Procedure Ref : IP-OPS-066

JHA No.: Mech-05-20 Revision No:0 Area: xxxxxxxxxx Job Locations:


Rev.: A1 Date:24/09/2020
JOB HAZARD ANALYSIS Date: Dec. - 2014
Job Ref (Contract No.: xxxxxxxxxxxxxxxxxx Hazardous Area Classification: Zone 0☐, Zone 1☐,
PageZone 2󠇯☑󠇯, Non Hazardous☐
1 of 12
Job Description: Erection of scaffolding. Permit Type & No. :

Risk Rating Residual


S/ Activities (Job Action Party /
Potential Hazards Before Controls / Mitigation Measures Risk/
N steps) Remark
Mitigation Rating
 Ensure all personnel have valid CLIENT Approved H2S
Training and HSE Induction prior to enter into Site.
P= 3XC (M) P= 1XC(L)
 If H2S is detected, stop work. Inform authorities and
 H2S and other toxic A= 0XA (NA)) A= 0XA (NA) Site Supervisor,
1 Entry to site evacuate immediately.
gases E= 2XC (M) E= 1XC (L) PTW Holder.
 All personnel working in the site shall have H2S personal
R= 2XC(M) R= 1XC(L)
gas monitor/Toxic clips.
 Provide area Gas Monitor if required by PTW.
P= 3XC(M) P=1XC (L)
 Noise A= 0XA (NA) A=0XA (NA) Supervisor, PTW
 Wear Ear Plug/ Muff with all other mandatory PPE.
E= 0XA (NA) E=0XA (N/A) Holder.
R= 2XC(M) R=1XC (L)
 Provide proper access to the area.
P= 3XC (M)  In case of any emergency follow MIC Emergency P= 1XC (L)
A= 2XC(M) Procedures. A= 1XC (L) Site Supervisor,
 Emergency condition
E= 0XA (NA)  Each employee should be instructed about safe working E= 0XA (NA) PTW Holder.
R= 2XC(M) procedure/technique and emergency procedure and R= 1XC(L)
response, in case of emergency.
2 Mobilization and  Unauthorized P= 3XC (M)  The area identified, confirmed & cleared prior to entry into P= 1XC (L) Site Supervisor,
demobilization of commencement of work A= 0XA(NA) the work area. A= 0XA (NA) PTW Holder.
workers  Exposing people E= 0XA (NA)  All personnel shall be trained of all mandatory trainings. E= 0XA (NA)
potentially harm or R= 2XC (M)  Authorized work permit holders shall ensure obtaining and R= 1XC(L)
danger. maintaining of valid work permits and associated
certificate.
 Lack of safety  The supervisor responsible for this activity has to check
awareness the PPE and tools of his crew to ensure that all required
items are available and properly used.
 Inform all people regarding permit conditions before work
starts.
 Supervisors must conduct daily toolbox talk about nature
of work and associated potential hazards and its control
measures. Discuss possible emergency and response
procedure.
Procedure Ref : IP-OPS-066
JHA No.: Mech-05-20 Revision No:0 Area: xxxxxxxxxx Job Locations:
Rev.: A1 Date:24/09/2020
JOB HAZARD ANALYSIS Date: Dec. - 2014
Job Ref (Contract No.: xxxxxxxxxxxxxxxxxx Hazardous Area Classification: Zone 0☐, Zone 1☐,
PageZone 2󠇯☑󠇯, Non Hazardous☐
2 of 12
Job Description: Erection of scaffolding. Permit Type & No. :

