You are on page 1of 4

Doc No :SEI/IPP/PRO/01

SHRI RAM Rev No :00


ENGG.INDS. Procedure for Initial flow Control
Rev Date:01.04.2018
Page 1 of 4

1. Purpose : To Define a procedure for control the initial flow of the parts during LVPT

2. Scope : All activities performed during LVPT ,Initial Supplies after sample approval (up to some duration
/lots/quantities.
3. Responsibility : Primary : QA-HEAD
Secondary : Production Head ,Stores Head ,Dispatch Head

Definition: First production part (FPP) lot,


A lot of such parts which are manufactured for the very first time after sample approval using actual
mass production process and condition, or which are produced for the first time just after the
implementation of one or more of the following changes :
1) Process Parameter change(e.g feed/angle/press/temp etc.). 2) Tool /Die /Machine/ Equipment
Changes 3) Layout change 4) Relocated plan :5) Supplier Change 6) Operator change 7) Starting
4 manufacturing after long Lay off (i.e 6 months ) 8) ECN Changes
Definition
Initial Product (I/P) : The first piece/part or lot samples from the first lot product during production.
Trial mass production trial SOP of a new part or change point i.e process change supplier change
operator change etc.

5 SYSTEM
INITIAL SUPPLY CONTROL
S.NO. INITIAL SUPPLY CONTROL (ISC) PROCESS RESPONSIBILITY REF. DPCUMENT
Information about SOP date : HOD project is responsible
for providing information regarding FPP approval and SOP
5.1 date to HOD QA,PS,WS, Machine Shop and Operation Head Head Projects _____
Through IOM

Head QA is
Deciding Official Person : Designate the person who will responsible for
initial supply
5.2 be over all responsible for the initiating,implementing control unless
_____
communicating with the customer. otherwise specified
by operation Head

Initial supply Control peroid : Fix the initial supply control


peroid with the customer during specification review Head QA / Head
SEI/DEV/F-13
meeting. Note : Default frequency for new parts is three Project
months
5.3
Head QA will inform to all concerned for start of initial
supply control peroid describing start date and end date Head QA SEI/DEV/F-13
based on SOP at customer end.

Identification of process of ISC : Identify the process


5.4 which is producing intial supply control parts with display Prodn/ Quality SEI/QA/F-13A
boards/Sign Boards which warrants the attention of Supervisor
operatrs & management.

Special controls : Decide special controls to be exercised


5.5 during intial supply control period.Limit samples to be Head QA SEI/DEV/F-13
provided on relevant station control item and method of
control is as discusssed in Sr.no. a to g.

PREPARED BY : REVIEWED BY : APPROVED BY : ISSUED BY :


DATE : DATE : DATE : DATE :
Doc No :SEI/IPP/PRO/01
SHRI RAM Rev No :00
ENGG.INDS. Procedure for Initial flow Control Rev Date:01.04.2018
Page 2 of 4

INITIAL SUPPLY CONTROL

S.NO. INITIAL SUPPLY CONTROL (ISC)PROCESS RESPONSIBILITY REF. DOCUMENT

Increased inspection items : Double inspection of All Head QA/ SEI/QA/ F-26
A Quality characteristic specified in Drawing and Control Process/PDI SEI/DEV/F-09
Plan. Engineer

Increased frequency : Half interval of time & double Head QA/ SEI/QA/F-04
B checking in setting approval & also double checking Process/PDI SEI/QA/F-03
frequency in process inspection report & in PDI also. Engineer

Frequent Process Capability (CPK) evaluation : Process


C capability study will be carried out for SC characteristic, Head Machine SEI/QA/F-06
corrective & preventive action for improvement in the shop
Cp/Cpk will be submitted in case of not ok.

