KE01-00-000-AK-A-PR-0676-000
REVISION A01
NOVEMBER 2004
ABSTRACT
This document defines how Suppliers shall identify, format and submit
documentation for Company review.
The copyright of this document is vested in Agip KCO NV, The Hague. All rights reserved. Neither the whole nor any part of this document may be reproduced,
stored in any retrieval system or transmitted in any form or by any means (electronic, mechanical, reprographic, recording or otherwise) without the prior
consent of the copyright owner,
Agip KCO KE01-00-000-AK-A-PR-0676-000
Rev. A01– November 2004
Page 2 of 22
Document Verification
RACIE Record
Signed:
Date:
Signed:
Date:
Signed:
Date:
RACIE Terms
Responsible
R
The person who actually does the work and/or produces the document.
Accountable
A
The person who has to answer for success or failure of the work and/or the quality and timeliness of the document.
Consulted
C
Those who must be consulted during the work and/or before the document is published..
Informed
I
Those who must be informed in order to do the job and/or produce the document.
Endorsed
E
Those who must approve the work completion and/or document before publication.
Hold Record
Mark Page Number
<HOLD>
Document Distribution
Date Copies No. Site Addressee / Position Holder Company
/Format
AKCO
5 Nov 04 ELEC LDN B. Surendran
AKCO
5 Nov 04 ELEC LDN B. Dunsmore
AKCO
5 Nov 04 ELEC LDN B. Twist
AKCO
5 Nov 04 ELEC LDN D. Sen
AKCO
5 Nov 04 ELEC LDN G. Gundy
AKCO
5 Nov 04 ELEC LDN M. Hellman
AKCO
5 Nov 04 ELEC LDN N. Grant
AKCO
5 Nov 04 ELEC LDN R. Barnett
AKCO
5 Nov 04 ELEC LDN R. Houston
AKCO
5 Nov 04 ELEC LDN R. Taylor
AKCO
5 Nov 04 ELEC LDN T. Jarvis
AKCO
5 Nov 04 ELEC LDN IMIS Coordinators
AKCO
5 Nov 04 ELEC LDN Package Managers
AKCO
5 Nov 04 ELEC LDN AGIPKCO Contracts and Procurement
Total
TABLE OF CONTENTS
1 INTRODUCTION 6
1.1 SCOPE 6
1.2 DISTRIBUTION, INTENDED USE AND REGULATORY CONSIDERATIONS 6
1.3 DEFINITIONS 6
1.3.1 General definitions 6
1.3.2 Specific definitions 7
1.4 ABBREVIATIONS 7
1.5 CROSS REFERENCES 7
2. ROLES AND RESPONSIBILITIES 7
3. DOCUMENTATION REQUIREMENTS 8
3.1 SUPPLIER DOCUMENTS REQUIREMENTS SCHEDULE (SDRS) 8
3.2 SUPPLIER DOCUMENT INDEX (SDI) 8
4. DOCUMENT FORMATS / IDENTIFICATION OF DOCUMENTS 9
4.1 DOCUMENT NUMBERING 9
4.2 SUPPLIER DOCUMENT DECALS/SUPPLIER DOCUMENT A4 COVER SHEETS 11
4.3 QUALITY OF DOCUMENTS 11
4.4 TRANSLATION REQUIREMENTS 11
4.5 OTHER PROFORMAS TO BE USED 12
5. METHOD OF SUBMISSION FOR COMPANY REVIEW 12
5.1 ELECTRONIC FORMATS 12
5.2 ELECTRONIC FILE NAMING CONVENTION 12
6. COMPANY REVIEW / SUPPLIER RESUBMISSION 13
6.1 RETURN CODES 13
6.2 TIME ALLOWED FOR COMPANY REVIEW 13
6.3 METHOD OF RETURN TO SUPPLIER 13
6.4 SUPPLIER RESUBMISSION 13
7. TECHNICAL OPERATING AND MAINTENANCE MANUAL (TOM) AND EQUIPMENT /
MATERIAL PASSPORT 14
7.1 TOM MANUAL (SDRS CODE N01) 14
7.1.1 Format and content 14
7.1.2 Hard copies required / translation requirements 14
7.1.3 Electronic copy of TOM (SDRS Code N10) 14
7.1.4 Submission instructions 14
7.2 EQUIPMENT / MATERIAL PASSPORT (SDRS CODE M01) 14
7.2.1 Format and Content 14
7.2.2 Hard copies required / translation requirements 14
7.2.3 Electronic copy of Equipment / Material Passport (SDRS Code M03) 15
7.2.4 Submission instructions 15
7.3 PRESENTATION OF MANUALS 15
7.3.1 Binders 15
7.3.2 Supplier Document A4/A3 Cover Sheet 15
7.3.3 Supplier’s Title page 15
7.3.4 Indexing and page numbering 16
7.3.5 Insertion of drawings and documents 16
8. FINAL ELECTRONIC HANDOVER (SDRS CODE N11) 16
ANNEX A – TYPICAL SUPPLIER DOCUMENT REQUIREMENTS SCHEDULE (SDRS) 18
1 INTRODUCTION
This procedure defines how Suppliers shall identify, format and submit documentation for
Company review.
