Section One Quiz: Answer Key On Next Page
Section One Quiz: Answer Key On Next Page
4. The project management life cycle includes all of the following process groups except for which
one?
A. Initiating
B. Planning
C. Executing
D. Commanding
5. A project manager must be able to communicate with all levels of the organization. Which level of
a typical organization is responsible for managing the tactics and strategy?
A. Executives
B. Functional managers
C. Project managers
D. Operations
C. Projects are a temporary endeavor with a definite beginning and definite ending.
A, B, and D are incorrect. Projects don’t go on forever. Project costs might be sometimes difficult to
predict, but this isn’t the best answer. Projects don’t always create a product; they could also create a
condition, service, or some other result.
A. Projects can have just one person. Choices B, C, and D are incorrect as you only need one person,
technically, on a project.
D. MACD means that you are moving, adding, changing, or deleting something. Choices A, B, and C
aren’t correct as these statements don’t properly define MACD.
4. The project management life cycle includes all of the following process groups except for which
one?
A. Initiating
B. Planning
C. Executing
D. Commanding
D. The project management life cycle includes initiating, planning, executing, monitoring and controlling,
and closing. Commanding is not part of the project management life cycle. Choices A, B, and C are
incorrect because these choices are part of the project management life cycle.
5. A project manager must be able to communicate with all levels of the organization. Which level of
a typical organization is responsible for managing the tactics and strategy?
A. Executives
B. Functional managers
C. Project managers
D. Operations