Professional Documents
Culture Documents
(Design Certificate)
[*Design Package No. Mumbai Coastal Road Package IV / the Definitive Design
Submission MCR4-LNT-422-DR-400065 A1 in respect of:
The documents scheduled in Section B below, for which a Notice to proceed has been issued,
are of relevance to this submission.
We certify that:
(a) the design of the Permanent Works, as illustrated and described in the documents
scheduled in Section A below, complies with the Employer's Requirements, local
regulations and standards and ...... N.A. [see note 1 below];
OR (in the case of a submission of documents that do not strictly comply with previous
documents for which a Notice to proceed has been received):
(b) A detailed review and design check has been undertaken and completed to confirm
the completeness, adequacy and validity of the design of the Permanent Works as
illustrated an described in the documents scheduled in Section A below;
(c) all necessary and required approvals relating to the design of the Permanent
Works, as illustrated and described in the documents scheduled in Section A below,
have been obtained and copies of such approvals are annexed in Section C below;
1|Page
AND (in the case of a submission covering a part of the Permanent Works only):
all effects of the design comprising the submission on the design of adjacent or other parts of
the Works have been fully taken into account in the design of those parts.
(for Designer):
Date: 09-04-2019
We certify that the Work described in Section A of this certificate has been checked by us, and
meets the requirements of the Contract.
Date: 09-04-2019
CONTRACTOR’S CERTIFICATION
This Certifies that all design has been performed utilising the skill and care to be expected of
a professionally qualified and competent designer, experienced in work of similar nature and
2|Page
scope. This further certifies that all works relating to the preparation, review, checking and
certification of design has been verified by us and that the design meets the requirements of
the Contract and has been accepted by us.
Date: 09-04-2019
Note 1
(ii) the Contractor's Technical Proposals and Design Packages Nos. MCR4-LNT-420-
PR-400010- A1 for which a Notice to proceed has been issued.
(iii) Design Packages Nos. MCR4-LNT-420-PR-400010- A1 for which a Notice to
proceed has been issued if such Design Packages develop and amplify the
Contractor's Technical Proposals.
(iv) The Definitive Design
Section A
Drawings:
Others:
3|Page
Section B
Documents for which a Notice to proceed has been issued and which are of relevance to this
Submission No.
Document: MCR4-LNT-420-PR-400010- A1
submitted with
Section C
[Contractor to attach copies of necessary and required approvals from statutory bodies, etc..]
4|Page
Disclaimer: Permission to proceed shall not constitute acceptance or approval of design details, calculations, analyses, test methods or materials developed or selected by contractor and shall not relieve the contractor from full compliance with contractual obligations.
Status codes: A: Notice of No Objection accorded – Work may proceed – B : Notice of No Objection accorded with comments – Revise and resubmit. Work may proceed subject to incorporation of comments – C: objection – Revise and resubmit. Work may not proceed –
D: Rejected – E: Review not required. Work may proceed.Contractual obligations.
Page 1 of 1
4/10/2019
Mumbai Coastal Road Project – Package IV
DEFINITIVE DESIGN
TBM Tunnel
(Sign)
Date: 29/03/2019
(Sign) (Sign)
CONTENTS
1. INTRODUCTION 1
2. REFERENCES 4
3. MATERIALS 7
3.1 Concrete 7
3.1.1 Durability and grade 7
3.1.2 Limits on cracks width 7
3.1.3 Water tightness 7
4.1 OVERVIEW 9
4.3 Seismicity 12
5.1 Generalities 13
6.1 Demoulding 51
6.2 Storage 53
6.3 Handling 55
7. TECHNOLOGICAL PARTS 67
7.1 Connectors 67
7.1.1 Introduction 67
7.1.2 Shear 67
7.1.3 Pull-out 67
7.2 Gaskets 69
7.2.1 Introduction 69
7.2.2 Water tightness 70
7.2.3 Tensile splitting 72
7.2.4 Corner shear 73
8. CONCLUSIONS 75
1. INTRODUCTION
Package IV of the Mumbai Coastal Road Project includes a twin-bore tunnel between km
5+270 (the launch pit) and km 3+280 (the southern portal). The tunnel shall be built with a
Tunnel Boring Machine (TBM).
The present technical report described the detailed design of the TBM tunnel demonstrating
the achievement of a safe tunnelling method and of a safe and durable permanent structure.
The structural and geotechnical design of the segmental lining is conducted in accordance
with the relevant applicable standards to check the ultimate (ULS) and serviceability (SLS)
limit states.
− Short and long-term actions induced by the construction procedure on the single
segment;
− Actions resulting from TBM advancement;
− Overburden, with appropriate vertical and horizontal pressures;
− Groundwater pressure;
− Surface load from traffic and buildings;
− Adjacent tunnels or excavations.
The structural and geotechnical verifications were supported by the numerical analysis of the
tunnel lining with 2D finite elements (FE) models in plane-strain conditions.
In the FE model the soil and the rock were treated as linear-elastic/perfectly plastic materials
with Mohr-Coulomb’s yield criterion (LE-PP/MC). The geo-mechanical parameters are in
agreement with the values reported in the geotechnical interpretation.
Figure 1-1 General Layout Plan from ch. 1+950 to ch. 3+300.
Figure 1-2 General Layout Plan from ch. 3+300 to ch. 4+700.
