PK01E-CAMCE-B2-K-0766

Daily Site Work Progress Report

SITE ACTIVITIES IN PROGRESS

Package IX – Switchyard Pictures


Weather:Cloud 32°C
Total Manpower: 40
Electrical :28
Mechanical : 6
Management staff Nos : 06
A. 132kV Mid- Breaker Shutdown Activities
1. 132 kv E0 Disconnector Switch Q12&Q11 old Cables Dismentalling from Mk is in
progress.
A1
2. 132 kv ATR-3 cable glanding inside panel is in progress.
A2
3. 132 kv E0 to E6 line side Surge Arrester Earthing conductor installation is in
A3
progress.
A5
4. 132 kv E2 CVT-20 cables glanding is in progress.
5. 132 kv E3 line side Surge Arrester Excavation is in progress.
6. CHB Housekeeping.
HSE
HSE Manpower:
Zain Ahmad (HSE supervisor), Bilal Raza (Safety Officer).
SOPs:
1. Daily Tool Box Talk for procedure related to PTW/shutdowns areas & Supervision
presence.
2. Good Housekeeping.
3. Social distancing among the staff and workers maintained at site premises wherever
required.
4. Clean drinking water facility provided to all workers and staff.
5. PPEs including masks provided to all staff and workers.
6. Emergency walkways/paths clear from all hurdles and barriers.

Site Work Progress Pictures:

Page 1 of 2 THU 2023.08.24

132KV & 220KV Switchyard


PK01E-CAMCE-B2-K-0766
Daily Site Work Progress Report

A2: 132 kv ATR-3 cable glanding inside panel is


A1: 132 kv E0 Disconnector Switch (Q12) old
in progress.
Cables Dismentalling from Mk is in progress.

A3: 132 kv E0 to E6 line side Surge Arrester A4: 132 kv E2 CVT-20 cables glanding is in
Earthing conductor installation is in progress. progress.

Page 2 of 2 THU 2023.08.24