 Comply with all general job requirements mentioned on


PTW.
 Wear all Mandatory PPE along with Earmuff and H2S
Personal Monitor.
P=2XC(M)  Maintain obstruction free access. P=1XC (L)
A=0XA (NA)  Beware of ankle breaker stones. A=0XA (NA) Supervisor, PTW
 Slip / Trip / Falls
E=0XA (NA)  Use only designated access. E=0XA (NA) Holder. .
R=2XC (M)  Maintain the cable/ hose management. R=1XC (L)
P=2XC(M)  Inspect the area before and during the activity for the P= 1XC(L)
A= 0XA (NA) presence of any snakes/Insects. A= 0XA (NA) Supervisor, PTW
 Snake/Insect bite.
E= 0XA (NA)  Don’t sit/Stand near Burrow. E= 0XA (NA) Holder.
R= 2XC(M)  Emergency standby vehicle to be provided at site. R= 1XC(L)
 Follow heat stress Management procedures.
 Don’t work alone and engage buddy working system.
 Cold drinking water to be provided.
P= 4XC(M) P= 1XC(L)
 Follow Flag system. Supervisor, PTW
 Heat stress/Heat stroke A= 0XA (NA) A= 0XA (NA)
 Work rest rotation to be followed. Holder.
and heat related Illness. E= 0XA (NA) E= 0XA (NA)
 Provide rest Shelter. Safety officer
R= 2XC(M) R= 1XC(L)
 Heat stress training to be provided to workforce.
 Heat stress Emergency awareness to be discussed
through TBT
3 Awareness of  Spread of coronavirus P=3xC (M) To protect yourself and Others DO the following, P=1xC (L) Panorama work
Coronavirus (COVID- E=0xA (NA) E=0xA (NA) crew
(COVID-19) infected prevention techniques and safety measures
19)
others people. A=0xA (NA)  Frequent hand washing with soap and water. A=0xA (NA) Panorama site
(pandemic) and
 The coronavirus R=3XC( M)  Any person entering a work site shall undergo a mandatory R= 1XC ( L) nurse/ doctor
prevention
techniques and (COVID-19) temperature and health check.
safety measures (pandemic) is a  When coughing and sneezing, cover mouth and nose with
respiratory virus which flexed elbow or tissue.
spreads through droplets  Dispose-off the tissue with responsibility in a trash bin and
generated when an immediately wash your hands.
infected person coughs
 Wear a mask to limit the respiratory droplets.
or sneezes, or through
 Avoid touching your eyes, nose and mouth.
droplets of saliva or
discharge from the nose  Maintain a clean environment & sanitize surfaces.
and close contact  Keep distances and avoid close contact to a
 Infected by Corona virus minimum (Maintaining 2-meter social distancing).
(COVID-19)  Hand washing facilities or hand sanitizer dispensers shall
 Spread of infection to be in place at entrances to every site, office, and toilet.
others  Any person entering a work site shall undergo a mandatory
temperature and health check.
Procedure Ref : IP-OPS-066
JHA No.: Mech-05-20 Revision No:0 Area: xxxxxxxxxx Job Locations:
Rev.: A1 Date:24/09/2020
JOB HAZARD ANALYSIS Date: Dec. - 2014
Job Ref (Contract No.: xxxxxxxxxxxxxxxxxx Hazardous Area Classification: Zone 0☐, Zone 1☐,
PageZone 2󠇯☑󠇯, Non Hazardous☐
3 of 12
Job Description: Erection of scaffolding. Permit Type & No. :

 Anyone with flu-like symptoms or a body temperature >


37.8 degrees Celsius shall not be permitted on site.
 Signs shall be erected at the site entrance with mandatory
COVID-19 access controls in place.

People Not Allowed to Work

 Anyone who falls under the conditions outlined below shall


not report to work:
 1. Having a body temperature >37.8oC, and/or a persistent
cough, sore throat, shortness of breath, difficulty breathing,
and joint pain or any flu-like symptoms.
 2. Has an underlying health or medical condition (e.g.
chronic respiratory illness, asthma, emphysema, cancer,
compromised immunity) that makes them vulnerable in
case of infection.
 3. Is in close contact or living with someone undergoing
self-isolation or a vulnerable person as outlined in category
2 above.
 Anyone who falls under any of the above categories must
remain in self-isolation at home and be instructed to
immediately report to his/her supervisor if they experience
any flu-like symptoms (e.g. fever, cough, muscle pain, sore
throat). If such symptoms develop, the supervisor shall
then contact the Communicable Disease Center (CDC) on
16000 for further guidance and notify the CLIENT Contract
Representative