Figure 1-3 General Layout Plan from ch. 4+700 to ch. 5+900.
2. REFERENCES
Design will be produced in accordance with the standards specified by tender documents:
[1] MCGM (2017). Mumbai Coastal Road Project (South) - Package IV. Volume 3:
Employer’s Requirements. Municipal Corporation of Greater Mumbai, Tender Document
for Design and Construction Contract (Princess Street Flyover to Priyadarshini Park).
[2] MCGM (2017). Mumbai Coastal Road Project (South) - Package IV. Volume 4: Outline
Design Specification. Municipal Corporation of Greater Mumbai, Tender Document for
Design and Construction Contract (Princess Street Flyover to Priyadarshini Park).
[3] MCGM (2017). Mumbai Coastal Road Project (South) - Package IV. Volume 5: Outline
Construction Specification. Municipal Corporation of Greater Mumbai, Tender Document
for Design and Construction Contract (Princess Street Flyover to Priyadarshini Park).
[4] MCGM (2017). Mumbai Coastal Road Project (South) - Package IV. Volume 7:
Reference Documents. Municipal Corporation of Greater Mumbai, Tender Document for
Design and Construction Contract (Princess Street Flyover to Priyadarshini Park).
[9] AFTES (1994). The choice of geotechnical parameters and tests useful to the design,
dimensioning and construction of underground structures. Recommendation GT7R4A1
by “Association Française des Tunnels et de l'Espace Souterrain”.
[10] AFTES (1974). Choice of tunnel support. Recommendation GT7R1A2 by “Association
Française des Tunnels et de l'Espace Souterrain”, English edition, special publication
SP 93.
[11] AFTES (1999). Settlements induced by tunnelling. Recommendation GT16R1A1 by
“Association Française des Tunnels et de l'Espace Souterrain”, English edition, special
publication SP 99.
[12] BTS/ICE (2005) Closed-face Tunneling Machines and Ground Stability. Guidelines by
the British Tunneling Society and the Institution of Civil Engineers, Thomas Thelford,
London, UK.
[13] Bamforth, P.B. (2007) Early-age thermal crack control in concrete. CIRIA Report C660,
London, Construction Industry Research and Information Association, London, UK.
[14] Anagnostou, G., Kovári, K., 1996. Face stability conditions with earth-pressure-balanced
shields. Tunnelling and Underground Space Technology 11: 165–173.
[15] Boscardin, M.D. and Cording, E.G. (1989). Building response to excavation-induced
settlement, ASCE Journal of Geotechnical Engineering, 115(1).
[16] Burland J. P. & Wroth C. P. (1974), “Settlement of buildings and associated damage”,
SOA Rev. Conf. Settlement of structures, Cambridge, Pentech Press, London, pp 611 ÷
654
[17] Guglielmetti, V., Grasso, P., Mahtab A. et Xu, S. (2008). Mechanized tunneling in urban
areas: design methodology and construction control. Taylor & Francis, London, UK.
[18] Mair, R.J., Taylor, R.N., and Burland, J.B., (1996), Prediction of Ground Movements and
Assessment of Risk of Building Damage. Geotechnical Aspects of Underground
Construction in Soft Ground, pp. 712-718, Balkema, Rotterdam, the Netherlands.
[19] Panet M. (1995) Le calcul des tunnels par la méthode convergence-confinement,
Presses de l’ENPC, Paris, France.
[20] Peila D. (1994). A theoretical study of reinforcement influence on the stability of a tunnel
face. Geotechnical and Geological Engineering, 12: 145-168.
[21] Peck, R. B. (1969); “Deep Excavations and Tunnels in Soft Ground”. Proceedings of
the 7th International Conference on Soil Mechanics and Foundation Engineering, Mexico
City, State of the Art Volume, pp. 225-290.
[22] Potts D.M. and Addenbrooke T.L. (1997), A structure's influence zone tunnelling-induced
ground movements, Proc. ICE – Geotechnical Engineering 125(2): 109–125.
3. MATERIALS
3.1 CONCRETE
The tunnels of the Mumbai Coastal Road, Package IV, have 120 years of design life. The
concrete grade selected by the Designer is M50. It is worth emphasising that at the time of
writing the additional ground investigation, which includes chemical testing to define the
aggressiveness of ground and groundwater is not complete. It will be necessary, once the
data become available, to verify that they confirm the design assumptions described here.
The tunnel lining concrete is designed to prevent excessive cracking due to flexure, early
age behaviour and thermal variations. The flexural crack width has been checked in
accordance with Appendix F of IS 456:2000, to verify compliance with the limits shown in
Table 3-1.
The cover thickness depends on the exposure conditions, that is the chemical and physical
conditions to which the structure is exposed in addition to the mechanical actions. Starting
from the exposure class and considering various factors such as the design working life of
the structure, the concrete strength class, the quality controls on production, it is possible to
define the required structural class and the minimum concrete cover.
However, the minimum cover will be checked again once the environmental aggressivity data
from the additional ground investigation (under way at the time of writing) become available.
The minimum amount of reinforcement was calculated to satisfy the structural ULS and SLS.
