You are on page 1of 10

Doc Name: INTEGRATED RISK ASSESSMENT

REVIEW(IRAR) PROCEDURE

Doc Code : BCG/TM/PRO-03/13 Rev:00

1.0 PURPOSE
This procedure describes the methodology of identification of Environmental Aspects as well as the
Occupational
Hazards, evaluating the Impact of the aspects and hazards, by applying a structured rating scale and taking
actions on the significant or unacceptable aspects or hazards and achieve the acceptable risks using Integrated
Management Programme

2.0 SCOPE
All activities routine or non-routine, carried out during fabrication, storage, maintenance installation at site and
activities carried out in the office premises including those carried out by our subcontractors, and the visitors
which have significant impact/risks direct or indirect on the environment and or on the OH&S.

3.0 RESPONSIBILITY
The MR and the functional representatives are responsible for identifying the aspects and hazards and their
associated risks in their respective areas alongwith the participation of workforce.

4.0 DEFINITIONS & VOCABULARY


Acceptable Risks:
Risk, that has been reduced to a level, which can be tolerated by BCG, having regard to the legal
obligations and our own IMS Policy. – Risk Value less than 5 - Refer Annexure 1

Environment:
Surroundings in which BCG operates, including air, water, land, natural resources, flora, fauna, humans
and their interrelation

Environment Aspect:
Element of BCG’s objectives/ products / services, that can interact with the environment.

Environmental Impact:
Any changes to environment whether adverse or beneficial, wholly or partially resulting from BCG’s
environmental aspects.

Environmental Management System- (EMS):


Part of BCG’s management system used to develop and implement our QHSE policy and manage our
environmental aspects.

Activity Name Date Signature

Preparation MR 10TH NOV. 2013

Review MR 15TH NOV. 2013

Approval CEO 20TH NOV. 2013

Page 1 of 10
Doc Name: INTEGRATED RISK ASSESSMENT
REVIEW(IRAR) PROCEDURE

Doc Code : BCG/TM/PRO-03/13 Rev:00

QHSE Objective:
Overall QHSE goal, consistent with QHSE policy that BCG has set itself to achieve.

HSE Performance:
Measurable results of BCG’s management of its HSE objectives.

Hazard:
Source, situation or act with a potential for harm in terms of injury or ill-health during activities
performed by BCG workforce.

Ill Health:
Identifiable adverse physical or mental condition arising from and/or made worse by a work activity/
work-related situation/ during the activities performed by BCG workforce.

Incident:
Work-related event(s) in which an injury or ill health (regardless of severity) or fatality occurred, or could
have occurred

Integrated Management System- (IMS):


Management system that integrates all of BCG’s systems and processes into one complete framework,
enabling our organization to work as a single unit with unified objectives.

IRAR : Integrated Risk Assessment Review –


a methodology of conducting the Impact and Risk Assessment of EMS and OHSMS respectively as
mentioned in the definition of Risk Assessment below.

Nonconformity:
Non-fulfilment of a requirement.

Occupational Health & Safety Management System- (OHSMS):


Part of BCG’s management system used to develop and implement our QHSE Policy and manage our
OH&S risks

Prevention of Pollution, Injury & Il-health:


Use of processes, practices, techniques, materials, products, services or energy to avoid, reduce or control
the creation, emission or discharge of any type of pollutant or waste, injury, incident, accident, near-miss
and ill-health, in order to reduce adverse environmental impact and occupational hazards .

Risk
Combination of the likelihood of an occurrence of a hazardous event or exposure(s) and the severity of
injury or ill health that can be caused by the event or exposure(s)

Risk Assessment: Process of evaluating the risk(s) arising from aspect(s) or hazard(s), taking into account
the adequacy of any existing controls, and deciding whether or not the risk(s) is acceptable

Workplace: Any physical location in which work related activities are performed under the control of
BCG management.

Page 2 of 10
Doc Name: INTEGRATED RISK ASSESSMENT
REVIEW(IRAR) PROCEDURE

Doc Code : BCG/TM/PRO-03/13 Rev:00

5.0 PROCEDURE

5.1 The Manager Project and Maintenance under the guidance of the MR collect information about
various (1) Environmental aspects & (2) Occupational Health & Safety of company’s own
operation and interface activities of sub-contractor (s) / suppliers including their impacts related to
activities.

5.2 IRAR ANALYSIS format BCG/TM/FRM-04/13 to be used for gathering the information from
the concerned areas and employees.

5.3 Ensure following points are considered, while Identifying Aspects & Hazards and subsequent
impacts (EMS and OHSMS point of view);

 The activities carried out by employees as well as Sub contractors.


 The activities/ transport/ material/ packing material interface with the Suppliers
 Facilities at site / workplace.
 Monitoring trends
 Routine & non routine activities
 Normal, abnormal and emergency conditions.
 Behavioral hazards
 Hazards originating from the outside of the organization having significant risk to the
workforce.
 Falls from heights
 Collapse of excavations / trench walls
 Injury from construction plant and equipment
 Injury from moving, flying or falling objects
 Injury while handling and lifting
 Slip, Trip or fall
 Suffocation
 Exposure to hazardous chemicals, gases
 Fires
 Electric Shocks
 Emission to air
 Discharge to drain
 Contamination of land
 Noise Pollution
 Use of raw material and natural resources
 Waste management- current practices

5.4 During identification of significant environmental aspects, keep in view the applicable legislative/
regulatory and other requirements.