This document does not cover how Suppliers shall submit data or operations and
maintenance information. This is contained in Contractor Data Requirements Definition
KE01-00-000-AK-Y-LS-0001-000.
This document supersedes KE01.00.000.KD.Z.PR.0004.000 Supplier Documentation
Instructions. Additions or changes to information from the last document have been
highlighted, however changes to numbering have not.
1.1 SCOPE
This procedure applies for all documentation required from Suppliers in the execution of an
Enquiry Requisition and subsequently the Purchase Requisition.
The standards of presentation and quality defined herein apply to all submissions /
resubmissions of Supplier documents.
Where this procedure accompanies an Enquiry package, the term “Supplier” shall mean
“Bidder”.
This document is the property of COMPANY. Permission is required to share this with any
other party other than internal to the target party to whom it is originally distributed.
This document is prepared and owned by the IMIS Group on the Kashagan Project.
All discussion and interpretation of this document is to be coordinated through the IMIS
group located in Brentford London or through their COMPANY representative.
1.3 DEFINITIONS
1.4 ABBREVIATIONS
3. DOCUMENTATION REQUIREMENTS
Supplier shall utilise Company supplied SDI proforma (for typical example refer Annex B).
The SDI shall be submitted 2 weeks after Purchase Order in electronic format (Microsoft
Excel or comma separated values .csv format).
The purpose of the SDI is to provide an agreed list of all the individual documents that
Supplier shall submit in connection of the Purchase Order. The SDI shall list all documents
and ancillary information in the format shown in Annex B. Once agreed the SDI effectively
replaces the SDRS. The SDI in itself is not used to record the status of documents, but to
provide the basic information for loading into Company’s document control systems which
are used to record receipt of documents and to report document status.
Each document submission (see section 5.1) shall be accompanied by file containing the
equivalent SDI details for loading into Company’s document control systems.
The following is a brief description of the SDI columns and their use:
Contract No. The Contract number allocated by Company to the requisition
Transmittal Number Supplier Transmittal number
Purchase Order No. The Purchase Order number allocated by Company to the
requisition
Project Document No. The document number allocated by Supplier in accordance with
section 4.1.2
Document Revision The document revision allocated by Supplier in accordance with
section 4.1.4. Only required when this index is submitted with
documents. See section 5.1
Supplier Document No. The Supplier’s own unique document number. See section
4.1.1
Supplier Document The Supplier’s own revision number. Only required when this
Revision index is submitted with documents. See section 5.1
Document Title The title as it appears on the document
Discipline The discipline code identified as part of the Project Document
th
No. This is the 4 character in the Purchase Order number
inserted in the Project document number. In the example shown
in section 4.1.2 this would be E.
Submission Date The actual date of submission of the document. Only required
when this index is submitted with documents. See section 5.1
SDRS Code The SDR code allocated as part of the Project Document No.
See section 4.1.2.
Supplier Name The Supplier company name
Critical Document As identified on Company SDRS column 5. Should be Y or N
Equipment Passport As identified on Company SDRS column 6. Should be Y or N
TOM Manual As identified on Company SDRS column 7. Should be Y or N
Expected date The expected date for document submission
Translation Required As identified on Company SDRS column 8. Should be Y or N
Language Code This will identify the language of the document being submitted.
E=English, R=Russian, DL=Dual Language, ET= Explanatory
Translation. Only required when this index is submitted with
documents. See section 5.1
Expected Date The expected date for document submission.
Final Native File Format This column will be completed by Company to identify
Required documents required finally in native file format.
The SDI shall be considered to be a “live” document for the duration of the Purchase Order
and even when it has achieved Return Code F (refer section 6.1) it should be submitted
periodically (every 8 weeks) to identify any significant changes to the list of documents.
Supplier is responsible for assigning document numbers to each document submitted. The
document numbers to be assigned shall be identified on the SDI. For each document there
will be 2 separate document numbers:
A A N N - A N- A A A A N N A - A N N - N N N N-N N N
(vi) Sheet Nr
KASH-AA01-PKDE01A
The underlined component PKDE01A is the PO Number structure that is used within the
Supplier document number.