In terms of crack width control, a certain amount of bonded reinforcement is required in the
zones where the existence of tensile stresses is foreseen. The minimum amount of
reinforcement was estimated from the equilibrium between the tensile force in the concrete
just before cracking and the tensile force in the reinforcement at yielding or at lower stress if
necessary, to limit the crack width.
4.1 OVERVIEW
As discussed in the Geological and Geotechnical Interpretative Report [6] the geotechnical
units encountered along the tunnel alignment are, from shallowest to deepest:
The rock masses of GU3, Basalt, And GU4, Breccia with Shale, are further classified in four
sub-units, labelled with letters from (a) to (d) according to their weathering grade, as
summarised in the following Table 4-1.
In the finite element (FE) calculations carried out to check the ground loading on the
segmental lining the geotechnical parameters defined in [6] were used, as detailed,
calculation by calculation, in the following sections. In particular, the shear strength of soils
– GU1, GU2a and GU2b – was defined with the Mohr Coulomb parameters presented in the
Geological and Geotechnical Interpretative Report (GGIR); the shear strength of the rock
masses – GU3 and GU4 – was defined converting into locally equivalent Mohr-Coulomb
parameters the Hoek-Brown parameters presented in the GIR.
The tunnel alignment has been divided into seven roughly homogeneous zones in which the
excavation behaviour is approximately similar. The zones are briefly described in the
following text and plotted in the geotechnical-geo-mechanical profile. For each zone a
representative cross section was identified and modelled in a FE analysis to evaluate the
structural action in the lining. The zones are presented here from the lowest to the highest
chainage (which is the opposite direction to the TBM drive as planned at the time of writing).
For this stretch, the section at km 3+440 is taken as representative an identified with LO1.
For this stretch, the section at km 3+750 is taken as representative an identified with CC1.
ZONE 3, km 4+400÷4+500: excavation in Breccia and Shales with low weathering grade. In
this area, however, the tunnel may encounter a zone of faulting, before the end of this
section, where the cover increases sharply from 20 m up to 60÷65 m under Malabar Hill.
For this stretch, the section at km 4+430, in the potentially faulted region, is taken as
representative an identified with FA1.
ZONE 4, km 4+500÷4+900: excavation mainly in Breccia and Shales with low weathering
grade and high rock cover of 45÷67 m. The Basal can occur on the crown of the tunnel.
For this stretch, the section at km 4+525, with the highest overburden, is taken as
representative and identified with HO1.
ZONE 5, km 4+900÷5+270: excavation in Basalt with variable weathering grade from low to
high. The cover is of 13÷45 m. The cover decreases smoothly towards the break-in.
For this stretch, the section at km 5+000, with mixed front conditions, is taken as
representative and identified with MF1
In the GGIR the strength and of the rock mass is defined according to the Hoek & Brown
criterion (1997; 2002) expressed by the following equations:
𝑎
𝜎′3 𝐺𝑆𝐼 − 100
𝜎′1 = 𝜎′3 + 𝜎𝑐𝑖 (𝑚𝑏 + 𝑠) 𝑚𝑏 = 𝑚𝑖 𝑒𝑥𝑝 ( )
𝜎𝑐𝑖 28 − 14𝐷
𝐺𝑆𝐼 − 100 1 1
𝑠 = 𝑒𝑥𝑝 ( ) 𝑎 = + (𝑒 −𝐺𝑆𝐼⁄15 − 𝑒 −20⁄3 )
9 − 3𝐷 2 6
Where:
GSI = geological strength index, a dimensionless index that represents the rock mass quality
(a function of the degree of fracturation, discontinuity conditions etc.) in the range from 0
(extremely poor) to 100 (extremely good)
The rock mass elastic modulus has been estimated with the approach proposed by the Hoek
e Diederichs (2006), which links the stiffness modulus of the rock mass to the modulus of the
intact rock, Ei, with the equation:
1 − 𝐷 ⁄2
𝐸𝑟𝑚 = 𝐸𝑖 (0.02 + )
1+ 𝑒 ((60+15𝐷−𝐺𝑆𝐼)⁄11)
The equivalent Mohr-Coulomb parameters (effective cohesion and friction angle) were
determined with the software RocLab 1.033 (Roscience). This was done by fitting an
average linear relationship to the curve generated by solving the Hoek & Brown criteria for a
range of minor principal stress values (comprised between σt and σ’3,max). σ’3,max is
determined for tunnels giving equivalent characteristic curve for the two failure criteria. In
case of shallow tunnels, the method is still valid excluding caving to surface (Hoek, Carranza-
Torres and Corkum, 2002)
The equivalent calculation parameters at front for the prevalent material are summarized in
Table 4-2 for each representative section.
Where,
sat saturated unit weight
Erm rock mass stiffness modulus;
rm drained Poisson’s ratio;
c’ effective cohesion;
’ angle of internal friction
4.3 SEISMICITY
As per Indian Standard IS 1893, the site falls under Seismic Zone III. The basic horizontal
seismic coefficient corresponding to this zone is 0.16g, where g is the gravitational
acceleration.
5.1 GENERALITIES
The structural actions on the tunnel, in its final configuration, were estimated by means of 2D
FE analysis with the software PLAXIS.
The proposed lining is built with 11.00 m internal diameter rings of 8 segments, which are
375 mm thick,
In the FE models, the final lining was modelled with beam characterised by a certain
where Ec is the Young’s modulus of concrete, A is the cross-sectional area (per meter run)
and I is the moment of inertia.