Page 3 of 10
Doc Name: INTEGRATED RISK ASSESSMENT
REVIEW(IRAR) PROCEDURE

Doc Code : BCG/TM/PRO-03/13 Rev:00

5.5 Compile the information and validate the same by through previous monitoring reports / any legal
notice or legal non-compliance. Also consider any accidents, minor or reportable as well as
incidents- potential emergency situations with the assistance of the concerned personnel

5.6 Based on the received/validated information, identify the aspects /hazard that can have an impact
on the environment. Ill-health or safety. Ensure that for each activity Aspect / Hazard are
mentioned separately to understand their unique rating, this will also enable identification of
unique Impact / Risk respectively.

5.7 Evaluate the identified aspects and hazards with HOD for determining significant aspects using the
criteria as given in Annexure of this procedure.

5.8 Follow the steps given below for carrying out Aspect / Hazard Identification and Impact/ Risk
Analysis:

5.9 Department / Section: Indicate the Department/ section in which IRAR is being conducted.

5.10 Activity: Indicate the activity for which the IRAR is conducted.

5.11 D/I: Direct or Indirect control over the activities.

5.12 Environmental Aspect / Occupational Hazard: the situation where the emission, vibration,
discharge, waste, noise, fire, fall, slips etc. are generated/ are probability (ies).

5.13 N/A/E: Indicate if the situation is normal, abnormal or emergency

5.14 Impact/Significant Risks: The consequence of the aspect / hazard like natural resource
depletion, soil/water/ air pollution, noise pollution, accident, slip, fall from height, exposure to gas/
heat/ dust, fatality etc. Ensure all the applicable impacts of the single aspect/ hazard are identified
separately.

5.15. Based on the above evaluation, calculate the Impact- the Magnitude as;

‘M’= (L*S)/C and rank the aspect / hazard based on impact score

(Note: For L & S Refer Annex-1) In case of the legal requirement found during the IRAR ,
identify and mark with “LL” at the relevant column of the format.

Page 4 of 10
Doc Name: INTEGRATED RISK ASSESSMENT
REVIEW(IRAR) PROCEDURE

Doc Code : BCG/TM/PRO-03/13 Rev:00

5.16 MR and the Heads of Fabrication and Installation to validate the score w.r.t. the current
practices and the monitoring trend. Ensure that the impact is calculated on the current status
and practices of the activities.

5.17 Arrive at significance level with following criteria

 Applicable legal and other requirements , identify for all the significant aspects the same by
the legend LL
 The existing control level of the organization in terms of the Engineering control, Documented
Procedures etc.
 all the emergency situations are taken in to consideration
These parameters shall decide the minimum score from where the significant impacts can be
identified. As a general guideline Risk Value greater than 10 and above should be considered for
defining controls. All the legal requirements are considered as significant.

5.18 Record the significant aspects/hazards in the “RISK Register” BCG/TM/FRM -05/13 for
which Integrated Management Programme is required to be planned while for others ensure that
Integrated Operational Procedure are identified. Ensure action plan by way of Integrated
Management Program (IMP) Objectives Targets and IMP- BCG/TM/FRM -06/13 for such
hazards follow the below mentioned hierarchy:

1. Elimination
2. Substitution
3. Engineering controls
4. Signage/warnings and/or administrative controls
5. Personal protective equipment
Adopt the best suitable option or the mix of option for the respective hazard for risk control.

5.19 Review the IRAR once a year or whenever there is major modification / update / addition
in process/activities.

5.20 In addition, if there is new knowledge regarding environmental impacts has been identified
during audits or in case of amendments to legislative requirements, review and update the “IRAR”.

6 RECORD:
IRAR ANALYSIS REPORT: BCG/TM/FRM -04/13

RISK REGISTER: BCG/TM/FRM -05/13

INTEGRATED MANAGEMENT PROGRAMME: BCG/TM/FRM -06/13

Page 5 of 10
Doc Name: INTEGRATED RISK ASSESSMENT
REVIEW(IRAR) PROCEDURE

Doc Code : BCG/TM/PRO-03/13 Rev:00

ANNEXURE 1- RATING SCALE

IRAR Risk Assessment Guidelines (the periodicity / frequency/ percentages mentioned are for guidance
only- do not consider it as limits)

(A) LIKELIHOOD OF OCCURRENCE- “L”:

5) CERTAIN : Can Occur any time.

4) VERY LIKELY: Chances of Occurrence is once a month

3) LIKELY: Chance of occurrence is more than 4 times a year

2) LESS LIKELY : Chance of occurrence may be once a year. Not all people are regularly trained.

1) UNLIKELY: No history of Occurrences in other similar industry also NO history of the occurrence in our
Organisation.