Note 3: SDRS Code as per the Supplier Data Requirements Schedule (SDRS) included in
the Purchase Order.
Note 4: A sequential number from 0001 to 9999, starting with 0001 for each SDRS Code.
Note 5: For documents, the Sheet Number shall be 000. Assignment of Sheet Numbers to
drawings is explained in 4.1.3.
Once a document has been listed on the SDI the Project document number shall not be re-
used if the document is superseded or issued void. If a document is superseded or issued
void then this shall be clearly indicated in the title space on the SDI.
4.1.5 Revision / Submission Indicators
In connection with the Supplier Document number defined above in section 4.1.1, Supplier
can use his own revision system to identify different issues of documents.
In connection with the Project Document number section 4.1.2 above, the Supplier shall
identify the submission of each issue of each document. Document submissions shall be
identified by Supplier on the Company supplied Decal or A4 Cover Sheet. The first
submission of each document is submission “01”, the second is “02”, the third “03” and so
on.
Supplier shall ensure each document carries either a Company Supplier Document Decal
(Refer Annex C) or a Company Supplier Document A4/A3 Cover Sheet (refer Annex D).
Company will provide both these items for Supplier to use. The decal is to be used for all
drawings A2 or A1 size. The Cover sheet is to be used for A4 documents.
Supplier may use either the Decal or the Cover sheet for A3 size drawings or documents.
Usually single A3 drawings should carry a Decal whereas multisheet A3 schedules should
be prefaced with the A4/A3 Cover Sheet see Section 4.1.3 above. Annexes C & D identify
the information that must be completed by Supplier on each and every submission. As the
primary method of submission (refer section 5.1) is electronic, it is essential that the decal or
A4 Cover sheet must be included in each and every electronic file submitted by Supplier.
Supplier shall utilise the standard ISO sizes for documents and drawings ie A4, A3, A2 and
A1. Supplier shall not use A0 size drawings without Company’s prior permission.
All documents shall be fully legible in either hard copy or electronic format. Company shall
receive all documents as electronic files for printing and circulation in house. It is essential
that all electronic files received can be printed into a legible format without the need for
Company to make adjustments.
All documents shall be supplied in the English language. The documents required to be
translated into Russian are identified in the SDRS. This requirement is transferred onto the
SDI so that each individual document required to be translated is identified. The Russian
translation is only required of the final English version accepted Code F. It is not required
during the review cycle.
Supplier is responsible for ensuring that the Russian version is accurate in terms of
translation and that the translation is of the correct Code F version. Where possible, the
Russian translation should be included as part of the English version i.e. as a composite
dual language document. Where the Russian translation is generated separately from the
English version, then when submitted, the Russian version shall be submitted together with
the English version.
Submission requirements (i.e. document formats and identification) for the final translated
Russian versions remain the same as for all other submissions.
Company will provide a “starter kit” to Supplier containing, in electronic format, the following
proformas to be used when submitting documentation:
• Supplier Document Index proforma (Excel) SDRS Code A01
• Supplier Document Decal (CAD & Word)
• Supplier Document A4 Cover Sheet (Word & Excel)
• TOM & Equipment / Material Passport proforma Cover Sheets & Spines
Apart from the manuals (refer section 7) and the final electronic handover (refer section 8),
Supplier shall submit all documents for Company review via IMIS (refer to Section 1.3.2) in
electronic format. This shall minimise mailing costs and delays. Electronic formats shall be
as follows:
Drawings: Adobe Acrobat pdf files (CAD files are NOT acceptable for review
purposes. These shall be required for final submission see section
8)
Textual documents: Microsoft Word files
Spreadsheets: Microsoft Excel files
Where documents comprise more than 1 file (for example, a Word document with an Excel
attachment) then the file must be submitted as a single Adobe Acrobat pdf file. It is essential
that the Decal or Cover Sheet (completed by Supplier) is included as part of the electronic
file.
Company describes the mechanism for the submission of these files in:
All files shall be uniquely identified by bearing the same naming convention as the document
number structure indicated in 4.1.2. This information shall be presented in the following
manner:
Each document number component part shall be separated by the “hyphen” character (-)
and include the revision indicator, followed by the format separated by “dot” (.), thus:
The PDF file for Document Number KE01-C0-PAKL01A-J99-0001-000 revision 01 would
carry a file name of:
KE01-C0-PAKL01A-J99-0001-000-01.pdf
Where Company makes comments, these shall be applied to the Supplier document itself.
