
109-
Thickness, mm 143 145 122 133 112 131 14 103-159 131 141 118 129 116 136 129 10
149
76-
DBM 100 101 102 79 92 75 90 12 66-114 104 97 83 89 86 102 94 9
112
BC 40 or 50 42 43 43 41 37 41 2 37-45 27 44 35 40 30 34 35 6 23-47
Bond between
Yes Yes Yes Yes Yes - - - Yes Yes Yes Yes Yes Yes - - -
DBM and BC
% Stripping in Mix
DBM None None
BC None None
Plasticity Index (PI): According to MORTH, PI of However, the mean density is 95% in the good area and
WMM should not exceed 6 percent. However, it is much lower, that is, 92% in the poor area. Both values
borderline (6) in the good area and exceeds (7) in the indicate inadequate compaction in the field, which
poor area. WMM with high PI, lose strength in presence further reduces the strength of the WMM.
of water. Granular Sub-Base (GSB) (Table 8)
In-Situ Density: The in-situ density of WMM should Gradation: The gradation of GSB in the poor area is
be at least 98% of optimum dry density (MORTH). finer all the way and is outside the range of MORTH
caused the premature distresses. This is rather unusual. iii. Intrusion of rainwater in the pavement system
Generally, one or two pavement courses are substandard from the surface including the full depth cracks is
in the poor area and therefore can be isolated as cause(s) causing serious problems in terms of disintegration
for premature distress. (potholes/loss of surface). The recommended
overlay system must ensure “complete sealing” of
Recommended Remedial Measures
the existing pavement.
This project experienced substantial distresses during the iv. The existing pavement has bottom up fatigue
first, second and third monsoons since it was constructed. cracking and therefore may not provide resistance
As immediate measure, all potholes should be repaired. to tensile strains. The new asphalt overlay must
The areas which show severe loss of road surface have its “own” reinforcement system to (a) resist
should be milled off and replaced with BC Grading 2 tensile strains at its bottom; (b) arrest cracking; and
(with gradation on the finer side of the JMF) containing (c) increase its fatigue life.
elastomeric PMB-40. [This work was carried out soon v. Despite its “own” reinforcement, the new asphalt
after this field evaluation.] These measures would ensure overlay would be subjected to extraordinary
the safety and comfort of the motoring public. stresses and strains due to inadequate support of
Then, pavement deflections should be measured on the the underlying courses. Therefore, the new asphalt
entire project using a falling weight deflectometer (FWD) overlay should be more flexible than BC Grading
which is more reliable and faster than the Benkelman 2; resistant to reflection cracking; and highly rut
Beam. Plot the results on a linear graph. Use IRC:81- resistant at the same time.
1997 to determine the thickness of asphalt overlay to Ideally, all pavement courses which are substandard
bring deflections below the acceptable level or IRC:115- should be replaced. However, it is not practical nor
2014 should be used. economical. Therefore, the following remedial measures
Conduct a “broad” survey of the road surface in this are recommended for Type A Category:
section to identify the following three (3) road surface i. Mill off the existing BC Grading 2 exhibiting
categories: alligator cracks and/or block cracking and replace
Type A with BC Grading 2 (redesigned with finer gradation)
containing elastomeric PMB-40 from a reliable
Road surface showing “severe” fatigue cracks (alligator international supplier. Ensure good quality control
type) in the wheel tracks and/or block cracks in the entire in mix production and compaction.
lane. ii. Provide a composite (combination) of non-
Type B woven geotextile (GT) paving fabric (which is
Road surface showing “moderate” fatigue cracks (one or continuous and has polyester and glass fibers) and
two longitudinal cracks in the wheel track). This surface a glass fiber grid reinforcement. The quality of the
is likely to become Type A in the near future. composite GT should conform to IRC: SP:59-2002.
