INSPECTION & TESTING REQUIREMENTS REVISION: 05/23/2011 CODE NUMBER: PAGE:

SAUDI ARAMCO FORM-175 REPLACES: 10/17/2000 IR791200 1 of 2


SCOPE: Re-Engineered Pump Casing Parts for API and Non-API Pumps.

TEST AND INSPECTION PER: P.O and Below Specifications

(1) VISUAL INSPECTION WITNESSING BY INSPECTOR (Note 1)


(2) CERTIFICATES / RECORDS TO BE CHECKED BY INSPECTOR
(3) CERTIFICATES / DATA TO BE PROVIDED BY VENDOR / SUPPLIER / MANUFACTURER
0010
0010
***
X X X
Pre-Fabrication/Production Requirements
Pre Inspection Meeting
Specification Details / Notes:
Inspection and Test Plan shall be submitted to Company
inspector for review and approval.

0020 X Welding Procedure Specifications (WPS) & Procedures Per ASME Section IX. One time Company approval is required
Qualification Records (PQR) for WPS & PQR.

0030 X Welders Qualification Records Per ASME Section IX.

0040 X NDT Personnel and Procedures Verify valid personnel qualification arid procedures.

0050 X Procedures and Personal for Metal Coating if Specified in the P.O. Verify valid personnel qualification and procedures.

0020
0010
*** X
In process inspection & test requirement
3D Scan of Supplied Part Sample
Specification Details / Notes:
The manufacturer shall develop the drawing for the part using
3D measurement device to scan the supplied sample part.

0012 X X Welding Repairs Per applicable material specification. If procedures are not
covered by the material spec., use ASME IX or EN 288.

0020 X X Non-Destructive Testing: a)Radiographic Examination If specified in the PO and shall be per PO Specification.

0030 X X Non-Destructive Testing: b) Liquid Penetrant Examination or Wet If specified in the PO and shall be per PO Specification.
Fluorescent Magnetic Particle Inspection.

0040 X X Post Weld Heat Treatment After major weld repairs if required by applicable ASTM
specification.

0030
0010
***
X X
Final inspection & test requirements
Hardness Testing
Specification Details / Notes:
For parts exposed to sour service and shall meet ISO 15156.

0020 X X Hydrostatic Test for Pressure Retaining Parts Duration 30 minute at 1.5 times maximum allowable pressure at
ambient temperature.

0030 X Visual Inspection Casting surfaces shall meet the visual requirements of
MSS-SP-55

IR791200 Continued...
INSPECTION & TESTING REQUIREMENTS REVISION: 05/23/2011 CODE NUMBER: PAGE:
SAUDI ARAMCO FORM-175 REPLACES: 10/17/2000 IR791200 2 of 2
(1) VISUAL INSPECTION WITNESSING BY INSPECTOR (Note 1)
(2) CERTIFICATES / RECORDS TO BE CHECKED BY INSPECTOR
(3) CERTIFICATES / DATA TO BE PROVIDED BY VENDOR / SUPPLIER / MANUFACTURER
0040 X X Dimensional Inspection and 3D Scan of Manufactured Parts Manufacturer shall conduct 3D measurement for final part &
compare it to original 3D model. Must meet tolerances.

0050 X X Material Test Reports Verify mechanical and chemical data compliance to P.O.
specifications.

Notes:
(1) All documents must be available for the purchaser inspector review upon his request.
(2) May only be waived by the responsible Saudi Aramco, ASC, or AOC Inspection Offices.
(3) See form SA175 - 000003 for instructions on using this form.

End of IR791200