Professional Documents
Culture Documents
Earth Loop: Direct Axxess For Earthlinked Heating / Cooling and Commercial Water Heating Systems
Earth Loop: Direct Axxess For Earthlinked Heating / Cooling and Commercial Water Heating Systems
The specification of an earth loop system begins with the correct sizing of the system and
completion of the appropriate site survey form, detailed in Section 9 of this manual.
Based on this information the appropriate earth loop configuration is selected, consistent with the
following guidelines:
The following site restrictions apply to drilling or excavation operations relative to all DIRECT
AXXESS® earth loop configurations:
• Before excavating or drilling, the site must be inspected to ensure the absence of electric, gas,
water, sewer, irrigation and telephone lines.
• Excavations are subject to OSHA regulations (Federal Register; Volume 54; No. 209; Oct. 31,
1989. Rules and Regulations page 45965 [29 CRF Part 1926]).Earth loop installations are not to
be within:
a. 10 feet of a foundation, water line or drainage zone of a building downspout.
b. 50 feet of a water well, septic system, or below the collection basin of de-icing salts or
barnyard runoff.
c. One-half the branch extremities of a tree or shrub.
EarthLinked® Commercial Water Heating systems utilize sealed copper tubing earth loops to
provide excellent heat transfer to and from the earth.
Prior to specifying an EarthLinked® system, the following guidelines are to be implemented to
determine if the EarthLinked® Cathodic Protection System is required.
The local soil conditions are to be evaluated for thermal conductivity because it can be a
determining factor concerning the requirement for an Auxiliary Cooling Module (ACM) based on the
following conditions.
The selection of the correct CPS model is based on the size of the compressor unit, as shown in
Figure 3.
Compressor Unit Cathodic
Sizes Protection System
-018 CPS-1830
-024 CPS-1830
-030 CPS-1830
-036 CPS-3642
-042 CPS-3642
-048 CPS-4872
-060 CPS-4872
-068 CPS-4872
-072 CPS-4872
When earth loops are ordered by the model numbers, they come complete and ready to install. All
earth loop systems include the manifolds. The line set to connect the manifolds to the
compressor unit is field supplied.
The advantage of the diagonal earth loop system is that it requires a smaller footprint (8 ft.
diameter circle) than the vertical design and therefore lends itself to smaller spaces and
retrofit applications. The earth loop plan layouts for the vertical and diagonal configurations
are detailed in Section 11.
All earth loop system s include the manifolds.
The line set that connects the manifolds to the compressor unit is field supplied.
Horizontal-Pit and Horizontal-Trench configurations are installed 5 to 6 feet under the earth
surface (no less than 1-1/2 feet below the frost line), in at least two geometric variations of each,
making these earth loop designs more compatible with the available earth surface geometry. As a
rule-of-thumb, for horizontal installations, the area of disturbed earth surface is 500 square feet per
ton of heat pump capacity.
R-410A
Horizontal Pit Earth Loop System
• 5 loops per ton
• 100 feet length per loop
• 5 to 6 feet typical depth of pit
(18 inches below frost line)
R-410A
Horizontal Trench Earth Loop
System
• 1 loop per ton
• 250 feet length per loop
• 4 to 6 feet typical depth of pit
(18 inches below frost line)
1. Compare the label on the Earth Loop packaging with ordering and shipping information to verify
the correct equipment has been shipped.
2. Verify refrigerant tubing is free of kinks and dents (see Figure 8a and 8b).
3. Inspect all manifolds. Connections must be free of kinks and dents (see Figure 9).
Check the earth loop to see that it is sealed, by quickly depressing and releasing the service valve
stem at the end of the earth loop liquid (smaller) tube. The rushing sound of escaping nitrogen gas
ensures that the earth loop is sealed.
Earth loops should be stored in a clean, dry area. Keep earth loops in original packaging until
installation.
If it is necessary to store earth loops on a job site, keep earth loops in their original packaging and
cover with other shipping cartons, vinyl film or an equivalent protective covering. In areas where
construction activities are taking place, all due precautions must be taken to avoid physical damage
to the earth loops and contamination by foreign material. Physical damage and contamination may
prevent proper start-up and may result in costly equipment clean up. Examine all earth loop
components before installing.