Company shall assign a Return Code for each submission of each document received for
review. The Return Code assigns a status to each document and identifies any further
action required by Supplier as follows:
Company shall be allowed 15 working days to review Supplier’s documents and return
comments.
Company shall return comments to Supplier via IMIS under cover of an electronic transmittal
attached to an email which shall list the documents in the consignment. All returned
documents shall be in Adobe pdf format and shall clearly show any Company comments,
the Return Code and Company’s authorising signature. Documents coded I, F or T will
have the cover sheet only returned showing Company acceptance.
Supplier shall be allowed 10 working days to revise and resubmit documents returned at
Code R.
Supplier shall resolve Company comments on any document returned Code U immediately.
As Code U is reserved for major comments, Supplier should initiate dialogue regarding the
nature of the comments immediately.
Supplier shall ensure that all revisions to documents are clearly identified by triangles or, for
textual documents, a line down the right hand side of the page. The method of resubmission
is as per first submissions.
translation. The explanatory Russian translation version is required only after the manual
has been accepted Code F, it is not required during the review cycle.
This section applies for the final handover hard copies of both the TOM Manuals and
Equipment / Material Passports.
7.3.1 Binders
The manuals shall be presented in sturdy white A4 sized 4 ring binders suitable for a shelf
life of 40 years. Supplier shall insert Front Cover sheets and Spines into the binder cover as
per Company provided formats (refer Annex E).
The electronic formats required during the review cycle are identified in section 5.1. As an
aid to long-term maintenance of equipment, Company requires a final electronic copy of key
documents, all in native file format.
Company has determined a set of standard electronic formats for native document
submissions as follows. Any deviation from this list is only acceptable if agreed specifically
with Company before submission.
• Microsoft Office (Word, Excel, Power Point – MS Office 2000 or above)
• Bentley Microstation – Version 7.1 (all reference files bound-in)
Note: Where it is not possible for the Supplier to provide documents in the above formats
alternatives may be proposed but only by exception and with explicit approval from
Company.
DOCUMENT TITLE 1 2 3 4 5 6 7
A - CONTROL DOCUMENTS
A01 SUPPLIER DOCUMENT INDEX 2 A Y
A02 FABRICATION / PRODUCTION SCHEDULE Y 2 A
A03 SUB-ORDER SCHEDULE / SUB ORDER COPIES 4 A
A04 WEEKLY PROGRESS REPORT 4 I
A05 MONTHLY PROGRESS REPORT 4 I
A06 SUB-SUPPLIER LIST Y 4 A
A99 MISCELLANEOUS NOTE 5
B - GENERAL ARRANGEMENTS
B01 GENERAL ARRANGEMENTS Y 6 A Y Y Y DL
B02 ACCEPTABLE NOZZLE LOADS (can be included in B01) 10 A Y ET
B03 INTERFACE & CONNECTION SCHEDULE (can be included in B01) Y 10 A Y Y DL
B04 FOUNDATION LOADING DIAGRAM & SUPPORT DETAILS (can be included in B01) 8 A Y Y DL
B05 LIFTING BEAM / FRAME / SLING DRAWINGS / LIFTING ARRANGEMENT DRAWINGS D-6 A Y DL
B06 EQUIPMENT SKID PIPING 12 A Y ET
B07 CIVIL/STRUCTURAL ARRANGEMENT DRAWINGS 6 A Y Y DL
B99 MISCELLANEOUS NOTE 5
C - SYSTEM DIAGRAMS & SCHEMATICS
C01 INSTRUMENT / ELECTRICAL LOGIC DIAGRAM 10 A Y DL
C02 PFDS AND HEAT MASS BALANCE. 6 A Y DL
C03 PIPING & INSTRUMENTATION DIAGRAM Y 8 A Y Y DL
