TEST AND INSPECTION PER: API-616,, Manufacturer Standard, and Specifications as noted below.
0020 X NDT Procedures and Personnel Qualification Verify valid personnel qualification and procedures.
0030 X Welder Qualifications Records Per any of the following: BSI /ASME /JIS /DIN /EN.
0040 X Welding Procedure Specifications (WPS) and Procedure Per any of the following: BSI /ASME /JIS /DIN /EN.
Qualification Records (PQR)
0050 X Inspection and Test Plan Shall be provided and approved by Company Representative.
0020
0010
*** X
In process inspection & test requirement
Workmanship, Components and Dimensions:
Specification Details / Notes:
0030 X Workmanship, Components and Dimensions: Per The applicable international standard identified above.
c) Weld Joint Preparation & In-Process Welding Inspection
0040 X Workmanship, Components and Dimensions: Per The applicable international standard identified above.
d) Full Penetration Welding on 2" or Smaller Weld Bosses
0060 X Workmanship, Components and Dimensions: Verify installation, venting, drains & accessibility. "Block valves"
f) Safety Relief Valve & Block Valve Installation shall be painted orange.
IR325513 Continued...
INSPECTION & TESTING REQUIREMENTS REVISION: 04/30/2011 CODE NUMBER: PAGE:
SAUDI ARAMCO FORM-175 REPLACES: 12/31/2005 IR325513 2 of 2
(1) VISUAL INSPECTION WITNESSING BY INSPECTOR (Note 1)
(2) CERTIFICATES / RECORDS TO BE CHECKED BY INSPECTOR
(3) CERTIFICATES / DATA TO BE PROVIDED BY VENDOR / SUPPLIER / MANUFACTURER
0100 X X Non Destructive Testing (NDT) All fuel piping welds shall be subjected to 100% NDT inspection
(radiography, magnetic particle, and/or dye-penetrate).(see note
3)
0030
0010
*** X
Final inspection & test requirements
Piping, Fitting & Flange Dimensions
Specification Details / Notes:
Dimensions shall be rechecked after PWHT.
0030 X Hydrostatic Testing Per API 616. Also Valves > 2" shall be hydrostatic tested.
0050 X Identification Marking & Final Inspection Packing and marking shall be per Purchase Order. Also, check
pipe end protection condition.
Notes:
(1) May only be waived by the responsible Saudi Aramco, ASC,and AOC Inspection Offices.
(2) See form SA175 -000003 for instructions on using this form.
(3) 10% Random Radiography (RT) for others. Acceptability shall be per the welding standard identified above.
End of IR325513