While the definition of the axial stiffness is straightforward also for a segmental lining, the
bending stiffness of an equivalent plate should take into account the reduced capability of
transmitting moments across the joints, which differentiate a segmental lining from a
monolithic lining with the same thickness.
In the resent calculation the reduced moment of inertia of the segmental lining was calculated
with the approach proposed by Muir and Wood (1975):
𝐼1 = 𝐼𝑗 + (4/𝑛)2 ∙ 𝐼𝑜
Where:
5.3.1 Model
The ground profile and the geo-mechanical parameters used in the analysis are reported in
the table and in the figure below.
First Second
Considering that this section represents the worst-case scenario (lowest overburden, rock of
poor quality at the front), the analysis is carried out considering the excavation of both the
bores to see the effect on the final lining of the first excavated section. The results refer to
two configurations:
1. Stress initialization: a K0 procedure is employed for the generation of the initial stress
state. The soils have a coefficient of earth pressure are rest K0 = 1- sen(φ), in
agreement with Jaky’s formula (1948). The rock has K0 = 0.7.
2. Front relaxation: equal to 30%: according to the analytical Longitudinal Displacement
Profile, LDP (Vlachopoulos and Diederichs, 2009);
3. Shield relaxation: according to the analytical Longitudinal Displacement Profile, LDP
(Vlachopoulos and Diederichs, 2009) at a distance from the front corresponding to
the TBM shield tail the relaxation is equal to 90%. For such a relaxation, the
convergence of the wall exceeds the gap around the shield. For this reason, a
kinematic constraint is assumed at 2 cm of convergence for the shield conicity. For
this section, the kinematic constraint is reached for a relaxation of 50%. Past that
level, the load is applied all on the lining;
4. Installation of the lining (ST1): the final lining is activated in this phase and the
relaxation is equal to 100%. The final lining is modelled by means of a plate element
with thickness equal to 37.5m and concrete grade M50;
5. Repeat from point 2 to 4 for the second tunnel (ST2);
6. Long-term condition (LT): the long-term conditions are assumed to a water load on
the crown of 11.0 m (according to the geological profile) increasing with the depth.
The figure below shows the adopted relaxations at the front and at the tail shield of the TBM
on the analytical LDP (Vlachopoulos and Diederichs, 2009).
Front
Tail Shield
5.3.2 Results
The figures below show the structural actions in the lining both for ST and LT phases as
described in the previous paragraph.
The influence of the second tunnel on the lining of the first tunnel in terms of change in the
structural actions is in the range of 4-9%.
5.4.1 Model
The ground profile and the geotechnical parameters used in the analysis are reported in the
Table 5-2
The analysis of the current section is carried out through the following phases:
1. Stress initialization
2. Front relaxation: equal to 30% according to the analytical Longitudinal Displacement
Profile, LDP (Vlachopoulos and Diederichs, 2009).
3. Tail shield relaxation: according to the analytical LDP at a distance from the front
corresponding to the TBM shield tail, the relaxation is 90%.
4. Installation of the lining (ST): the final lining is activated in this phase and the
relaxation goes up to to 100%.
5. Long-term condition (LT): the long-term conditions are assumed to a water load on
the crown of 11.0 m (according to the geological profile) increasing with the depth.
The figure below shows the adopted relaxations at the front and at the tail shield of the TBM
on the analytical LDP (Vlachopoulos and Diederichs, 2009).
Front
Tail Shield
5.4.2 Results
The figures below show the actions in the lining both for ST and LT phases as described in
the previous paragraph.
5.5.1 Model
The ground model and the geo-mechanical parameters used in the analysis are reported in
the table and in the figure below. The angle at which the potential fault would intersect the
tunnel is not known with certainty. In order to maximise the adverse effects in the
calculations, the fault was modelled as an inclined band of much weaker rock completely
encasing the tunnel.
Fault - - 17 5 33 30
The analysis of the current section is carried out through the following phases:
1. Stress initialization
2. TBM excavation: in the fault section the front is not stable. In such a case, a TBM
front pressure of 1.6 bar is applied. According to the analytical Longitudinal
Displacement Profile at at the TBM shield tail relaxation is 90%. In this range (0%-
90%), the front pressure is applied by the TBM to stabilize the excavation.
3. Installation of the lining (ST): the final lining is activated in this phase and the
relaxation goes ut to 100%.
4. Long-term condition (LT): the long-term conditions are assumed to a water load on
the crown of 11.0 m (according to the geological profile) increasing with the depth.
5.5.2 Results
The figures below show the structural actions in the lining both for ST and LT phases as
described in the previous paragraph.
5.6.1 Model
The ground model and the geo-mechanical parameters used in the analysis are reported in
the Table 5-4and in the Figure 5-30 below.
The analysis of the cross section is carried out through the following phases:
1. Stress initialization: in this section, the tunnel is deep (H > 3D) and a field stress
procedure is adopted where a state of stress corresponding to the geostatic stress at
the tunnel axis is assumed. The rock has a coefficient of lateral earth pressure at rest
equal to 0.7.
2. Front relaxation: equal to 30%: according to the analytical Longitudinal Displacement
Profile
3. Tail shield relaxation of 90%.
4. Installation of the lining (ST): the final lining is activated in this phase and the
relaxation goes up to 100%.
