CA-58 Contract Progress as on date:

1. RSS Works Electric Works: overall progress 47%


a. Power and Traction transformers erected at RSS, Oil filtration and accessories
installation work under progress.
b. 1 km 110 kV EHV cable route laid out of 3.25 km cable route.

2. RSS Civil Works: overall progress 58.4%


a. 30 nos Equipment foundations completed out of 44.
b. 2 nos firewall completed out of 3.
c. 20 Columns out of 27 completed of 1st floor.
d. 308 mtr earthing of RSS completed out of total scope 2000 mtr.

3. ASS Works: overall progress 42%


a. 500KVA Transformer installed at 3 stations (Bandongri, M&M and National park) out of
13 stations
b. 33 kV GIS installed at 2 stations (Bandongri and National park) out of 13 stations.

*Weightage considered for overall progress: Design=20%, Supply= 20%, Installation=40%,


T&C=20%