Professional Documents
Culture Documents
ITA Report n° 23 - Planning Health and Safety Risk Management for Underground Works - N°ISBN: 978-2-9701242-5-2 / MAY 2020
Layout : Longrine – Avignon – France – www.longrine.fr
The International Tunnelling and Underground Space Association/Association Internationale des Tunnels et de l’Espace Souterrain (ITA/AITES) publishes this report to, in accordance with its
statutes, facilitate the exchange of information, in order: to encourage planning of the subsurface for the benefit of the public, environment and sustainable development to promote advances
in planning, design, construction, maintenance and safety of tunnels and underground space, by bringing together information thereon and by studying questions related thereto. This report
has been prepared by professionals with expertise within the actual subjects. The opinions and statements are based on sources believed to be reliable and in good faith. However, ITA/AITES
accepts no responsibility or liability whatsoever with regard to the material published in this report. This material is: information of a general nature only which is not intended to address the specific
circumstances of any particular individual or entity; not necessarily comprehensive, complete, accurate or up to date; This material is not professional or legal advice (if you need specific advice,
you should always consult a suitably qualified professional).
>> Foreword, Scope and Objectives >> Definitions
4 PLANNING HEALTH AND SAFETY RISK MANAGEMENT FOR UNDERGROUND WORKS ITA WORKING GROUP N°5 5
>> Introduction >> General Recommendations
1. The planning of underground construction, 1. Client organisations should establish a constraints in undertaking their design,
underground asset operations and health and safety risk management framework constraints which arise as a consequence of
maintenance, and underground asset for proposed or existing underground assets working in the underground environment.
refurbishment requires rigorous management (‘assets’) in accordance with current guidance
of risks. This is because there is generally a and good practice, technological trends, 6. Contractors having assessed and
higher level of risk within confined spaces local, national and international standards, accounted for the health and safety risks that
and associated with the use of plant and regulations and requirements through design, cannot be eliminated by the reference design
equipment underground. Therefore, such construction and operational lifecycles. (or an equivalent alternative), are placed in
activities are likely to fall outside of ‘business Accordingly, the WG recommends adopting control of the worksite and should manage
as usual’ oversight for client organisations the risk management principles of ISO 31000. the residual worksite risks. It is recommended
that do not regularly undertake underground This process should require the client to that the acceptance of these risks is explicitly
construction or maintenance. assess their own competence for procuring, done through risk registers incorporated into
operating and maintaining underground assets the construction contract.
2. The most effective risk management and, if necessary, supplement their corporate
methods are those that implement the experience with personnel experienced
hierarchy of controls of Figure 1 below. in underground design and construction,
Therefore, decisions that enable or preclude procurement, risk management and operation
the use of ‘elimination’ (that is ‘eliminating’ and maintenance.
risks) may be made early in the project
life cycle and this raises the significance 2. At each design stage, including concept
of the Clients role in health and safety risk PPE5 design and particularly prior to tendering,
management. Clients should acknowledge clients should conduct a health and safety
that by fixing the alignment and dimensions review (HSR), and use risk registers to record
of the underground asset, often as part of the following items: (i) safety and health issues
statutory consent procedures and property identified during the design reviews and
acquisition, they force the contractor to incur actions taken; and (ii) risks that cannot be
risk, which the contractor cannot eliminate/ Figure 1. Hierarchy of risk management principles. removed through design changes. (iii) primary
avoid in accordance with hierarchical risk responsibility for risk ownership. The HSR
management principles shown in Figure 1. risk register should be a live document which
This aspect also emphasizes the importance will be updated as and when new risks are
of establishing that a reference design for identified.
the underground assets is safe to construct,
maintain and operate, prior to tendering. 3. Client organisations should implement
and maintain oversight of health and safety
processes for activities undertaken by them
or on their behalf by formal review throughout
design phases for the assets and throughout
construction, operations and maintenance
or whenever design changes are made
(recommended by ISO 45001)
5
PPE : Personnal Protective Equipment
6 PLANNING HEALTH AND SAFETY RISK MANAGEMENT FOR UNDERGROUND WORKS ITA WORKING GROUP N°5 7
>> Recommendations for Tendering >> Prompt for Risk Sources for Risk Assessments8
1.
Client organisations should assess the • Any schedule constraints of the client management culture within an organisation. • Ground conditions including contamination, • Fire risks, from natural gases, natural and
competence of design organisations requiring the need to select underground Therefore, it is in the interest of client groundwater conditions and inundation introduced materials, and plant
in addressing constructability in the construction activities to be performed in organisations that superior health and risks9 • Toxic or explosive gases
underground environment when selecting parallel safety risk management features of a tender • Exceptionally adverse weather • Hyperbaric working
professional advisers. It is recommended • Temporary ventilation during the construction are positively acknowledged during client
• Methods of working10 • Explosives
that only experienced underground design of shafts and underground working areas organisation assessments of the quality of
firms are used. • Ventilation, electrical and electro-mechanical tendering parties corporate experience and • Lighting conditions • Worksite layout and the potential for flooding
installations for construction, operation and tender submissions. • Occupational Noise • Access and egress to the construction or
2.
