You are on page 1of 3

PT.

Mandala Putera Prima


Ruko Pejaten Town House No. 3-4
Jl. Salihara I Pasar Minggu Jakarta 12520
(P) +62 21 78848389
(F) +62 21 78848397
QUOTATION
No: 002/LTG/Q-MPP/RF/III/20
This quotation is subject to the terms and conditions as stipulated in this letter, unless otherwise specifically agreed in separate contract
CLIENT: Date : Maret 27th, 2020
PT. PEMBANGUNAN PERUMAHAN (PERSERO), TBK. Subject : Quotation of Feeder Cable PJI Perimeter
PJU Parimeter - NYIA, KULONPROGO

Attn : Bpk. Untung Susilo From : KKH


Phone : Cc :
Fax : Attached : BOQ
Email : Email : kukuh@mandalapp.com

Dear Pak Untung,


Kindly please find our quotation as following:

UNIT PRICE UNIT PRICE


NO. DESCRIPTION VOL UNIT
(IDR) (IDR)

PEKERJAAN PENGADAAN DAN PEMASANGAN KABEL FEEDER PJI


1 1 ls 517,500,000.00 517,500,000.00
PARIMETER YIA

TOTAL (IDR): 517,500,000.00


PPN 10% (IDR): 51,750,000.00 +
GRAND TOTAL (IDR): 569,250,000.00

1. TERM & CONDITIONS


1.1. Price are exclude 10% PPN & PPH
1.2. Term of Payment:
- 50%, DP 50% after finished

1.3. Services Condition:


- Delivery point: Franco on Site, NYIA, Kulonprogo, Yogyakarta

2. VALIDITY OF OFFER
2.1. This quotation valid for 1 (one) week from the date of this letter, afterward we reserve the right to review our price structure.

Should you have any further questions, please feel free to contact us. We are looking forward for your feedback. Thank you.

Sincerely Yours,

legitimate w/o signature

KUKUH PANUWUN
+62 81286456242
KEGIATAN : PEKERJAAN PENGADAAN DAN PEMASANGAN KABEL FEEDER PJI PARIMETER YIA
PELAKSANA : PT. PEMBANGUNAN PERUMAHAN (PERSERO), TBK
LOKASI PROYEK : KULONPROGO, YOGYAKARTA
0.70 0.70 27,750.00

Harga Satuan Jumlah Harga Total Harga Material &


No. Uraian Sat Volume Material Upah Material Upah Upah
Rp Rp Rp Rp Rp
1 2 3 4 5 6 7=4x5 8=4x6 9=7+8

1 Pengadaan dan penarikan kabel NYFGBY 4 x 50 mm2 meter 1000 277,500.00 27,750.00 277,500,000.00 27,750,000.00 305,250,000.00

2 Galian dan urugan meter 1000 57,000.00 57,000,000.00 57,000,000.00

TOTAL F 362,250,000.00
KEGIATAN : PEKERJAAN PENGADAAN DAN PEMASANGAN KABEL FEEDER PJI PARIMETER YIA
PELAKSANA : PT. PEMBANGUNAN PERUMAHAN (PERSERO), TBK
LOKASI PROYEK : KULONPROGO, YOGYAKARTA

Harga Satuan Jumlah Harga Total Harga Material &


No. Uraian Sat Volume Material Upah Material Upah Upah
Rp Rp Rp Rp Rp
1 2 3 4 5 6 7=4x5 8=4x6 9=7+8

1 Pengadaan dan penarikan kabel NYFGBY 4 x 50 mm2 meter 1000 396,428.57 39,642.86 396,428,571.43 39,642,857.14 436,071,428.57

2 Galian dan urugan termasuk pelindung kabel meter 1000 81,428.57 81,428,571.43 81,428,571.43

TOTAL F 517,500,000.00