5. Long-term condition (LT): the long-term conditions are assumed to a water load on
the crown of 11.0 m (according to the geological profile) increasing with the depth.
The figure below shows the adopted relaxations at the front and at the tail shield of the TBM
on the analytical LDP (Vlachopoulos and Diederichs, 2009).
Front
Tail Shield
5.6.2 Results
The figures below show structural actions in the lining both for ST and LT phases as
described in the previous paragraph.
5.7.1 Model
The ground model and the geo-mechanical parameters used in the analysis are reported in
the table and in the figure below.
1. Stress initialization: in this section, the tunnel is deep (H > 3D) and a field stress
procedure is adopted where a state of stress corresponding to the geostatic stress at
the tunnel axis is assumed. The rock has a coefficient of lateral earth pressure at rest
equal to 0.7.
2. Front relaxation: equal to 30%
3. Tail shield relaxation: according to the analytical relaxation is 90% at the shield tail.
4. Installation of the lining (ST): the final lining is activated in this phase and the
relaxation is brought up to 100%.
5. Long-term condition (LT): the long-term conditions are assumed to a water load on
the crown of 11.0 m (according to the geological profile) increasing with the depth.
The figure below shows the adopted relaxations at the front and at the tail shield of the TBM
on the analytical LDP (Vlachopoulos and Diederichs, 2009).
Front
Tail Shield
5.7.2 Results
The figures below show the structural action in the lining both for ST and LT phases as
described in the previous paragraph.
The earthquake effects in bored tunnels were estimated through equivalent static methods
that, according to ITA, AFTES and other international design criteria, can be used instead of
a full dynamic analysis allowing for ground-structure interaction. The Free-field distortion
method is adopted here.
Earthquake-induced strains in the ground are estimated in the absence of structures. This
provides an approximated – and pessimistic - estimate of the actual structure’s deformation.
A horizontal displacement is directly applied at the tunnel crown; and the ensuing additional
actions are calculated.
The bending moment and axial force increment in full slip and no slip condition are computed
according to Penzien (2000):
Full slip
∆𝑑 𝛾𝑚𝑎𝑥
=±
𝑑 2
𝑛
±∆𝑑𝑙𝑖𝑛𝑖𝑛𝑔 = ±𝑅 𝑛 ∆𝑑𝑓𝑟𝑒𝑒−𝑓𝑖𝑙𝑒𝑑
𝑛
6𝐸𝑙 𝐼Δ𝑑𝑙𝑖𝑛𝑖𝑛𝑔 𝜋
𝑀(𝜃) = − 𝑐𝑜𝑠2 (𝜃 + )
𝑑2 (1 − 𝜐𝑙2 ) 4
𝑛
24𝐸𝑙 𝐼Δ𝑑𝑙𝑖𝑛𝑖𝑛𝑔 𝜋
𝑉(𝜃) = − 𝑠𝑖𝑛2 (𝜃 + )
𝑑3 (1 − 𝜐𝑙2 ) 4
No slip
𝑛
±∆𝑑𝑙𝑖𝑛𝑖𝑛𝑔 = ±𝑅 𝑛 ∆𝑑𝑓𝑟𝑒𝑒−𝑓𝑖𝑙𝑒𝑑
𝑛
6𝐸𝑙 𝐼Δ𝑑𝑙𝑖𝑛𝑖𝑛𝑔 𝜋
𝑀(𝜃) = − 𝑐𝑜𝑠2 (𝜃 + )
𝑑2 (1 − 𝜐𝑙2 ) 4
𝑛
24𝐸𝑙 𝐼Δ𝑑𝑙𝑖𝑛𝑖𝑛𝑔 𝜋
𝑉(𝜃) = − 𝑐𝑜𝑠2 (𝜃 + )
𝑑3 (1 − 𝜐𝑙2 ) 4
5.8.2 Results
In the table below the terms introduced in the previous paragraph are detailed and the
correspondent values are shown.
The characteristic seismic internal forces are calculated in two main geo-mechanical
configurations:
ROCK PARAMETERS
Rock unit weight rm (kg/m3) 2300 2300
Elastic modulus of the rock Em (MPa) 3000 10000
Elastic modulus of the rock Em (kPa) 3000000 10000000
Poisson ratio vm (-) 0.25 0.25
Small strain rock shear
Gmax (kPa) 1200000 4000000
modulus
Shear wave velocity Cm (m/s) 722 1319
TUNNEL PARAMETERS
Tunnel equiv. diameter d (m) 11.8 11.8
Tunnel radius r (m) 5.88 5.88
Once the actions in the ring are known, they are compared with the structural capacity of the
reinforcement segments and of joints, gaskets and connectors.
The steel cage resulting from the structural sizing of the segments is generally composed by:
− Two steel grids placed at the intrados and extrados of the segment, respectively;
The structural verification of the segment is carried out considering a reinforced section with
100 kg/m3 steel ratio. The check is carried out per meter in the out-of-plane direction. The
verification considers the maximum design bending moment and the minimum characteristic
axial force in order to maximize the eccentricity.
According to IS, the characteristic seismic internal forces are multiplied by a factor of 1.5
when combined with the static ones. The static internal forces are always multiplied by a
partial factor of 1.5.