See Section 12 for tools and equipment required to install a DIRECT AXXESS® Earth Loop
System.
After locating the manifolds per distances A and B, record this information on the DIRECT
AXXESS® Warranty Registration (LIT-64). A copy is shown in Section 13.
Provide a copy of this completed form to the owner.
4. Vertical/Diagonal Installation
a. Site Preparation and Bore Holes
Lay out the bore hole circle and location of each bore hole with spray paint or flag markers,
consistent with the selected DIRECT AXXESS® Earth Loop System per the appropriate
configuration in Section 11.
Diagonal bore hole patterns may be laid out on an 8 feet diameter circle. The space diagrams
for diagonal bore hole patterns in Section 11 are based on an 8 feet diameter circle.
Drill bore holes at least 3” diameter to allow for appropriate grouting operations. Bore holes are
to be drilled to a depth consistent with (1) the length of the earth loop and (2) the braze joint
connections to the manifolds in the manifold pit. Details of the manifold pit connections are
shown in Figure 10.
Maintain each earth loop the same length. Do not shorten an earth loop. If it is too long, bend or
coil it in a radius no smaller than 1 ft. to take up the extra length. It is critical that each earth loop
have the same length to ensure normal system performance.
It is recommended that the bore hole angle for diagonal installations not exceed 45° because
above this angle a consistent grout fill becomes difficult to accomplish.
b. Earth Loop Installation
The earth loop bore holes are drilled to a depth appropriate to accept the specified earth loops.
The installer should check the earth loop to see that it is sealed, by quickly depressing and
releasing the service valve stem at the end of the earth loop liquid (smaller) tube. The rushing
sound of escaping nitrogen gas ensures that the earth loop is sealed.
The pressurized coiled earth loop is uncoiled and straightened in 4 to 6 ft. lengths (as a
minimum), and inserted into the bore hole. As an option, a flexible grouting hose (tremie tube)
may be fed into the bore hole with the earth loop, at the same time. If the diameter of the drilled
bore hole is large enough, the grouting hose can be inserted after the earth loop has been
lowered into place. The method is the installer’s choice.
d. Manifold Assembly
After earth loops have been inserted and grouted into the bore holes, the terminations of the
earth loops are to be connected to the manifolds as shown in Figure 10.
The vapor manifold (larger tubes) is to be located above the liquid manifold (smaller tubes)
with the vapor manifold earth loop feeders “up”, the liquid manifold earth loop feeders “down,”
as shown in Figure 10.
Typical liquid and vapor manifolds are shown in Figure 9.
First, the liquid earth loop tube terminations are cut and cleaned and fit to the liquid manifold
connections, also cleaned. The liquid line of the field supplied manifold line set is cleaned and
connected to the main port on the liquid manifold, also cleaned.
Earth Loop line set sizes for R-407C systems are shown in Figure 14a.
Prior to or after brazing the earth loop and line set to the manifolds, the line set should be
installed and run to the location of the compressor unit. The methods are shown in Figures 15a
and 15b.
If the compressor unit is to be placed outdoors, the line set is brought up through the ground
adjacent to the compressor unit back side (nearest the wall), maintaining separation of the
insulated refrigerant lines.
If the compressor unit is to be placed indoors, the line set must be run through or under an
outer wall to the compressor unit location. The following guidelines are to be used in
conjunction with Figures 16a or 16b.
1. Enter the building above grade, if at all possible.
2. Below grade entry is a source for basement wall leakage. Seal with flexible sealant that
maintains a tight seal for temperatures from -40°F to +200°F and adheres to all materials
involved.
The sealant recommended for use in building entry is DAP Silicone Ultra (100% silicone rubber
sealant, #7079811646) or equivalent. MSDS information for this product is available at
www.dap.com.
The foam recommended for use in foaming the insulated line set tubes inside the PVC sleeve is
DOW Insulating Foam Sealant (“Great Stuff”, #7498500154), which is airtight and waterproof.
MSDS information for this product is available at www.dow.com.
It is noted that after the insulated vapor and liquid lines enter the building they must continue to be
separated by an air space from the point of building entry to the compressor unit.
After all brazing has been done on the earth loops/manifolds/line set; the line set “compressor
unit ends” of the tubes are to be prepared as shown in Figure 17, in preparation for the earth
loop system seal test.
Braze a service valve into the vapor line termination and a cap onto the liquid line termination
as shown in Figure 17.
After brazing the earth loop system joints as noted above (includes manifolds, earth loops and
earth loop line set, but NOT the compressor unit or any other HVAC refrigeration system
component), the complete underground system is to be seal tested with 400 PSIG nitrogen.
After connecting a high pressure hose from the regulator on the nitrogen tank to the service
valve on the vapor line of the line set, slowly increase the nitrogen pressure to 400 PSIG,
checking for any obvious leaks audibly.
If no audible leaks are detected, check all joints to ensure they are sealed, by one of the
following methods:
1. Ultrasonic Leak Detector or Bubble Solution Leak Detector
2. Electronic Leak Detector (requires a trace amount of refrigerant in the system)
When the Earth Loop System (earth loops, manifolds and line set assembly) has been
successfully seal tested, leave 400 psig nitrogen with pressure gauge on the service valve
in Figure 17. Valve off the nitrogen source and monitor the pressure on the underground
system to ensure that 400psig has been maintained for minimum of 8 hours. After
successfully passing these seal checks, the underground earth loop system is ready for
backfilling, prior to connecting it to the compressor unit.
Monitor the pressure reading during the backfilling operation to ensure that the earth loop
system remains sealed.
g. Backfilling
Prior to backfilling the manifold pit, shown in Figure 10, add water to the pit, covering the
manifolds. The water in the pit will ensure firm compaction of the sand that is to be packed
around the manifolds and earth loop connections. Carefully pack sand around the manifolds to
EL-SIS (05/12) Page 35
ensure that the manifolds are firmly oriented as shown in Figure 10 (manifolds are shown with
proper spacing and orientation, and manifold bodies are VERTICAL as shown).
Ensure that enough sand is packed around the manifolds/earth loops/line sets that backfilling
will not move them from the indicated positions of Figure 10.
Backfill the line set trench with excavated fill if there are no rocks or sharp objects. If the backfill
has rocks and/or sharp objects, fill the earth loop trench with 2” of sand under and over the line
set and then carefully backfill the excavated fill.
5. Horizontal Pit/Trench Installation
a. Site Preparation and Excavation
Lay out the shape of the pit or trench earth loop system with spray paint or flag markers,
consistent with the selected earth loop configuration in Section 11.
Excavate to a depth of at least 5 feet and no less than 1-1/2 feet below the frost line (5 to 6
feet depth is typical). The bottom of the horizontal pit or trench system must be level
within 12” continuously from one end to the other, as shown in Figure 18.
LEVEL LINE
12" MAX.
If there are rocks or sharp objects at the pit/trench bottom, spread a 2” layer of sand or finely
crushed limestone across the bottom before installing the earth loop system.
b. Earth Loop Installation
The rolled tubing is checked for pressure at the service valve. Quickly depress and release the
service valve stem at the end of the earth loop. The rushing sound of escaping nitrogen gas
ensures that the earth loop is sealed.
c. Manifold Assembly
Assemble the liquid manifold, earth loops and manifold line set first, as shown in Figure 19, after
all copper tubes are cut to length, cleaned and deburred. (Do not add sand at this time.)
The vapor manifold earth loop tubes and manifold line set connections, are brazed after the
liquid connections are brazed. When brazing is completed on all liquid and vapor connections
at the manifolds, insulate both liquid and vapor line sets (from the manifold connection point)
with ½” wall thickness insulation (Armaflex™, Insul-Lock® or equivalent) and orient the
manifolds and earth loops in the manifold pit as shown in Figure 19, ensuring that the two
manifolds are vertical. Add water to shored-up area around manifolds and earth loop
EL-SIS (05/12) Page 38
connections to cover the manifolds. This will ensure firm compaction of the sand that is to be
packed around the manifolds and earth loop connections. Carefully pack sand around the
manifolds to ensure they are firmly oriented vertically.
d. Line Set
Follow the instructions in Section 4e of this manual.
e. Seal Test
Follow the instructions in Section 4f of this manual.
f. Soaker Hose Installation
FOR THE PIT INSTALLATION, the soaker hose is installed directly on top of the copper earth
loop system, as shown in Figure 20.