Erection of  slip, trip and falls P= 3XB (M)  Mandatory and additional PPE must be worn. P= 1XB (L) PTW Supervisor
scaffolding A= 0XA (NA)  Area must be barricaded and signs must be posted. A= 0XA (NA) & Safety
4 E= 0XA (NA) E= 0XA (NA) Officer/scaffolders
 Proper housekeeping in work area.
R= 3XB (M)  Proper working platform while working at height R= 1XB(L)
 Spark generation /Fire P= 3XB (M)  Verify the work area is gas free. P= 1XB (L) PTW Supervisor
A= 3XB (M)  Use non sparking tools in hazardous location A= 1XB (L) & Safety Officer
E= 0XA (NA)  Check the work area is freed from harmful of flammable E= 0XA (NA)
R= 3XB (M) gases with continues monitoring. R= 1XB(L)
 Sharp object P= 3XB (M)  Wear hand protection P= 1XB (L) PTW Supervisor
A= 0XA (NA)  Remove sharp edges. A= 0XA (NA) & Safety Officer
E= 0XA (NA)  Safety signage describing the hazards should be present. E= 0XA (NA)
R= 3XB (M) R= 1XB(L)
Procedure Ref : IP-OPS-066
JHA No.: Mech-05-20 Revision No:0 Area: xxxxxxxxxx Job Locations:
Rev.: A1 Date:24/09/2020
JOB HAZARD ANALYSIS Date: Dec. - 2014
Job Ref (Contract No.: xxxxxxxxxxxxxxxxxx Hazardous Area Classification: Zone 0☐, Zone 1☐,
PageZone 2󠇯☑󠇯, Non Hazardous☐
4 of 12
Job Description: Erection of scaffolding. Permit Type & No. :

 Untrained Personnel. P= 3XB (M)  Use certified scaffolders. P= 1XB (L) PTW Supervisor
A= 3XB (M)  Adequate Supervision A= 1XB (L) & Safety Officer
E= 0XA (NA) E= 0XA (NA)
R= 3XB (M) R= 1XB(L)
 falls from height, P= 3XB (M)  Use fall protection equipment. P= 1XB (L) PTW Supervisor
A= 0XA (NA)  All safety equipment must be inspected. A= 0XA (NA) & Safety
E= 0XA (NA)  Only certified Scaffolder will be allowed to work. E= 0XA (NA) Officer/scaffolders
R= 3XB (M)  Use safety harness with double lanyard when working at R=1XB(L)
height.
 Ensure safety harness to have 3rd party certificates with
BCP stamp.
 Other parties working in the area will be notified and
advised to leave the area.
 Adequate barricading with appropriate safety signage will
be installed.
 Maintain 3point contact of all time while ascending and
descending ladder.
 Be aware of slippery surfaces. .
 Ensure use of safety harness with 100% tie off.
 Use third party certified and BCP approved Safety
Harness

 Falling object P= 3XB (M)  Work area must be properly barricaded and restricted. P= 1XB (L) PTW Supervisor
A= 0XA (NA)  Adequate Supervision A= 0XA (NA) & Safety
E= 0XA (NA)  Ensure proper lowering of components using approved E= 0XA (NA) Officer/scaffolders
R= 3XB (M) method, approved scaffolding lifting bag• R= 1XB(L)
 Cordon off area • Store loose materials (ties, clamps and
etc.) in sacks or bag.
 All openings in the platform to be adequately covered.
 Barricade the area and provide safety signage.
 Limited access to be done
 Don’t drop the materials use Approved Scaffolding
material’s bag
 Secure all tools and materials at all times
 Do not throw the ,secure all the hand tools using lanyard,
barricades the area with display of sign boards
5 Manual loading and  Improper handling of P= 3XB (M)  Appropriate Supervision. P= 1XB (L) PTW Supervisor
unloading works material. A= 0XA (NA)  Access from the storage to the Loading/offloading site A= 0XA (NA) & Safety
E= 0XA (NA) must be clear. E= 0XA (NA)
R= 3XB (M) R= 1XB (L)
Procedure Ref : IP-OPS-066
JHA No.: Mech-05-20 Revision No:0 Area: xxxxxxxxxx Job Locations:
Rev.: A1 Date:24/09/2020
JOB HAZARD ANALYSIS Date: Dec. - 2014
Job Ref (Contract No.: xxxxxxxxxxxxxxxxxx Hazardous Area Classification: Zone 0☐, Zone 1☐,
PageZone 2󠇯☑󠇯, Non Hazardous☐
5 of 12
Job Description: Erection of scaffolding. Permit Type & No. :