Table 5-7: Maximum bending moment and axial forces in absolute values.
Seismic increment
Characteristic maximum Design maximum Total
(Design)
Sectio
n Nmin Mmax Nmin Mmax Nmin Mmax N M
[kN/m] [kNm/m] [kN/m] [kNm/m] [kN/m] [kNm/m] [kN/m] [kNm/m]
LO1 520 69 780 104 5 14 785 117
CC1 93 10 140 15 5 14 144 29
FA1 1047 10 1571 15 5 14 1575 29
HO1 339 2 509 3 5 14 513 17
MF1 230 1 345 2 3 8 348 9
The Figure 5-47 below shows that the internal forces are in the M-N domain for all the
analysed section.
200
150
LO1
100
50 LO1 CC1
HO1 FA1
Mrd [kNm]
0
-1000 -500 0 500 1000 1500 2000
-50
-100
-150
-200
N [kN]
M-N Domain Internal forces
Figure 5-47 Bending moment and axial forces check for all the analysed sections.
The table below shows the strength design values of the reinforced concrete section used in
the temporary situations.
Strength
Section
Short-term Concrete M15 -
Long-term Concrete M50 -
Steel 100 kg/m3
ULS
MULS,ST 107.6 kNm/m
MULS,LT 122.2 kNm/m
MULS,ST 215.2 kNm
MULS,LT 244.4 kNm
6.1 DEMOULDING
For demoulding, it should be considered that, after casting, each segment is aged in the
formwork until the concrete has reached a minimum compressive strength equivalent to M15,
before being lifted out of the formwork. The segments are lifted out of the formwork by
vacuum pads fixing the segment at its centre; this can be studied with the simplified static
system shown in the following figure.
During this stage, the segment is stressed by his own weight and by the adherence strength
of moulder as well. Considering the segment will be demoulded my means of a vacuum
device, the dead load is increased by 50% to account for the dynamic load. Basing on similar
experiences, the adherence strength could be evaluated approximately in 10 kPa and
considered as a variable load. The structural analysis is carried out considering the very
conservative assumption of segment restrained only at its central position.
The structural verification of the segment is carried out considering a 100 kg/m3 steel
reinforced section. Considering the strength values of Table 6-1, the verification is satisfied.
Check
ULS Verified
6.2 STORAGE
The segments are stored outside the factory by stockpiling together those forming a complete
ring. The first segment is placed on two supports in 0.8 m to the segments centre. Each
additional segment is placed on two supports that are aligned vertically over the first
supports.
To prevent large bending moments and shear forces, it is important that the supports
between the segments are aligned vertically. To check potential damage to the segments
due to inappropriate vertical alignment of the supports, two different cases will be considered:
(I) internal misalignment of supports by 100 mm and (II) external misalignment of supports
by 100 mm (as shown in the following figure).
Since storage in stack will be effectuated immediately after demoulding, when complete
concrete maturation has not been reached yet, as for demoulding verification a characteristic
cylinder compressive strength equal to 12 MPa is taken into account.
The structural verification of the segment is carried out considering a 100 kg/m3 steel
reinforced section. As a safety choice, no axial force is considered. Generally, the curing
process is not finished during storage in stack and a concrete grade of M15 is considered.
nstock 8 -
Wsup 632.8 kN
R 316.4 kN
pult 9.38 kN/m/m
e 0.1 m
Lsupports 0.80 m
Lsbalzo 1.45 m
Check
ULS Verified
6.3 HANDLING
A handling clamp will be employed for handling the segments. At the time of writing, no
indication about the geometry of the device was available. It’s assumed that the clamp can
lift a maximum of three segments at the same time.
A total load of 168.8 kN weights on the base segment, divided in two concentrated forces
(considered variables) of 84.4 kN each one. Dead load of the base segment and variable
loads due to the weight segments are increased by 50% to take into account dynamic effects.
As we defined an offset d = 0.1 m in the storage check, the following static schemes will be
adopted.
The structural verification of the segment is carried out considering a 100 kg/m3 steel
reinforced section. As a safety choice, no axial force is considered.
Check
ULS Verified
The ground for the backfilling is injected at a certain pressure in the tail void between the
installed ring and the rock/soil. The grout pressure acts as a distributed load on the final
lining.
During the excavation phase and until the hardening of the grouted backfilling, the effect of
the radial pressure can be analysed with the Mariotte’s formula:
𝑃𝐷 500𝑘𝑃𝑎 ∙ 11.75𝑚
𝜎 = 𝛾𝑄 = 1.5 = 11.8 𝑀𝑃𝑎 < 𝑓𝑐𝑑 = 26.7𝑀𝑃𝑎
2∙𝑡 2 ∙ 0.375𝑚
Where P is the injection pressure (kPa) equal to the maximum value of 500 kPa, D is the
tunnel diameter (m) and t is the thickness of the final lining (m).
6.5.1 Overview
The thrust force was estimated summing two components: (a) the face support pressure
applied at the front, (b) the force required to overcome the shield friction.
The TBM advancement is obtained through hydraulic jacks pushing against the mounted
segmental rings. Concentrated thrust applied locally leads to high localized compressive
forces and tensile splitting forces in the ring joint.
The calculation of the stress state originating in the segmental lining takes into account the
arrangement of the hydraulic jack around the ring and the detailed geometry at the jack-
segment contact.