1. Install the soaker hose (perforated hose) on top of the copper tubing so as to evenly
distribute water over the site during soaking.
2. The solid (non-perforated) portion of the hose must run from the perforated portion of the
soaker hose to a faucet.
3. After backfilling, run the soaker hose assembly at full flow for 24 hours.
4. Do not operate the system in the heating mode for two (2) weeks to allow water to
percolate away from earth loops.
FOR THE TRENCH INSTALLATION, the soaker hose is installed after partial back filling of
the trench is completed as shown in Figure 21. This technique reduces the potential for the
backfilled earth to “bridge” across the trench and impair earth loop heat transfer.
Follow the preceding instructions for the trench soaker hose installation and operation, except
place the soaker hose within 2 ft. of the ground surface directly above the earth loop.
Run at full flow for 24 hours, as shown in Figure 21. Do not operate the system in the
heating mode for two (2) weeks to allow water to percolate away from earth loops.
g. Backfilling
Prior to backfilling the pit or trench earth loop system, carefully pack sand around the manifolds,
as shown in Figure 19 to ensure they are firmly oriented and will not be moved during the
backfilling operation.
If there are rocks or sharp objects in the backfill, put a 2” layer of sand under and over the earth
loop and manifold line set lines before backfilling.
Backfill the pit or trench system by gradually moving backfill progressively across the copper
lines. Do not dump or drop backfill onto the earth loop, manifolds or manifold line set.
See Figure 22.
After backfilling the pit or trench earth loop system, run the soaker hose as detailed in Section 5f
at full flow for 24 hours.
For horizontal earth loops, the corrosion protection system anode should be located at least 20
feet away as shown in Figure 23. No METAL pipes, wires or other objects should be between the
anode and the earth loops. The horizontal anode installation as shown in Figure 25 is
preferred for horizontal earth loops; however, the vertical anode installation as shown in Figure
24 is fully acceptable.
It is recommended that the vapor line wire lead be connected near the compressor unit to the earth
loop vapor line of the line set connecting the compressor earth loop vapor line to the earth loop
manifolds, as shown in Figure 28. It is, however, satisfactory to connect the vapor line wire lead to
the earth loop liquid line coming out of the compressor unit.
Details for installing the vapor line wire clamp to the earth loop vapor line follow, with reference to
the illustration in Figure 28.
1. Insert bolt assembly into strap hole marked “INSERT SCREW HERE.”
5. Loosen set screw, insert vapor line wire lead and tighten.
The green indicator light on the front of the CPS control will illuminate to show the CPS system
is operating.
The CPS control is equipped with an audible signal to indicate that service is required due to an
interruption between the CPS control and the anode or vapor line connections.
In the event the audible signal is triggered, or the green panel light goes out, pull the power
cord from the wall socket. Then:
1. Check all connections and wire continuity between the CPS control and (1) the anode and
(2) the vapor line connection, and repair as appropriate.
2. Looking at the front of the CPS control in Figure 28, check the fuse on the far left for
continuity. This is the line voltage fuse. Replace as necessary with a 3AG Slow Blow panel
access fuse.
3. Looking at the front of the CPS control in Figure 28, check the fuse second from the far left
for continuity. This is the anode fuse. Replace as necessary with a 3AG Fast Blow panel
access fuse.
5. With a sensitive, high quality refrigerant leak detector, determine if one of the joints at the
manifold connections leaks. If not, go to step 9. If so, recover the refrigerant through a service
valve Schrader port and re-braze the leaking joint with 15% silver brazing alloy after brazing
with nitrogen as described in section 4d of this manual.
6. Test the system at 150 psig using nitrogen to check the seal at the repaired joint and the other
manifold connection.
7. The earth loops must be evacuated and the system recharged with refrigerant. This is to be
done in accordance with the appropriate Installation, Operation and Maintenance Manual.
8. Recharge the system in accordance with the procedure described in step 7 and proceed to
back fill.
9. However, if none of the manifold joints indicate a leak, then each of the earth loops must be
checked individually until the leaking earth loop is found.
10. To check each earth loop, do the following:
a. Cut the liquid and vapor earth loop refrigerant tubes (for ONE earth loop) 12” from each
manifold. Braze the cut end of the liquid (smaller) earth loop line to seal it and braze a
Schrader valve onto the cut end of the vapor (larger) earth loop line.
b. Pressurize the earth loop with nitrogen, through the Schrader valve, to 400 psig. Close the
nitrogen supply valve and observe if the pressure drops continually, indicating a leak in that
earth loop.
c. If the pressurized earth loop does not experience a continuous pressure drop, the earth loop
is leak-free and can be rebrazed to the manifold where the tubes were cut.
d. This procedure is repeated on each earth loop (vapor and liquid line) until the leak is found.
It is good practice to check each of the earth loops in the event there is more than one leak.
e. Repeat the process described in steps 5 through 8 above.
Job Name:
Location:
Note: Taking photos where the appears next to an item is good documentation. Take photos of
any other items you feel would be important to the installation of new equipment.
1. Determine the applicable regulations and codes governing the drilling of bore holes and
excavating for the site. Explain:
2. Show space available for earth loop system in the following space. Locate property lines,
existing structures, obstructions, utility and service lines, water lines, water well, septic
system, drainage zone of building downspout, collection basin for de-icing salts or barnyard
runoffs, trees and shrubs. Attach appropriate reports or surveys documenting the pathways for
electric, gas, water, cable or any other underground lines or fixtures that may be impacted by
the intended location of the earth loop system. Also, show any slopes on land (% grade and
direction).
3. Soil/rock types and conditions (describe based on general knowledge or information from local
soil and water agency):
4. Results of soil tests and samples at various depths and locations to determine potential
chemical contaminants. Explain.
6. What electric power is available for the direct geoexchange system? (check all that apply)
Date:
Customer/Job:
Street
Address: City: State:
NOTE: Taking photos where the icon appears next to an item is good documentation. Take photos
of any other items you feel would be important to the installation of new equipment.
Bore Hole Drilling Regulations and Special Code Requirements:
RETROFIT
Water requirements: Complete with as much information as known.
1. Hot water requirement: U.S. Gallons per day @ temperature of °F.
2. Peak hot water demand: U.S. Gallons per hour.
3. Present hot water storage capacity, U.S. Gallons: . (Include storage capacity of water
heater(s) and additional hot water storage tank(s).)
4. Present water heater input: BTUH (natural gas, LP gas or oil), OR kW (electric).
GENERAL
What is the general condition of the hot water heater? Good Poor Emergency (check
one)
Comments:
Comments:
Comments:
Comments:
Comments:
Comments:
Are flammable vapors located in the area of the water heater? Yes No
LIT-127 Page 2 of 8 02.10.09
Page 55
MIXING VALVES
Are there mixing valves in the mechanical room? Yes No
If yes, now many?
T&P VALVE
Is the T&P (temperature and pressure) relief valve dripping? Yes No
Comments:
DRAIN
Is there a floor drain in the boiler room? Yes No
Comments:
EXPANSION TANK
Is there a thermal expansion tank in the system? Yes No
If so, is it operational? Yes No
What is the brand?
What is the model number?