 Skilled manpower to shift the load. Officer/scaffolders


 Proper procedure to be adopted during manual lifting.
 Sufficient break to rest.
 Use proper PPE
 Materials stored on site will be limited to those that are
necessary for the current work.
P= 3XB (M)  Keep walk ways always clear of obstruction; Regular P= 2XB (L) PTW Supervisor
 Heavier loads A= 0XA (NA) clearing of work site shall be implemented. A= 0XA (NA) & Safety
E= 0XA (NA)  Ensure load to be manually lifted does not cross 25 KGs. E= 0XA (NA) Officer/scaffolders
R=3XB (M) For heavier loads, use mechanical means. R= 1XB(L)
 slip, trip and falls P= 3XB (M)  Suitable means of access. P= 1XB (L) PTW Supervisor
A= 0XA (NA)  Good housekeeping and PPE’s must be worn (hand A= 0XA (NA) & Safety Officer
E= 0XA (NA) gloves). E= 0XA (NA)
R= 3XB (M)  Provide sufficient access and working platform R= 1XB(L)
 Platform shall be inspected and green tagged, same
applies for access ladders.
 Watch & be cautious for slippery wet surfaces
 Area must be barricaded and signs must be posted.
 Lifting of excess load. P= 3XB (M)  Skilled manpower to lift /shift the load. P= 1XB (L) PTW Supervisor
 Back strains A= 0XA (NA)  Proper procedure to be adopted during manual lifting. A= 0XA (NA) & Safety Officer
E= 0XA (NA)  Sufficient break to rest. E= 0XA (NA)
R= 3XB (M)  Use proper PPE R= 1XB(L)
 Reduce the amount of twisting , stooping and reaching
 Avoid lifting from floor level or above shoulder height,
especially heavy loads
 Adjust storage areas to minimize the need to carry out
such movements
 Consider how you can minimize carrying distances
 Assess the weight to be carried and whether the worker
can move the load safely or needs any help – maybe the
load can be broken down to smaller, lighter components
P= 3XB (M)  Wear hand protection P= 1XB (L) PTW Supervisor
A= 0XA (NA)  Remove sharp edges. A= 0XA (NA) & Safety Officer
 Sharp Objects E= 0XA (NA)  Safety signage describing the hazards should be present. E= 0XA (NA)
R= 3XB (M) R= 1XB(L)
Using of hand tools  Risk of injury due to use P= 3XB (M)  Make sure you are using the correct tool for the task at P= 1XB (L) PTW Supervisor
of improper and A= 0XA (NA) hand. A= 0XA (NA) & Safety Officer
6
/defective hand tools
Procedure Ref : IP-OPS-066
JHA No.: Mech-05-20 Revision No:0 Area: xxxxxxxxxx Job Locations:
Rev.: A1 Date:24/09/2020
JOB HAZARD ANALYSIS Date: Dec. - 2014
Job Ref (Contract No.: xxxxxxxxxxxxxxxxxx Hazardous Area Classification: Zone 0☐, Zone 1☐,
PageZone 2󠇯☑󠇯, Non Hazardous☐
6 of 12
Job Description: Erection of scaffolding. Permit Type & No. :