The resistance of the segments against the TBM thrust jacks must be checked by verifying
that the segments reinforcement withstands:
6.5.2 Compression
The area of the circular section loaded by the thrusting rams is equal to:
The verification is carried out considering the maximum nominal thrust Smax:
The stress in the lining along the longitudinal direction induced by the thrust of the TBM is
equal to:
The stress (independent from the arrangement of the rams along the ring) is much lower
than the compressive strength fcd (M50). The lining can sustain the maximum nominal thrust
of the TBM.
The verification is carried out considering the concentration of stress induced by the thrusting
ram in the localized area underneath.
For this check, reference is made to the stress distribution induced by small loading
according to §6.7 of l’EN 1992-1-1:2004 and showed in the figure below.
Figure 6-7 Model for the stress distribution of small loading area.
The rubber contact of the shoe is assumed with a rectangular shape with dimensions bo =
33 cm e l0 = 103 cm. The rubber contact distributes the thrust of a couple of jacks. The rubber
contact area is equal to:
The maximum homothetic distribution of the force in the segment thickness (Ac0) is equal to:
The verification is carried out considering the maximum nominal thrust Smax of thrusting ram:
In case the thrusting jacks are not positioned accurately, an eccentricity between the ram
axis and the segment axis could happen. In such a case, the stress distribution is not uniform.
The accidental eccentricity of the thrusting force can be taken into account as follows:
2 ∙ 𝐹𝑠𝑑
𝜎𝑚𝑎𝑥 = 𝑖𝑓 𝑒 > ℎ1 ⁄6
3 ∙ (ℎ1 ⁄2 − 𝑒) ∙ 𝑏
𝐹𝑠𝑑 6∙𝑒
𝜎𝑚𝑎𝑥 = ∙ (1 + ) 𝑖𝑓 𝑒 ≤ ℎ1 ⁄6
𝐴𝑐0 ℎ1
Where:
h1 = width of the rubber shoe on which act the force produced by the jack, considering the
most unfavourable dimension (330 mm)
Two different load configurations are considered where the maximum allowable eccentricity
is prescribed in order to avoid structural damage to the segments or concrete spalling:
− CASE 2: maximum allowable eccentricity and working thrust (p=300kPa) with Q=1.5:
𝐹𝑠𝑑 = 2711 𝑘𝑁 (e = 0.07 m)
6.5.3 Splitting
6.5.3.1 Generalities
High concentrated forces are introduced in the lining by the thrust of the rams. As a result, a
so-called disturbed region (D-region) developed, as schematically shown in figure below for
a load acting on a 2D element (Collins & Mitchell, 1997), leading to:
Figure 6-9 Single concentrated load acting on a slab. Example of 2D D-region, (Collins &
Mitchell, 1997).
A local reinforcing bars for withstanding to these tensile stresses after cracking is necessary.
The total transverse bursting force Z (Fsd), is calculated as (Leonhardt, 1977):
𝑑1 330𝑚𝑚
𝐹𝑠𝑑 = 0.25 ∙ 𝑃 ∙ (1 − ) = 0.25 ∙ 8750𝑘𝑁 ∙ (1 − ) = 263𝑘𝑁
𝑑2 375𝑚𝑚
Where the ratio d1/d2 basically governs the amount of expected bursting stresses and P
corresponds to the applied load by the ram, computed with the maximum nominal thrust:
263𝑘𝑁
𝐴𝑠 = 𝐹𝑠𝑑 /𝑓𝑦𝑑 = = 6.71𝑐𝑚2
391300𝑘𝑃𝑎
Zy
Zz
a) b)
Figure 6-10 Scheme of the superposition of principal compressive trajectories (two-planes)
in presence of a 3D D-region (Leonhardt, 1975) b) 3D D-region as the sum of two
2D contributions.
In case of eccentric force, the total transverse bursting force Z (Fsd), is calculated as
(Hiltscher and Florin, 1963):
2𝑒 2∙50𝑚𝑚
𝐹𝑠𝑑 = 0.15 ∙ 𝑃 ∙ (1 − √ ) = 0.15 ∙ 8750𝑘𝑁 ∙ (1 − √ ) = 262𝑘𝑁
𝑑2 375𝑚𝑚
Where the ratio e/d2 basically governs the amount of expected bursting stresses, e is the
eccentricity of the load equal to 50 mm and P is the applied load by the ram.
262𝑘𝑁
𝐴𝑠 = 𝐹𝑠𝑑 /𝑓𝑦𝑑 = = 6.71𝑐𝑚2
391300𝑘𝑃𝑎
Note that similar relationships are reported in recommendations concerning precast tunnel
segments (AFTES; ITA Report (2000) and DAUB).
The splitting forces of all the rams affect the opposite side with respect to the thrust. The total
transverse bursting force Z (Fsd), is calculated as (Hiltscher and Florin, 1963):
𝑑1 330𝑚𝑚
𝐹𝑠𝑑 = 0.25 ∙ 𝑁𝑒𝑑 ∙ (1 − 𝑑2) = 0.25 ∙ 2938𝑘𝑁 ∙ (1 − 375𝑚𝑚) = 88𝑘𝑁
Where the ratio d1/d2 basically governs the amount of expected bursting stresses and Ned
corresponds to the applied load by all the rams along the lining perimeter, computed with the
maximum nominal thrust:
88𝑘𝑁
𝐴𝑠 = 𝐹𝑠𝑑 /𝑓𝑦𝑑 = = 2.25𝑐𝑚2
391300𝑘𝑃𝑎
The effect of the eccentricity between the thrusting ram axis and the segment axis produce
internal forces in the longitudinal direction. The structural verification of the segment is carried
out considering a 100 kg/m3 steel reinforced section.
