You are on page 1of 3

Table for HAZOP Studies

St ID: 0419022037 Name: Mysha Momtaz


Study node: Ammonia solution feed line to the DAP reactor
Parameter Guide word Possible causes Possible consequences Existing safeguards Required actions/
(deviation) recommendations
Flow No 1. Flow control valve A fail close 1. Possible accumulation 1. Flow indicator and 1. No flow alarm
2. Sensor or flow indicator of unreacted controller 2. Redundant flow control system
failure phosphoric acid into the 3. Independent and uninterrupted
3. Plugging of line reactor if valve C is power supply for control
4. Leakage or rupture in line closed system
5. No feed material in the 2. Unreacted phosphoric 4. Periodic maintenance and
ammonia solution storage acid carried over to the inspection for valve A
tank DAP storage tank and
lead to corrosion

High 1. Flow control valve A fail open 1. Possible accumulation 1. Flow indicator and 1. High flow alarm
2. Sensor or flow indicator of unreacted ammonia controller 2. Redundant flow control system
failure inside the reactor if 2. Pressure safety 3. Independent and uninterrupted
valve C is closed and valve on the power supply for control
phase change due to storage tank and system
any increase in reactor 4. Periodic maintenance and
temperature and 3. Ammonia detectors inspection for valve A
pressure leading to and alarms 5. Flow control valve fail close
explosion
2. Unreacted ammonia
carried over to the DAP
storage tank and
release into the
enclosed work area
Low 1. Partial failure of flow control 1. Possible accumulation 1. Flow indicator and 1. Low flow alarm
valve A or control valve of unreacted controller 2. Redundant flow control system
stiction phosphoric acid into the 3. Independent and uninterrupted
2. Plugging of line reactor if valve C is power supply for control
3. Leakage or rupture in the line closed system
4. Shortage of feed material in 2. Formation of an off- 4. Periodic maintenance and
the ammonia solution storage specification product inspection for valve A
tank due to the abundance
5. Operator sets ammonia of phosphoric acid in
solution flow rate too low the reactor
3. Unreacted phosphoric
acid carried over to the
DAP storage tank and
lead to corrosion

Temperature High 1. No adequate insulation 1. Phase change of 1. Pressure safety 1. Adequate insulation around the
around the pipeline ammonia and possible valve on the pipeline
2. Unusual rise in ambient explosion due to reactor and storage 2. Temperature Indicator in the
temperature increase in pressure tank pipeline
2. High energy release due 3. High temperature alarm
to high reaction rate at 4. Ammonia solution cooling
high temperature system
leading to explosion
Low 1. Unusual fall in ambient 1. No significant
temperature consequence
Pressure High 1. Temperature rise of ammonia 1. Possible explosion of 1. Pressure safety 1. Adequate insulation around the
solution reactor valve on the pipeline
reactor and storage 2. Temperature Indicator in the
tank pipeline
3. High temperature alarm
4. Ammonia solution cooling
system
Low 1. Plugging of line 1. Decrease in reaction 1. Ammonia detectors 1. Regular inspection and
rate and possible and alarms maintenance of pipeline
accumulation of condition
unreacted ammonia
inside the reactor
carried over to the
storage tank and
enclosed work area

You might also like