You are on page 1of 2

DESING AND OPERATION OF CAVING AND SUBLEVEL STOPING MINES

3. Higher productivity than slusher drifts. that an actual decision involved a


compromise of costs and anticipated
4. Lower cost than gravity system. operating results.
5. Allows easier handling of larger boulders. UNDERCUT LEVEL
Disadvantages – Load – Haul – Dump Draw Decisions concerning layout, amount, and
System. direction of undercutting should be made
1. Larger openings that are susceptible to only after considering the available options.
caving if excessive ground weight develops. These factors are important, but this is one
of the most common areas in mine planning
2. Requires wider drawpoint spacing along Where the method selected is based on
draw drift. Therefore, it is more applicable to personal preference or the experience of the
coarse – breaking ore. mine planner. Study and analysis, however,
3. More experienced operating and should be undertaken, particularly since
maintenance personnel required. one’s experience may not have encompassed
the most economical approach.
Analysis of Draw Systems
Development
Capital estimates for the three systems
usually show that the gravity system is the Development of the undercut level usually
highest. A present value analysis of the starts at a special raise or off the top of
capital cost and operating savings can be drawpoints. From here drifts are advanced
performed, but the most important factor in over the top of other drawpoints until the
determining the draw system may be the ore block is sufficiently developed to allow the
extraction results that are anticipated. start of undercutting. This activity requires
decisions on elevation of undercut level, size
As noted earlier, draw control can be better of undercut drift, pattern of development,
administered with the gravity system since it and quantity of ore to be blasted in
lends itself to more positive control and undercutting.
better ore accountability. Also, a major
disadvantage of both the slusher and LHD Elevation of Undercut – The height of the
method is that of access if drifts take weight, undercut level above the base of the
cave, and restrict entry. The gravity system drawpoint varies from mine to mine, but in
can experience a great deal of squeezing – recent years the use of concrete support has
off of grizzly drifts and still remain productive allowed this interval to be held to a
as long as the worker can gain access to the minimum. A low-height interval gives
drawpoints. Obviously a larger opening is shorter, lower-cost draw raises and easier
required for the scraper to continue access to hangups, but these advantages are
operating and an even larger opening is often offset to some degree by the fact that
necessary for LHD units. Both scraper and it provides less support or solid ground over
LHD methods not only require access of the the back of the draw drift and the floor of
worker to drawpoints, but also necessitate the undercut drift is too thin, it will provide
movement of equipment (scraper and LHD little support and will erode and deteriorate
unit) to transport the ore. Clearly the choice as ore is drawn through the drawpoints.
of draw methods is not determined by costs The pros and cons of this design feature may
alone, and later in this report it will be shown be listed as follows:
Advantages of Short Draw Raises Size and Support of Undercut Drift – the size
and support of the undercut drifts are
influenced primarily by the strength of the
(ii) Easier access to hangups. ore on the undercut level. Ideally, minimum
support is desired in this area since it must
(iii) Shorter development time. all be removed when the draw commences,
(iv) Fewer hangups. Which allows better but in actual practice, some form of support
draw control. is necessary. Generally, support is a simple
wooden cap and post set or rock bolts used
Disadvantages of Short Draw Raises initially to support random slabs, but as
undercutting progresses and weight
(i) Higher drift maintenance cost.
develops, support is required, since spalling
(ii) Disruption of draw caused by caving of can be removed without the drift becoming
drifts. too oversized. Pillars are reduced in size
during undercutting and spalling may be
The development savings of shorter draw considered a part of pillar removal. Drilling
raises can be accurately calculated, but and blasting of the back of the undercut level
unfortunately the extra costs or savings of may be undertaken simultaneously with
the other factors noted above are difficult to pillar removal and the depth of this drilling
quantify. The disadvantages are dependent influenced by the caving action expected. If
to a great extent on the operational strong, competent rock is anticipated, caving
activities, and may be reduced to some can be aided by removing a thicker, caving
extent by correct undercutting and draw can be aided by removing a thicker, higher
procedures. Certainly the mine planner undercut. Caving can also be assisted by the
would not choose a low-level interval if it use of boundary weakening.
was likely to cause severe support problems
in the draw drift. The losses resulting from a Block sequence – A checkerboard or isolated
closed draw drift can be so high that any block layout of caving stopes was in favor at
design likely to allow this should be avoided. one time, but generally this practice has
If access to the drawpoints is restricted, given way to the panel or continuous
production will be lost, poor draw control sequence of design. The checkerboard
incurred, and support conditions allow, system claimed to provide more flexibility
raises should be held to a minimum since and quicker development, and also give
development savings alone can be better control by decentralizing operations.
significant, as indicated below. The fact that many blocks, particularly those
in the early stages of production, have four
In the example given earlier, draw raises
were necessary and a raise height of 5
meters’ vas assumed. However, if poor
ground conditions were encountered, then
perhaps 10 meter raises would be necessary.
This would mean an extra 420 meters of
raising at $400 permeter, or $160,000 in
increased development cost per block, and
assuming 180 blocks, the savings over the
mine’s life would be quite significant,
amounting to over $30 million.

You might also like