Reaffirmation of operator skills : Provide operator on


the job training for the requirement of initial supply
D control and its significance,Extra care to be taken while Concerned Head SEI/HR/F-06
producing,inspecting the parts. Monitor the skill and
update skill matrix

PREPARED BY : REVIEWED BY : APPROVED BY : ISSUED BY :


DATE : DATE : DATE : DATE :
Doc No :SEI/IPP/PRO/01
SHRI RAM Rev No :00
ENGG.INDS. Procedure for Initial flow Control Rev Date:01.04.2018
Page 3 of 4
INITIAL SUPPLY CONTROL

S.NO. INITIAL SUPPLY CONTROL (ISC)PROCESS RESPONSIBILITY REF. DOCUMENT

Reduced cycles of initial supply control : Observe & record Head


E PS,WS,Machine SEI/QA/ F-29
problems, take countermeasure as per the procedure for CAPA shop

Termination of initial supply control : Consider to


terminate the initial supply control after the completion of
defined period(i.e 3 months) provided; 1. It is confirmed
that the capability of the process can fully satisfy the
specified tolerance/ accuracy requirements (Cpk>1.33 &
5.6 Cp>1.67) 2. It is confirmed that the countermeasure taken CFT & Head QA SEI/DEV/F-13D
for the problems occured during production of FPP lot are
effective. 3. If the countermeasure taken against problems
observed during initial supply control itself are found
effective. If any of the criteria listed above are not met, ISC
period shall be extended till the time all criteria are met.

B. INITIAL PRODUCT CONTROL


S.NO. INITIAL SUPPLY CONTROL (ISC)PROCESS RESPONSIBILITY REF. DPCUMENT

Incharge quality
5.7 Identification of initial product : Identify the initial (PDC/GDC/
SEI/QA/F-13A
product with identification tag. Machine
shop/fetting)

Identification of initial product (Supplier Part) : For


BOP parts, instruct the supplier to submit the parts with
Head purchase/
5,7.1 initial
product identification tag for supplier.Note : Recevie Incharge BOP/RQC SEI/QA/F-13A
the material from supplier with initial product Engineer
identification tag only. If the material is not provided with
the tag, Do not accept such material.

Retention Peroid of inspection Reports : For A parts and


Incharge quality
functional parts, inspection reports must be preserved for (PS/WS/
5.8 Machine ___
min 5 years and incase of general parts min. 3 years or shop)
otherwise as agreed with customer.

Accetance criteria : For the items for which specification


are nor decided or tolerance are not specified in the Head QA/Head
5.9 Project ___
drawing by customer, discuss the acceptance during
engineering standards/ international standards.

PREPARED BY : REVIEWED BY : APPROVED BY : ISSUED BY :


DATE : DATE : DATE : DATE :
Doc No :SEI/IPP/PRO/01
Rev No :00
SHRI RAM
ENGG.INDS. Procedure for Initial flow Control Rev Date:01.04.2018
Page 4 of 4

INITIAL SUPPLY CONTROL

S.NO. INITIAL SUPPLY CONTROL (ISC)PROCESS RESPONSIBILI REF. DPCUMENT


TY

Perormance & durability evalution : Carry out all the


inspection & test as defined in drawing/any maruti
specified test other than drawingwhich has been discussed Incharge
in specification review meeting.if the facility is not Quality
5.10. Inspection Report
available for the inhouse inspection. cosult the external (PS/WS/Mac
lab/company maintain all such records of test Note : hine shop)
Performance shall be given to NABL (ISO 17025) accrediated
Labs/Companies.

Handling of Rejected initial : Each & every lot Rejected


during intial supply control shall be critically examinated Incharge
by CFT team (Q.C+Prod.+Dev.Team) for defect and Quality
5.11 SEI/QA/ F-29
necessary CAPA action shall be taken, with exphasis on (PS/WS/Mac
prevention of defect. If necessary FMEA should be hine shop)
modified.

Check of initial product inspection report and tag : Incharge


Before dispatching the product to customer ensure that Quality
5.12 initial product are identified with INITIAL PRODUCT (PDC/GDC/M SEI/QA/F-13A
IDENTIFICATION TAG and / or inspection report as Achine shop/
applicable. Fettling)

PREPARED BY : REVIEWED BY : APPROVED BY : ISSUED BY :

DATE : DATE : DATE : DATE :

You might also like