E= 0XA (NA)  Never use a damaged or defective hand or power tool. E= 0XA (NA)
R= 3XB (M)  Tools are not toys. Never throw or toss a tool in the R= 1XB (L)
direction of or directly to a coworker.
 All operatives shall be trained for proper handling of tools
 Appropriate tools only have to be used and its
requirements.
 Inspect the tools .Don’t use defective tools .Defective
tools must be remove from the site to avoid the usage of
defective tools which may cause of incident.
 All operatives shall wear their PPEs without fail.
 Poor ergonomics P= 3XB (M)  Good posture is about more than finding a comfortable P= 1XB (L) PTW Supervisor
A= 0XA (NA) position to work in, or what “feels right.” Especially when A= 0XA (NA) & Safety
E= 0XA (NA) you consider that some positions, while comfortable for E= 0XA (NA) Officer/All
R= 3XB (M) the worker, may not be ergonomically correct. R= 1XB (L)
 Change it Up
 Repeating the same movement continuously through the
day can cause strains. If it is possible to alternate tasks, it
is advisable to do so. If job rotation or alternating tasks
throughout the shift is unrealistic.
 Be sure to incorporate several rest breaks. Stretch during
breaks, or do simple exercises to keep your muscles and
tendons from becoming tense or strained.
 Be sure that if your job involves manual lifting, that you
are trained in manual material handling, and that you
practice proper lifting techniques. Never lift with the
muscles in your back. Lift with your knees.
 Risk of striking hand P= 3XB (M)  Ensure other personnel are well clear. P= 1XB (L) PTW Supervisor
A= 0XA (NA)  Make sure you are using the correct tool for the task at A= 0XA (NA) & Safety
E= 0XA (NA) hand E= 0XA (NA) Officer/scaffolders
R= 3XB (M)  Beware of sharp edges on tools R= 1XB (L)
 The right tool for the job should always be used to
decrease the chances of injury, incidents, or damage to a
tool through improper use
 Risk of striking others P= 3XB (M)  Never use a damaged or defective hand or power tool P= 1XB (L) PTW /Supervisor
A= 0XA (NA)  Keep only required persons at site. A= 0XA (NA) & /scaffolders
E= 0XA (NA)  All tools shall be kept clean for easy use. E= 0XA (NA)
R= 3XB (M)  Ensure other personnel are well clear. R= 1XB (L)
 Proper communication each other.
Procedure Ref : IP-OPS-066
JHA No.: Mech-05-20 Revision No:0 Area: xxxxxxxxxx Job Locations:
Rev.: A1 Date:24/09/2020
JOB HAZARD ANALYSIS Date: Dec. - 2014
Job Ref (Contract No.: xxxxxxxxxxxxxxxxxx Hazardous Area Classification: Zone 0☐, Zone 1☐,
PageZone 2󠇯☑󠇯, Non Hazardous☐
7 of 12
Job Description: Erection of scaffolding. Permit Type & No. :

 Make sure you are using the correct tool for the task at
hand.
 Tools are not toys. Never throw or toss a tool in the
direction of or directly to a coworker.
 Sharp Objects P= 3XB (M)  Wear hand protection P= 1XB (L) PTW Supervisor
A= 0XA (NA)  Remove sharp edges. A= 0XA (NA) & Safety Officer
E= 0XA (NA)  Safety signage describing the hazards should be present. E= 0XA (NA)
R= 3XB (M) R= 1XB (L)

 slip, trip and falls P= 3XB (M)  Suitable means of access. P= 1XB (L) PTW Supervisor
A= 0XA (NA)  Good housekeeping and PPE’s must be worn (hand A= 0XA (NA) & Safety Officer
E= 0XA (NA) gloves). E= 0XA (NA)
R= 3XB (M)  Provide sufficient access and working platform R= 1XB (L)
 Platform shall be inspected and green tagged, same
applies for access ladders.
 Watch & be cautious for slippery wet surfaces
 Area must be barricaded and signs must be posted.
 Pinch point P=3xB (M)  TBT to be conducted and close supervision to by carried P= 1XB (L) PTW Supervisor
A=0xA (NA) out. A= 0XA (NA) & Safety Officer
E=0xA (NA)  Hand gloves to be used. E= 0XA (NA)
R=3xB (L)  Safety signage describing the hazards should be present. R= 1XB (L)
 Damaged hand tools P=3xB (M)  Ensure that equipment and accessories are of P=1xB (L) PTW Supervisor
A=2xA (NA) appropriate standard & correct specifications A=1xA (L) & Safety Officer
E=0xB (NA)  Never use a damaged or defective hand tool E=0xB (NA)
R=3xB (L  The damaged Hand tools must be reported and R=1xB (L
immediately return to store.

