You are on page 1of 1

PROJECT : OKADA MANILA - TOWER B

SUBJECT : DCII PUNCHLIST CLOSEOUT MONITORING


LEVEL : 9F, ZONE 1
DATE :7/8/2019

OVER-ALL PERCENTAGE

9061
STATUS : 99%
REMAINING PERCENTAGE: 1%
BALANCE/S
AREA ITEM COMMENT
LIVING ROOM MULLION/SILL TRIM RETOUCH PAINT AND BALANCE GROUT

9070
STATUS : 99%
REMAINING PERCENTAGE: 1%
BALANCE/S
AREA ITEM COMMENT
WALL STONE TERMINATION ON FLOOR & CEILING
TOILET AND BATH SWITCH PLATE NOT YET INSTALLED
SHOWER (FLOOR DRAIN) VERIFY FLOOR DRAIN (APPROVAL)

9071
STATUS : 96%
REMAINING PERCENTAGE: 4%
BALANCE/S
AREA ITEM COMMENT
RESIN PANEL NOT YET INSTALLED
LIVING ROOM
POWER POINTS BALANCE DATA OUTLET
FLOOR DRAIN (SHOWER AREA) VERIFY LOCATION
TOILET AND BATH
PEDESTAL BALANCE GROUT

9072
STATUS : 97%
REMAINING PERCENTAGE: 3%
BALANCE/S
AREA ITEM COMMENT
WALL STONE EXCESS GROUT
TERMINATION ON FLOOR AND CEILING
VANITY MIRROR (ACCESSIBLE) NOT YET INSTALLED
DEFOGGER NOT YET INSTALLED
TOILET AND BATH
POWER POINT NOT YET INSTALLED
FLOOR STONE (TOILET) UNEVEN SHADE
POWER POINT (TOILET) NOT YET INSTALLED
TELEPHONE (TOILET) NOT YET INSTALLED