RISK OBSERVATION/RISK EXISITING CONTROLS/ACTION FURTHER ACTION PROPOSED RESPONSIBILITY

Use of old and worn-out  


INSURANNCE OF LAND CRUSER/ equipment without insurance There should be funding
PROPERTY can be of great risk to the allocated for insurance of
  council e.g. is the motor property under LDP, so that There should be proper
Probability: H vehicle like the land cruiser property for the projects and planning for insurance of
Impact : H which is always on the road the council are secure property to avoid loss in case
  and the risk is too high to the in case of disaster of an accident in the future.
  institution     Director of Admin/Finance

The impact of not spending


according to time is that the
community at large may not I propose that, at the
receive the service when they There should be beginning of the year in
need it. implementation plans Both DDCC and management
And probably we may risk accordingly ,strategically implementation plans should Director of Planning
Reduction funds an showing how and when to be critically emphasised as
LUCK OF TIME SCHEDULED experience we have gone spend funds to avoid going we submit the budgeted
IMPLEMENTATION through as a council. with unspent funds in Expenditure lists from various
PLANS Which affects the community The proceeding years departments.
that needs the development There should be an
Probability: H in the long run. attachment
Impact : H of a time bound
  implementation plan which
should be followed
critically to avoid rush hour
spending when its end of year
LUCK OF SUPLEMENTARY BUDGETS ON It has been noticed that there Every expenditure must be
VARIATION OF AND EXCESS FUNDS are no supplementary accounted for by planning Before funds are spent there
budgets drafted on variation accurately how it will be should be a budget in place. Director of Planning
Probability: H of contractual works as well utilised and the Which should account for
Impact : H as any extra funds emanating Only way is to budget for it. each and every expense.
  from gains, from our , rather than spending before
  cooperating partners, hence Its fully accounted by way of
Spending is being done. There an expenditure plan?
is a high risk of manipulation  
of funds if budgets are not  
Generated. Budgets will help
us account for Funds
accurately unlike otherwise.
CRACKS ON BUIDINGS
Probability: H There is a high risk of BOQ to renovate the Civic Periodic mentainance is Planning and Engineering
Impact : H accidents occurring due Centre and periodic check necessary departments under its
obsolesce of building inspection by our building Directorate
inspectorate team
Probability: H
Impact : H
 
NON AVAILABILITY OF CONSTANT
RUNNING WATER It was observed water is Borehole has being sunk at Need for installation of the Director of Human Resources
Probability: H stored in buckets for use in the civic centre existing borehole to be and Admin in collaboration
Impact : H toilets and there is a risk of functional. with director of engineering
  disease if there isn’t enough
running water

Director of Admin in
Use of old and worn-out Requested for new PPE attire New attire should be collaboration with Director of
LACK OF PERSONAL PROTECTIVE
equipments for all workers purchased for the section Engineering
Equipments(PPE)

Probability: M
Impact : H
 
LACK OF OFFICE EQUIPMENT Use of personal and old office Requested for new office
Probability: L Use of personal and old office equipments equipments Director of Planning
Impact : M equipments
 
No procurement plan in place Procurement should come up
DELAY IN PROCUREMENT OF There is risk of execution of by originating departments with a procurement plan
MATERIALS work according to time and and section. submitted by the Director of Admin
works delay departments and sections.
Probability: H
Impact : H
 

LOSS OF SOFT WARE INFORMATION computers at the council


have not Antivirus and there Antivirus installed There is need to Provide Programmer under planning
Probability: H is a risk of loss of data in cases external backup director in collaboration with
Impact : H where the system director finance
  malfunctioned
LACK OF TRANSPORTATION
The council has inadequate A budget allocated for the Proposal to procure one to TC and Director Planning
Probability: M transportation for use in daily procurement of vehicles two vehicles
Impact : H operations and the two
vehicles that are there are
over used
FIRE Fire policy,30 Fire fighters,2 Procurement of fire Ensure there are enough Chief Fire Officer under
Fire tender,1 water bauzer protection equipment like installations of fire Engineering Director in
Probability: L extinguishers. extinguishers at strategic rehearsal with director of
Impact : H positions to beef up fire finance
section

THEFT
There is a risk of theft due to Deployment of Council Police Employment of council police Director of Admin
Probability: H inadequate council police in strategic point to night
Impact : H Patrols.

LOSS OF REVENUE It has being observed that


there is loss of revenues on No revenue collection plan in There should be a time bound Director of Finance
Probability: H certain collection avenues of place its being collected at revenue collection plan in
Impact : H the council e.g. random and no Data base for place indicating time and
clients in place month of collection as well as
data base for clients.
RISK REGISTER

FOR
MBALA MUNICIPAL COUNCIL
FROM

INTERNAL AUDIT UNIT


PREPRED BY: Lloyd Muhuji

GROUP INTERNAL AUDITOR