(B) SEVERITY OF OCCURRENCE: “S”


(a) is Environment related and (b) is Occp. Health & Safety

5) EXTREMELY HIGH: (a) Environmental impact spreads outside the Organisation. (b) FATAL OR Very
Serious Injury and/or Ill-health resulting in Absence from work more than 6 MONTHS.

4) HIGH: (a) Environment impact is within the entire Organisation. (b ) Serious Injury and/or Ill-health
resulting in Absence from work more than 1 MONTH.

Page 6 of 10
Doc Name: INTEGRATED RISK ASSESSMENT
REVIEW(IRAR) PROCEDURE

Doc Code : BCG/TM/PRO-03/13 Rev:00

3) MODERATE: (a) Environment impact is within the same Department. (b ) Injury and/or Ill-health
resulting in Absence from work for more than 3 DAYS.
2) LOW: (a) No significant Environment Impact and limited within the work place, (b ) Injury and/or Ill-
health resulting in absence from work of 1 DAY.
1) NEGLIGIBLE: (a) No Environment Impact. (c )Injury and/or Ill-health No significant loss in work
HOURS.

Page 7 of 10
Doc Name: INTEGRATED RISK ASSESSMENT
REVIEW(IRAR) PROCEDURE

Doc Code : BCG/TM/PRO-03/13 Rev:00

(C) EXISTING CONTROLS IN PLACE- “C”

1.0) VERY HIGH CONTROL: Processes or Procedures are in place in All AREAS and the benefits are very
apparent, almost all areas and activities are well managed by having Process Measurements and also
Improvements on Continual basis. All people are aware of the process / procedure requirements. All
Documents and Records are well Managed and easily retreivable. Most of the processes / procedures have
FOOL PROOF mechanism.

0.8) HIGH CONTROL: Processes or Procedures are in place in All AREAS and the benefits are also
apparent, Process Measurements are in place in many Areas. Highly competent people.

0.5) MODERATE CONTROL: Processes or Procedures are in place in All AREAS but the benefits are NOT
very apparent, Process fairly implemented and only in couple of Areas the Process Measurements are in place .

0.3) LOW: Process or Procedures in place in most areas but not well implemented. Less than 50% people are
Competent and Trained

0.1) VERY LOW CONTROL: Only a few Processes or Procedures are in place and only a handful or
very few people are Competent or Trained.

GENERAL GUIDELINES:

LIKELIHOOD SEVERITY CONTROL MAGNITUDE

L: Likelihood or Probability of S: Severity of the C: Present Control


M = (L*S)/C
Occurrence/Failure Impact / Occurrence Measures

TYPE OF ACTIVITY BEING PERFORMED NATURE OF IMPACT

N - Normal D - Direct
A - Abnormal I - Indirect
E - Emergency  

Page 8 of 10
Doc Name: INTEGRATED RISK ASSESSMENT
REVIEW(IRAR) PROCEDURE

Doc Code : BCG/TM/PRO-03/13 Rev:00

Environmental
Env. Impact OH&S Hazards OH&S Risk
Aspect
Emission of Air Air Pollution Slip/ Trip Hazards Minor Injury
Release of Gas / /
Ozone depleting Ozone Depletion Caught in/ Obstructed by/ hit by Major Injury/ Fracture /
substances
Hazardous waste Land Fill-/ Green Temporary Disability/
Fall from height
Disposal House Gases Permanent Disability
Irritation/ nausea / Respiratory
Exposure to Gas/ Heat/ Extreme
Spills/ Leak Soil Pollution Disorders (WITH LONG
Cold/ Dust
EFFECT)
Consumption of
Natural Resource
Natural Resources Repetitive Movements / Long Backache / muscular pain-
Depletion / Non-
:Water/ Electricity/ Working in similar posture disorders
renewable resources
Air/ Fuel/ Paper
Fire / Explosion/ Blast / Hit by
    car/ Road Accident / Fatality/ Multiple Fatality
Train-Air Accident

DECISION OF ACCEPTABLE RISK- ANYTHING ABOVE "20" IS


NOT A ACCEPTABLE RISK
AFTER YOU USE THE FORMULA (L*S)/C YOU WILL GET SCORES, NOW CATEGORISE THEM
USING THE THE FOLLOWING BANDS

LOW <10 No action Reqd

No action reqd but maintain and monitor


MEDIUM >10 < 20 controls
Action reqd to be completed in next 120
HIGH >21 < 80 days
Immediate Action reqd to be initiated to
EXTREME > 80 reduce the Risk Level to below 20 within
60 days .

Page 9 of 10
Doc Name: INTEGRATED RISK ASSESSMENT
REVIEW(IRAR) PROCEDURE

Doc Code : BCG/TM/PRO-03/13 Rev:00

CROSS REFRENCE OF PROCEDURE

Section No Procedure Format Page no in the procedure

BCG/TM/FRM- 2

4.3.1 04/13

BCG/TM/FRM 5
BCG/TM/PRO-03/13

-05/13

BCG/TM/FRM 5

-06/13

Page 10 of 10

You might also like