What is the pressure charge? psi
LIT-127 Page 3 of 8 02.10.09
Page 56
ELECTRIC POWER
Power available (check one):
Dormitory
• Mens Number of men:
• Womens Number of women:
• Combined Number: Ratio M/W:
Nursing Home
• Number of beds:
Food Service
• Full Meal Restaurant
Max. meals per day: ; Avg. Meals per day
• Sandwich or Snack Shop, Luncheonette, Grille, Drive-In
Max. meals per day: ; Avg. Meals per day
• Fast Food
Apartment
• Number of units:
Motel/Hotel
• Number of units:
Office Building
• Number of people:
LIT-127 Page 4 of 8 02.10.09
Page 57
School
• Elementary
Number of students
• Junior High School
Number of students
• Senior High School
Number of students
Laundry
• Number of washing machines:
• Domestic Machine(s) Commercial Machine(s) Commercial Machine(s) Size, Lbs.:
WATER SUPPLY
Source of potable water supply:
Municipal Well Other (explain)
Results of potable water analysis (either from municipal water supply or laboratory results of test
sample. Any contaminants above EPA acceptable level?
Soil/rock types and conditions (describe based on general knowledge or information from local soil
and water agency):
Are there any concentrations of acids, chlorides, sulfides, sulfates or ammonia in the soil at this
site?
DIAGONAL
D1 & T1 Earth Loop System: 1 – 100’ loops per ton ................................................ 66
D1.5 Earth Loop System: 1.5 – 100’ loops per ton .................................................. 67
D2 Earth Loop System: 2 – 75’ loops per ton .......................................................... 68
D3 Earth Loop System: 3 – 50’ loops per ton .......................................................... 69
HORIZONTAL PIT
H5 Loop System: 5 – 100’ loops per ton .............................................................. 70
HORIZONTAL TRENCH
H1 Loop System: 1 – 250’ loops per ton .............................................................. 86
Company Name:
Telephone:
Address:
City:
Earth Loop Warranty Registration (LIT-64)
State/ Zip:
Earth Loop System Seal Test: 400 psig Yes No (circle one)
Start-up Date:
MODEL:
Draw location of MANIFOLDS from Draw the measured location of the
permanent structure (use triangulation Cathodic Protection System ANODE, if
SERIAL:
method per installation instructions). installed with Earth Loop System.
Page 93
01/30/08
OR E-MAIL TO info@earthlinked.com.
Warranty Summary for Heating/Cooling Systems
WARRANTY SUMMARY: HEATING/COOLING SYSTEMS
ETI Limited Warranty Coverage
ETI’s limited warranty provides coverage for all EarthLinked® System component parts. A
component part is any factory-installed part within a system.
Upon failure of a component part during the warranty period, ETI will provide a replacement
part to the servicing dealer. In addition to replacement parts, the servicing dealer will be paid a
repair or replacement labor allowance in accordance with the current In-Warranty Allowance for
EarthLinked® Components and DIRECT AXXESS® Earth Loops, LIT-66. The labor
allowance is designed to reduce the cost of repairs. However, it may not cover the entire labor
fee charged by the servicing dealer.
ETI shall not be liable for any defect, unsatisfactory performance, damage or loss, whether
direct or consequential, relative to design, manufacture, construction, application or installation
of field-specified items.
1. All field specified and installed storage tanks, water heaters, water piping and water
temperature controls not supplied by ETI.
2. Conditions or damages resulting from any of the following:
a. Improper transportation or delivery, installation, service, or maintenance
b. Any repair, modification, alteration or adjustment not authorized by ETI
c. Misuse, abuse, accidents and unreasonable use
d. Improper setting or use of any control
e. Improper electrical supply or refrigerant charge
f. Improper backfill, grouting or compaction of earth loops
g. Use of system components in a corrosive atmosphere
h. Use of earth loops in a corrosive soil without ETI’s Cathodic Protection System
i. Subjecting installed earth loops to electrical currents
j. Field supplied and installed system components not supplied by ETI
k. Installation done by anyone other than an ETI trained and authorized installer.
l. Use of any field supplied component that is not listed with applicable industry
safety and performance standards agencies.
Page
R-407C
Diagonal ............................................................................................................................ 108
Vertical .............................................................................................................................. 110
Horizontal Pit ..................................................................................................................... 112
Horizontal Trench .............................................................................................................. 113
R-410A
Diagonal ............................................................................................................................ 114
Vertical .............................................................................................................................. 118
Horizontal Pit ..................................................................................................................... 121
Horizontal Trench .............................................................................................................. 122
Diagonal