7 Damage scaffolding P= 3XB (M)  Take extreme care during erection of scaffolding for P= 1XB (L) PTW Supervisor
materials A= 0XA (NA) damaged /defective scaffolding materials. A= 0XA (NA) & Safety Officer
E= 0XA (NA)  Regularly checking of scaffolding materials for any E= 0XA (NA)
 Fall of personnel R= 3XB (M) R= 1XB (L)
damage
 Provide guardrail & toe board to prevent falling of tools
/objects/personnel
 The damaged scaffolding materials must be reported and
immediately replace with good materials by the certified
scaffolding crew with PTW.
 Risk of collapse of P= 3XB (M) P= 1XB (L) PTW Supervisor
scaffolding/working A= 0XA (NA)  Area check for scaffolding .Excavation shall not allowed A= 0XA (NA) & Safety Officer
platform E= 0XA (NA) near scaffolding Area E= 0XA (NA)
Procedure Ref : IP-OPS-066
JHA No.: Mech-05-20 Revision No:0 Area: xxxxxxxxxx Job Locations:
Rev.: A1 Date:24/09/2020
JOB HAZARD ANALYSIS Date: Dec. - 2014
Job Ref (Contract No.: xxxxxxxxxxxxxxxxxx Hazardous Area Classification: Zone 0☐, Zone 1☐,
PageZone 2󠇯☑󠇯, Non Hazardous☐
8 of 12
Job Description: Erection of scaffolding. Permit Type & No. :

R= 3XB (M)  Don’t over load platform. R= 1XB (L)


 Provide correct base plats
 Risk of persons falling P= 3XB (M)  Take extreme care during erection of scaffolding for P= 1XB (L) PTW Supervisor
A= 0XA (NA) damaged /defective scaffolding materials. A= 0XA (NA) & Safety Officer
E= 0XA (NA)  Regularly checking of scaffolding Materials for any E= 0XA (NA)
R= 3XB (M) damage R= 1XB (L)
 Provide guardrail & toe board to prevent falling of tools
/objects
 The damaged scaffolding materials must be Report and
immediately replace with good materials by the certified
scaffolding crew with PTW.
8 Working in Extreme  Rain P= 3XB (M)  Follow CLIENT procedure, rules and regulation during rain. P= 1XB (L) PTW Supervisor
Weather/Heat A= 0XA (NA)  During heavy rain and windy weather condition all work A= 0XA (NA) & Safety Officer
Stress E= 0XA (NA) shall be stopped. E= 0XA (NA)
R= 3XB (M)  Be aware of slippery surface R= 1XB (L)
 Strong winds P= 3XB (M)  Follow CLIENT procedure, rules and regulation during P= 1XB (L) PTW Supervisor
A= 0XA (NA) strong wind. A= 0XA (NA) & Safety Officer
E= 0XA (NA)  Working at height OR lifting not allowed in high wind as per E= 0XA (NA)
R= 3XB (M) CLIENT procedure. R= 1XB (L)
 Conduct TBT prior start the job.
 During heavy rain and windy weather condition all work
shall be stopped.
 Heat Stress P= 3XB (M)  Follow CLIENT heat stress procedure, rules and regulation P= 1XB (L) PTW Supervisor
A= 0XA (NA) and summer timing A= 0XA (NA) & Safety Officer
E= 0XA (NA)  Follow CLIENT Heat Stress management procedure. E= 0XA (NA)
R= 3XB (M)  Summer timings to be followed strictly by all crews. R= 1XB (L)
 Conduct TBT prior start the job.
 All personnel must carry water Flask with full water.
 Ensure enough cool water at site is provided.
 All workers must have the Heat Stress Awareness training
prior mobilize to site.
 Follow flag color, work rest cycle and drinking water
protocols.
 Never work alone
P=2XC(M)  Ensure all equipment / materials removed from area. P=1XC (L) PTW Supervisor
Housekeeping. A=0XA (NA)  Clear the area of any slip, trip or fall hazards. A=0XA (NA) & Safety Officer
9 Slip, trip and falls
Post activity checks, E=0XA (NA)  All equipment’s and tools removed on completion of job. E=0XA (NA)
R=2XC (M)  Be cautious for the wet slippery surface. R=1XC (L)
Procedure Ref : IP-OPS-066
JHA No.: Mech-05-20 Revision No:0 Area: xxxxxxxxxx Job Locations:
Rev.: A1 Date:24/09/2020
JOB HAZARD ANALYSIS Date: Dec. - 2014
Job Ref (Contract No.: xxxxxxxxxxxxxxxxxx Hazardous Area Classification: Zone 0☐, Zone 1☐,
PageZone 2󠇯☑󠇯, Non Hazardous☐
9 of 12
Job Description: Erection of scaffolding. Permit Type & No. :

 Regular housekeeping at site shall be performed;