Client organisations should assess the maintenance stages • Environmental Noise worksite
competence of construction organisations • Personal Protective Equipment (PPE) 10.
Client organisations should consider the
• Vibration • Demolition12
in appropriately eliminating and effectively assessments and use of BIM7 and other digital technology
managing health and safety risks. Key areas • Incident and Emergency plans for fire and and processes as a means of identifying • Manual handling •
Incident and emergency management for
that should be requested in the Tender for other emergency scenarios in conjunction hazards, associated risks and their • Fatigue and shift patterns the activities
underground construction include provision with local emergency services and provide mitigation. • Heat/cold • Naturally occurring and combustion gases
of a Temporary Ventilation Management this information to tenderers. An objective of • Respirable crystalline silica
Plan and an Occupational Health and the reference design should be to establish 11.
Client organisations should require • Biological hazards
Hygiene Management Plan. A Ventilation that the scheme can be constructed and tenderers to provide health and safety • Ambient temperatures • Naturally occurring asbestos
Engineer and Occupational Hygienist maintained safely. assessments (reviews) to accompany • Natural and artificial ventilation • Diesel exhaust emissions
should be nominated by the constructor in their tenders. Client organisations should • Tunnel transport • Welding fumes and gases
the Tender schedules. 6. Client organisations should require tenderers require such assessments to include all • General dusts from excavation, spoil handling
to use the hierarchy of controls throughout risk sources (hazards) listed below as a •O
ffsite spoil transport, and the associated
hazards with heavy vehicle safety or generated through subsequent asset
3.
Client organisations should assess and their works planning and operations. This minimum. construction or maintenance processes,
evaluate the health and safety risks may preclude certain methods of working • Pedestrians in the tunnel
e.g., drilling, grinding or application of
associated with proposed assets prior that may be acceptable above ground and • Existing structures sprayed materials.
to releasing tender documentation may also require the use of specialised plant
• Unexploded Ordinance (UXO) • Use of chemicals, resins, grouts.
for construction, rehabilitation, or and engineering technologies to ensure that
maintenance. The principal objective of this certain risks are managed using higher- • Adjacent infrastructure including utilities11 •
The placement of concrete and concrete
evaluation should be the identification of order controls6. •
Electrical power installations and stored formwork
foreseeable risks throughout the lifecycle energy • UV radiation
of the assets against a defined level of 7.
Client organisations should incentivise • Mechanical and electrical equipment used, • Radon gas and Ionizing Radiation
acceptability in accordance with the risk innovation to improve health and safety including TBMs. Particular attention should
management framework established by risk management offered by the client • Radioactivity
be made to the assessment of the suitability
the client organisation under the general organisation reference design (scheme). of general construction plant to be used • Mental health and wellbeing
recommendations above. The client organisation reference design for underground working (both for static • Living conditions if projects require remote
provisions should be considered as installations and moving plant) worksites
4. In order to produce the evaluation, the health minimum requirements for compliance and
•
Concurrent worksite activities, especially • Shift patterns and travel to wor
and safety risks associated with alternative should be in full compliance with all relevant
walkways and moving plant risks • “Social” risks and discrimination
design options and alternative construction local laws, regulations and rules.
methodologies should be compared and • Underfoot conditions (‘slips, trips and falls’) • Are there any other foreseeable hazards and
evaluated. 8. Client organisations should allow adequate • Materials and material handling risks?
time for the interactive assessment and • Lifting and lowering operations
5. Client organisations should prepare comparative evaluation of the health and
• Working at heights
reference designs, requirements and risk safety risk management proposals by all
assessments for: tenderers prior to finalising construction and/
• Geotechnical conditions or operations or maintenance contracts.
• Construction methodologies and processes Note that not all risk sources will occur on a project and the list may not provide exhaustive list of risk sources
8
10
Are there alternative construction methods that can eliminate or reduce health and safety risks?
6
For example, the use of positive air pressurised, enclosed and sealed cabins for mined tunnelling to protect mined-tunnelling operators.
7
Building Information Model 11
Should underground utilities or underground structures be de-commissioned and removed or re-located or retained in-situ?
12
Demolition of existing buildings in urban areas is increasingly common and can add considerable complexity in terms of risk sources to health and safety planning.
Given the focus of tunnelling contractors on tunnelling risk management, it is recommended that such activities be undertaken by demolition specialist firms in
advance of the main tunnelling works.
8 PLANNING HEALTH AND SAFETY RISK MANAGEMENT FOR UNDERGROUND WORKS ITA WORKING GROUP N°5 9
>> References >> Notes
10 PLANNING HEALTH AND SAFETY RISK MANAGEMENT FOR UNDERGROUND WORKS ITA WORKING GROUP N°5 11
longrine 04 90 14 48 48 - (22024 - 09/20)
ITA Secretariat - c/o MIE2 – Chemin de Balexert 9 - CH-1219 Châtelaine (GE) - Switzerland
Tel. : + 41 22 547 74 41 - Email : secretariat@ita-aites.org - Web : www.ita-aites.org