Task
Task Main Module Sub-Modules Timelin
No.
es
Provide basic training on MyEasyISO to the core team and
1 All IMS modules • All QHSE related modules Day 1-3
users to familiarize themselves with MyEasyISO.
Task
Task Main Module Sub-Modules Timelines
No.
Top Management shall create life cycle management for IMS → QMS →Context of
8 different products at different stages and identify control Organization • Life Cycle management Day 17-18
action which may affects the environment.
9 QHSE Manager shall define QHSE Policy. IMS → QMS →Policy & • Policy Day 19
Objective
10 QHSE Manager shall determine QHSE Objectives. IMS → QMS →Policy & • Objective Day 20-22
Objective
11 Identify at least two critical processes for each department. IMS → QMS → Operations • Process Identification Day 23-26
HSE Manager shall establish: IMS → HSE →HSE Planning
12 • Aspect - Impact Assessment
a. Aspect - Impact Assessment (Environment) Day 27-30
b. Hazard - Risk Assessment (Health and Safety) • Hazard & Risk Assessment
HSE manager shall determine compliance obligation related IMS → HSE →Compliance
13 Obligation • Compliance Obligation Day 31-32
to HSE.
Define ideal competence for designation and carry out • Ideal Competence
14 IMS → QMS → HR • Competence Evaluation Day 33-34
competence evaluation for all employees.
• Training Identification
QHSE Manager shall determine QHSE Training for
15 IMS → QMS → HR • Training Attendance Day 35 -36
employees.
• Training Evaluation
Create offline communication policy -
16 whom, what and how to communicate QHSE-related IMS → QMS → • Offline Communication Policy Day 37-38
communications to employees and Interested parties Communication
Task
Task Main Module Sub-Modules Timelines
No.
Complete Operations-related requirements: IMS→ QMS→ Operations
a. Create Process validation for special processes like • Process Validation
Welding and Coating where output cannot be • Operations Planning
22 measured. • Work Order Execution Plan
b. Create Operational Planning for products/services • External Property
c. Create Work Order and Execution Plan for Closed • Monitoring Evaluation Day 58-62
deals/New projects
d. Update the property/resources received from
Customers and Suppliers
e. Create Monitoring Evaluation(KPI) for any applicable
process
IMS → QMS →
Create/Upload documents in documented information
23
Documented Information • Documents
module to capture any physical QHSE forms (Empty
template), procedure, checklist (Empty template), flowchart
and Manual to bring them under documented information Day 62-64
control.
(This module will act as Master list of Documented
Information)
Task
Task Main Module Sub-Modules Timelines
No.
Define Waste Management and monitor waste at regular
25 interval:
a. Create Profile for Air, Water and Solid Waste
b. Monitor Air, water and Solid waste at regular IMS→ HSE→ Waste • Air Emission Profile
interval. Management • Water Waste Profile
Complete this module only when below scenarios arise: • Solid Waste Profile
• Air Emission Monitoring Day 66 – 70
1. Air is polluted due to any one of your
operations/process • Water waste Monitoring
2. Water is wasted during any one of your • Solid Waste Monitoring
operations/process
3. Solid Waste is generated during any one of your
operations/process
HSE Manager shall define Hazardous material used in IMS → HSE→ HSE • Hazardous Material
26 Operations/process and create Material Safety Data Sheet Operations • Material Safety Data Sheet Day 71 – 72
related to chemical
Create work permit for Visitors / Employees (whenever
27 IMS → HSE→ • Work Permit ---
necessary)
HSE Operations
IMS → HSE→ • PPE Master PPE Inspection
Create Personal Protective Equipment used during
28
operation and carry out PPE Inspection at regular Interval
HSE Operations • PPE Process Day 73
Task
Task Main Module Sub-Modules Timelines
No.
29 Create Emergency Preparedness and capture Mock drill/
IMS → HSE→ • Planning Emergency
Actual Emergency response:
a. Create Emergency Plan
HSE Operations • Testing Emergency
b. Carry out Mock drill at regular interval (Emergency • Actual Emergency Day 74-77
testing) • Emergency Response team
c. Capture Actual Emergency (only when it happens) • Emergency Contact list
Capture Incident / Accident Investigation report for Near- IMS → HSE→ • Incident/ Injury / Accident Reporting
30 HSE Operations • Calculate LTR / TAR / ASR ---
miss, Accident and Fatal (whenever happens)
IMS→HSE→ • HSE KPI
Capture HSE performance Evaluation:
Performance Evaluation • HSE Checklist
31 a. Create HSE Checklist Day 78
• HSE Inspection
b. Carry out HSE Inspection at regular interval
IMS → QMS→ Internal
32 Prepare Master QHSE audit schedule for the whole year: Audit • Master Internal Audit plan
a. Select the departments and months (Multi-select) Day 79
within Audit Cycle year.
Task
Task Main Module Sub-Modules Timelines
No.
Capture Non-Conformance: (Any deviation from
35 Requirement)
a. Create Non-Conformance and assign responsible
person IMS→ QMS→
b. Take Correction and identify Root cause Non-Conformance • Non-Conformance ---
c. Propose a Corrective Action
d. Add the Actual Corrective Action under taken
e. Verification of Corrective Action
f. Closure of NC with final review comments
Ensure closure of proposed actions on identified dates for IMS • Respective Modules
High Significant Aspect and Hazard, Non-Conformance and Day 92-95
36 HSE operations
Conduct QHSE management review meeting and identify IMS→ QMS→ MRM
37
Action plan:
a. Invite all attendees for Management Review • MRM Day 96
Meeting
b. Capture Minutes of meeting and Action plan.
• Not Applicable
38 Coordinate with the certification body to conduct audit. Day 100