 Keep walk ways always clear of obstruction
P=2XC(M)  Use Proper PPE for the task. Use dust mask/face mask. P=1XC (L)
A=0XA (NA) A=0XA (NA) Supervisor, PTW
Dust
E=0XA (NA) E=0XA (NA) Holder.
R=2XC (M) R=1XC (L)
 Wear heavy duty gloves for the task.
P=2XC(M) P=1XC (L)
 Keep the body parts away from sharp edges.
A=0XA (NA) A=0XA (NA) Supervisor, PTW
 Sharp Edges Protect the sharp edges with some sort of means if
E=0XA (NA) E=0XA (NA) Holder.
R=2XC (M) possible. R=1XC (L)
P= 3XB (M) P= 2XB (L)
 Fire Risk due to
presence of combustible
A= 3XB (M)  Remove flammable material and chemical every end of A= 2XB (L) PTW Supervisor
E= 0XA (NA) the shift as per CLIENT procedure E= 0XA (NA) & Safety Officer
material
R= 3XB (M) R= 1XB(L)
 All waste to be disposed at CLIENT approved waste
P=2XC(M) management center. P=1XC (L)
 Wrong disposal area
A=0XA (NA)  All waste to be segregated as per CLIENT Regulation A=0XA (NA) Supervisor, PTW
10 Waste management  Improper collection of
E=2XC (M) before disposal. E=1XC (L) Holder.
Wastes R=2XC (M)  All waste materials shall be removed end of the shift/ day. R=1XC (L)

P= 3XB (M)  All waste to be disposed-off as per CLIENT waste P= 2XB (L)
 Waste Material A= 0XA (NA) management procedure. A= 0XA (NA) Supervisor, PTW
Generation E= 3XB (M) E= 2XB (L) Holder.
R= 3XB (M) R= 1XB(L)
P= 3XB (M)  Wear heavy duty gloves for the task. P= 1XB (L)
A= 0XA (NA)  Keep the body parts away from sharp edges. A= 0XA (NA) Supervisor, PTW
 Sharp Object
E= 0XA (NA)  Protect the sharp edges with some sort of means if E= 0XA (NA) Holder.
R= 3XB (M) possible. R= 1XB(L)
 Ensure all equipment / materials removed from area.
 Clear the area of any slip, trip or fall hazards.
P= 3XB (M) P= 1XB (L)
 All equipment’s and tools removed on completion of job.
 Slip, trip and falls A= 0XA (NA) A= 0XA (NA) Supervisor, PTW
 Be cautious for the wet slippery surface.
E= 0XA (NA) E= 0XA (NA) Holder.
R= 3XB (M)  Regular housekeeping at site shall be performed. R= 1XB(L)
 Keep walk ways always clear of obstruction

11 Emergency  Lack of awareness P=3xB (M)  Conduct TBT prior start the job. P=1xB (L) PTW Supervisor
Preparedness during emergency E=0xA (NA)  Ensure supervisor will communicate to all workers how to E=0xA NA) & Safety Officer
situation A=0xB (L) response during emergency and it should understand by A=0xB (L) and all
R=2xB (L R=1xB (L)
Procedure Ref : IP-OPS-066
JHA No.: Mech-05-20 Revision No:0 Area: xxxxxxxxxx Job Locations:
Rev.: A1 Date:24/09/2020
JOB HAZARD ANALYSIS Date: Dec. - 2014
Job Ref (Contract No.: xxxxxxxxxxxxxxxxxx Hazardous Area Classification: Zone 0☐, Zone 1☐,
PageZone
10 of 2󠇯☑󠇯, Non Hazardous☐
12
Job Description: Erection of scaffolding. Permit Type & No. :

all workers. All workers must to know what they should to


do in case of emergency.
 In case of emergency stop all work, identify / verify alarm if
Toxic Gas released, immediately safely move to the safest
& nearest Assembly Point considering the wind direction &
evacuate crosswind.
 Follow CLIENT emergency response procedure.

TEAM MEMBERS & ENDORSEMENT


Position / Ref Position / Ref Sign
S/N Name Sign S/N Name
Indicator Indicator
1 Nasrullah Jan HSE Coordinator 4
2 5
3 6
JHA Team Leader Authorization: Ref Indicator: Sign :

JHA Approval (Permit Authority / Asset Holder): Ref Indicator: Sign :