C04 BILL OF MATERIALS 8 A Y DL
C05 OPERATING PHILOSOPHY 12 A Y DL
C06 CAUSE & EFFECT CHARTS 12 A Y DL
C07 CONTROL PHILOSOPHY & BLOCK DIAGRAM 12 A Y DL
C08 OIL SYSTEM OPERATING PHILOSOPHY 12 A Y DL
C09 ELECTRIC / ELECTRONIC / PNEUMATIC / HYDRAULIC SCHEMATIC 8 A Y ET
C10 SPECIFICATION FOR LINES 12 A Y ET
C11 ELECTRICAL EQUIPMENT LIST 12 A Y DL
C12 PIPING MATERIAL SPECIFICATION 12 A
C99 MISCELLANEOUS NOTE 5
D - DATA SHEETS
D01 UTILITIES SCHEDULE Y 10 A Y DL
D02 WEIGHT DATA SHEET 12 A Y DL
D03 EQUIPMENT DATA SHEETS Y 8/16 A Y Y DL
D04 NOISE LEVEL DATA SHEET 8 A Y DL
D05 TECHNICAL SPECIFICATIONS 10 A Y DL
D06 INSTRUMENT DATA SHEETS 12 A Y DL
D07 MOTOR DATA SHEETS 12 A Y DL
D08 SAFETY (COSHH) DATA SHEETS. 20 A Y DL
D99 MISCELLANEOUS NOTE 5
E - ELECTRICAL / INSTRUMENTATION
E01 INTERCONNECTION DIAGRAMS 8 A Y DL
E02 INSTRUMENT TERMINATION & HOOK UP DETAILS 16 A Y DL
E03 PANEL CABINET LAYOUT 16 A Y DL
E04 TERMINAL BLOCK DIAGRAMS 20 A Y DL
E05 DISTRIBUTION BOARD SCHEDULE 10 A Y DL
E06 COMPUTER SYSTEM DOCUMENTATION 20 A Y DL
E07 ELECTRICAL SINGLE LINE DIAGRAM 20 A Y DL
E08 ELECTRICAL TERMINATION AND HOOK-UP DETAILS 8 A Y DL
E09 LOOP DRAWINGS 12 A Y DL
E10 INSTRUMENT LAYOUT DRAWINGS 16 I Y DL
E11 INSTRUMENT OUTLINE DRAWINGS 16 I Y DL
E12 INSTRUMENT INDEX 8 A Y DL
E13 CABLE SCHEDULE 16 A Y DL
E14 LOAD / MOTOR LIST 8 A Y DL
E15 BIT MAP / SERIAL LINK PROTOCOL 12 A Y DL
E16 HAZARDOUS AREA EQUIPMENT SCHEDULE 12 A Y DL
E17 HAZARDOUS AREA CLASSIFICATION 12 A Y DL
E18 INPUT / OUTPUT LIST 12 A Y DL
E19 CABLE TECHNICAL DATA 10 A Y ET
E20 TRACE HEATING DRAWING / ISOMETRICS 12 A Y ET
Final Native
Contract Transmittal Purchase Document Submission Critical Equipment Translation Language File Format
No. Number Order No. Project Document No. Revision Supplier Document No. Supplier Document Revision Document Title Discipline Date SDRS Code Supplier Name Document Passport IOM Manual Required Code Expected Date Required
Below is a worked example for a fictional package
SUPPLIER
2003-0111 PAKM01A KE01-A1-PAKM01A-A01-000 01 3408H512035 00 DOCUMENT M 01-May-2004 A01 John Smith Ltd N N N Y E 07-May-2004 Y
SCHEDULE
Company As per Project Document The current expected date for
Company As per Project Document Date must be in As per Project Document
Supplier allocated As per Project Document Numbering Numbering procedure KE01-00- As defined on the As defined on the SDRS As defined on the As defined on the As defined on the submission of the next revision For Company to
allocated Contract Numbering procedure KE01- XXXXXXXXX (no dashes, slashes spaces etc) As shown on the document following UK format as Numbering procedure KE01-
transmittal number Purchase Order procedure KE01-00-000-AK-A-PR-0001-000 000-AK-A-PR-0001-000 (The 4th SDRS (Y/N) (Y/N) SDRS (Y/N) SDRS (Y/N) SDRS (E/R/D/ET) of this document. Date must be complete (Y/N)
Number 00-000-AK-A-PR-0001-000 above.DD-MMM-YYYY 00-000-AK-A-PR-0001-000
Number character of the PO number) in UK format as above.
Reviewing
Date
Engineer
NOTES:
KASHAGAN DEVELOPMENT
EXPERIMENTAL PROGRAM
A4 / A3 COVER SHEET
DOCUMENT TITLE *
P/O DESCRIPTION *
SUPPLIER *
TAG NUMBER *
NOTES:
A) THIS COVER SHEET SHALL BE USED FOR A4 / A3 SIZE DOCUMENTS OR
DRAWINGS. IT SHALL NOT BE USED FOR A2 / A1 SIZE DRAWINGS
FIGURE E.1 - COVER SHEET FOR TOM MANUAL & EQUIPMENT / MATERIAL
PASSPORT AS APPLICABLE
NOTE1: THIS PROFORMA TO BE SUPPLIED IN A4 SIZE
NUMBER OF VOLUMES:
EQUIPMENT DESCRIPTION:
SUPPLIER’S NAME:
EQUIPMENT DESCRIPTION: