Department: Engineering Section: Maintenance Activity : Changing Light Bulb using Ladder Date : 10.2.2017
WORK ACTIVITY HAZARDS EFFECT EXISTING CONTROL RISK ASSESSMENT RISK CONTROL
STEP NO.
1-4 5-12 15-25
Nature of Risk Control (Describe) L S Recommended Risk Control PIC/STATUS/DUE DATE
Low Medium High
Climbing up the ladder Fall from height Broken bones Maintain a 3-point contact
while carrying equipment Buddy system 2 2 4
1 Falling object Head injury Safety awareness briefing Maintain current practice NIL
Safe work area boundary
2 2 4
Safety awareness briefing
Changing light bulb Electric shock Minor burns Safety awareness briefing
Provide PPE (cotton glove & safety shoes)
2 2 4