Two different load configurations are considered according to the maximum allowable
eccentricity prescribed in §6.5.2.3 to avoid structural damage to the segments or concrete
spalling:
− CASE 2: maximum allowable eccentricity and working thrust (p=300kPa) with Q=1.5:
𝐹𝑠𝑑 = 2711 𝑘𝑁 (e = 0.07 m)
7. TECHNOLOGICAL PARTS
7.1 CONNECTORS
7.1.1 Introduction
The connectors along the circumferential joint (between two rings) can be verified according
to the calculation scheme proposed in the following picture, where it’s considered the case
of an accidental disengagement of the rams on the top segments. In such a way, the specific
requirements for the shear and pull-out strength of the connectors will be determined.
7.1.2 Shear
𝑊 84.4𝑘𝑁
𝑉 = 𝛾𝑄 ∙ = 1.5 ∙ = 63.3𝑘𝑁
2 2
Where W is the weight of the segment (kN), γQ is partial coefficient for variable load. A shear
strength higher than 80 kN is prescribed.
7.1.3 Pull-out
The bending moment induced by the dead weight of the segment is computed as:
𝑊 ∙ 𝐿𝑙𝑜𝑛𝑔 84.4𝑘𝑁 ∙ 2𝑚
𝑀 = 𝛾𝑄 ∙ = 1.5 ∙ = 126.6𝑘𝑁𝑚
2 2
Where W is the weight of the segment (kN), γQ is partial coefficient for variable load and
Llong is the segment depth.
𝑀 126.6𝑁
𝑇= = = 158.2𝑘𝑁𝑚
2 ∙ 𝑧 2 ∙ 0.40𝑚
7.2 GASKETS
7.2.1 Introduction
Single segmental linings are sealed by gasket frames. The proof of suitability for the gasket
frames is carried out by experiments. It is recommended a Dätwyler M38936 Type “Rennes”
or an EPDM anchored gasket with equivalent properties.
Geometry
d1 49 mm
ds/2 51 mm
ds 102 mm
a 26 mm
b 3 mm
g1 12 mm
g2 12.1 mm
l min 29 mm
Figure 7-3 Typological geometry of the gasket with the dimensions used in the calculations.
The decisive water pressure shall be maintained without leakage. The tightness tests are
carried with different offsets and groove basic gaps. It shall be accounted for, that the gaskets
must also be effective, if the lining deforms and/or the construction tolerances are fully
utilized.
After installation, the segments are loaded and consequently the joints may open locally.
Moreover, assembly inaccuracies as well as the different loading of the segmental rings lead
to offsets after installation, which are usually limited to a maximum of 10 mm.
The compressive stress decay in the gaskets due to a short-term relaxation is shown in the
figure below. The relaxation is equal to 30%.
The joint gap width for the design of the element can be determined starting from the force-
displacement line of the gasket applying the following contributes:
The total assumed gap is almost 5 mm. In the tightness diagram this value guarantee water
tightness at least for pressure of 10.0 bar:
Where Pnominal is the maximum water pressure on the tunnel alignment taking into account
the uncertainties under Malabar Hill.
At the edges of the groove for the gasket, compressive stresses are introduced into the
segments due to the compression of the gaskets during installation of the segments. Due to
the redistribution of these stresses in the segment, transverse tensile stresses occur.
Because of the small size of the groove for gasket, and the small spacing between the groove
and the outside edge of the segment, the installation of a tensile splitting reinforcement in
this zone usually is not possible. Therefore, the tensile strength of the unreinforced concrete
of the segment is accounted for the proof of the transverse tensile stresses.
Technological
Tolerance
= 2 mm
γm 1.8 -
Leonhardt (1977)
The verification is satisfied since the strength values is higher than the loading one.
The shear loading of the unreinforced concrete of the segments shall not exceed the
admissible values. Because of the small size of the groove for gasket, and the small spacing
between the groove and the outside edge of the segment, the installation of a shear
reinforcement in this zone usually is not possible.
The verification is satisfied since the strength values is higher than the loading one.
k 2 -
vmin 0.63 -
Vrdmin 18.8 kN
Shear Load
Fd 74.3 kN/m
p 1350 kN/m2
Vs,c 16.3 kN/m
8. CONCLUSIONS
A 11.00 m internal diameter, 375 mm thick segmental lining was designed for TBM-
excavated tunnel of the Mumbai Coastal Road project (Package IV).
The proposed lining, which is made of grade M50 concrete and is reinforced with a steel ratio
of 100 kg/m3, was verified in the permanent situation by means of 2D FE analysis that
covered the different geotechnical conditions encountered at the site.
- segments demoulding,
- stockpiling,
- handling,
- TBM thrust during construction
- grouting during construction
The proposed lining satisfies all the design checks mentioned above.