Application should consist of heavy tack coat of
Type C VG-30 bitumen (not emulsion) at a rate specified
Surface showing no fatigue cracks. There is no guarantee by the manufacturer of GT paving fabric. The
that fatigue cracks would not appear in the future given nonwoven geotextile together with heavy tack coat
the substandard quality of underlying pavement courses would ensure “complete sealing” of the existing
(even in the good areas) unless proven otherwise with pavement. The glass fiber geogrid would provide
additional explorations like this one. “reinforcement” to the overlying 50 mm asphalt
Type A Recommended Remedial Measures overlay to resist tensile stresses at its bottom. It
would also prevent lateral movement of the overlay
Any suggested remedial measures should take into asphalt mix.
consideration the following: iii. Provide 50 mm of Stone Matrix Asphalt (SMA)
i. All or most of the pavement courses are substandard in accordance with IRC:SP:79-2008 (drafted by
in quality. the first author) containing elastomeric PMB-40
ii. Alligatored BC cannot be kept within the pavement over the composite geotextile. A minimum asphalt
system because it is shattered and therefore likely overlay thickness of 50 mm is required over
to cause problems in future if overlaid without geotextile. Although SMA is preferred, BC Grading
removal from the distressed areas. 2 with highly modified asphalt binder HiMA can
also be considered. HiMA has about 7% SBS systematic sampling and testing so that suitable remedial
polymer compared to about 3% SBS in conventional measures could be recommended.
PMBs. Research at NCAT Test Track in the US has In general, good quality control of various pavement
shown it is highly resistant to rutting and fatigue courses was not exercised during construction, which
cracking. Due to its higher structural strength, 41 led generally to the development of “bottom up”
mm of BC with HiMA is approximately equivalent fatigue cracking on this project. The following general
to 50 mm of BC with conventional PMB. HiMA is deficiencies were noted on this project:
commercially available in India.
Subgrade: CBR values from the trial pits of 6 in good
iv. If the pavement deflection analyses show that
area and 4 in the poor area were less than the CBR value
asphalt overlay should be more than 50 mm, then
of 15 used in the structural design of this project. This
additional BC Grading 2 overlay should be provided
apart from inadequate compaction of the subgrade layer
prior to laying the geotextile.
resulted in an under designed pavement.
Type B Recommended Remedial Measures
Granular Subbase (GSB): Gradation; plasticity
Same as Type A above except that the existing BC need index (PI) and % compaction did not meet MORTH
not be milled off and replaced. However, all potholes and requirements. This results in poor subsurface drainage
surface deficiencies of existing BC should be corrected. and inadequate support to the overlying pavement
Cracks over 5 mm wide should be filled with hot asphalt- courses especially in presence of water.
rubber or hot VG-30 bitumen. Do not use emulsion
which would shrink when about 35% water contained in Wet Mix Macadam (WMM): Gradation; plasticity
it evaporates. index (PI) and % compaction did not meet MORTH
requirements. This results in weak WMM which provides
Type C Recommended Remedial Measures inadequate support to the overlying pavement courses
In case the deflection analysis does not require any especially in presence of water.
asphalt overlay, apply Microsurfacing Grade III (6 Dense Bituminous Macadam (DBM) Base Course:
to 8 mm) in accordance with IRC:SP:81-2008 to the DBM has excessive air voids (due to inadequate
existing road surface to seal it from moisture intrusion compaction) which allow water intrusion during rains
as a preventive maintenance. Then, it would be a matter causing potholes. High air voids also make the mix more
of “wait and watch”. If fatigue cracks start to develop, prone to cracking. Some DBM mixes contained soft,
use Type B remedial measures. In case, the deflection friable aggregate most likely from quarry overburden.
analysis requires an asphalt overlay, use 40 mm or 50 Also, traffic allowed on the DBM during construction
mm SMA rather than BC Grading 2 considering the before placing the BC can induce bottom up fatigue
substandard quality of underlying courses, unless proven cracking in it. These cracks then reflect though the BC
otherwise after explorations like this one. at a later date.
6. SUMMARY Bituminous Concrete (BC) Wearing Course: Deficient
On completion of the four-laning of this 50-km national bitumen content; gradation outside JMF tolerances
highway, premature pavement distresses were observed (generally coarser which allows intrusion of rainwater);
on it during the first monsoon. The following pavement and high air voids (due to poor compaction) made the mix
distresses were observed: open surface texture; raveling; more prone to cracking. Some BC mixes contained soft,
hungry surface; alligator cracks; and potholes. By far, friable aggregate most likely from quarry overburden. In
premature fatigue cracking was the primary distress most cases, BC did not provide an impermeable surface
ranging from moderate cracking (one to two cracks in for the pavement to prevent water intrusion.
wheel path) to severe cracking (alligator cracks in the Based on preceding deficiencies, all five pavement
wheel path or block cracks across the lane). Therefore, courses were substandard in quality. This resulted in a
this was the primary focus of this investigation. rather complex investigation, where the relatively good
Further successive deterioration of pavement occurred area also had serious deficiencies in case of some test
during the second and third monsoons. Several areas of parameters.
severe alligator cracks also developed shallow and deep It has been recommended that pavement deflections
potholes which required extensive patching. should be measured on the entire project using a falling
It was decided to investigate the specific causes of weight deflectometer (FWD). Plot the results on a linear
premature pavement distresses on the entire project by graph. Use IRC: 81-1997 or IRC:115-2014 to determine
the thickness of asphalt overlay to bring deflections asphalt (SMA). If two sets of extractions (bitumen
below the acceptable level, wherever needed. content and gradation) and Marshall tests are faithfully
Conduct a “broad” survey of the road surface on the done every day as per MORTH requirements, there is no
entire project to identify the following three (3) road reason as to how the quality can be compromised.
surface categories: 7. GENERAL RECOMMENDTIONS
Type A: Road surface showing “severe” fatigue cracks The following general recommendations are made so
(alligator type) in the wheel tracks and/or block cracks that major highways do not develop premature distresses
in the entire lane. as observed on this project:
Type B: Road surface showing “moderate” fatigue cracks (a) The pavement design life should not be based on
(one or two longitudinal cracks in the wheel track). This “stage construction” such as 10 years. Rather, it
surface is likely to become Type A in the near future. should be for the full operational period.
Type C: Surface showing no fatigue cracks. There is (b) Construction quality control (QC) needs to be
no guarantee that fatigue cracks would not appear in exercised by the contractor and quality assurance
the future given the substandard quality of underlying (QA) should be exercised by the concessionaire/
pavement courses (even in the good areas) unless proven Independent Engineer (IE) – both were lacking on
otherwise with additional explorations like this one. this project.
Type A Recommended Remedial Measures (c) DBM base course should not be used by traffic for
long periods of time; it should be overlaid with BC
Details are given in the body of this paper. Briefly, remedial
as soon as possible so that bottom-up fatigue cracks
measures consist of (a) mill off existing BC Grading 2
and replace with new BC Grading 2 with elastomeric do not develop in DBM due to reduced pavement
PMB-40 Bitumen; (b) provide a composite geotextile thickness.
paving fabric and glass fiber grid reinforcement; and (c) (d) Although not applicable to this project, the thickness
provide 50 mm of Stone Matrix Asphalt. of DBM should not be reduced when modified
binders are used. This is technically unwarranted
Type B Recommended Remedial Measures
and would further aggravate the problem of under
Same as Type A above except that the existing BC need designing the pavement structure.
not be milled off and replaced. However, all potholes and (e) If subgrade is constructed with high CBR soil from
surface deficiencies of existing BC should be corrected. identified borrow areas, it should be ensured that
Cracks over 5 mm wide should be filled with hot asphalt- local soil with low CBR value is not used.
rubber or hot VG-30 bitumen, not emulsion.
8. BIBLIOGRAPHY
Type C Recommended Remedial Measures
1. Kandhal, Prithvi Singh, “Bituminous Road
In case the deflection analysis does not require any Construction in India”. Textbook. Prentice Hall of
asphalt overlay, apply Micro surfacing Grade III (6 to 8 India, New Delhi, July 2016.
mm) in accordance with IRC:SP:81-2008 to the existing
2. Kandhal, P.S. and A. Veeraragavan, “Review of
road surface to seal it from moisture intrusion. Then, it
Practices for Improving Ride Quality and Periodical
would be a matter of “wait and watch
Renewal of Bituminous Pavements in India”. Paper
Quality Control No. 662. Journal of the Indian Roads Congress,
In all remedial measures, strict quality control need to Volume 77-3, October-December 2016.
be exercised during bituminous mix production and 3. Yoder, E.J., “Principles of Pavement Design”. John
compaction. It is especially important for stone matrix Wiley & Sons, New York, 1965.