Professional Documents
Culture Documents
Team 5
Overview:
• Designed to create spur in Economic Development
• Improve the trade relations with alternate high speed transportation
• One of the largest privately funded construction Project between two countries
• 51.5 Km long double rail tunnel.
• Project was initially estimated at 5.5 Billion dollars on completion the cost increased
to 14.9 Billion dollars
French and
British Govts.,
Transmanche Link
(TML) (Construction)
Scope Management
Rating :
2
2 2
2
Inception Development Implementation Closeout
2
• Lack of defined • Enormous scope • IGC had major • Even when the
scope • Measures to control over tunnel was
• Scope defined in prevent the scope deemed to
Lump sum basis scope creep was • Frequent complete, there
• Difficulty in not put in place change in scope were
Resource • Project • Door and A/c discrepancies
planning Planning, cost System over scope of
estimation, contributed to some works.
• Formation of
IGC Funding was major scope
affected due to changes
scope change
Time Management
Rating :
3
Inception 3 Development 2
Implementation Closeout
• Hasty Bidding • Change in 3 • Faster Tunneling 2
• Cascading effects
and concept requirement by • Rail and car of previous
development IGC caused delay systems were phases
• Not enough time • Approval of delivered late • 19 month delay
provided to drawings • Alteration of • Project
complete mandated from passenger door management
detailed design both sizes caused team could not
studies governments delay for 9 be held
• Very good months. responsible
tracking with
hefty status
report
Cost Management
Rating :
2
2
Inception Development Implementation Closeout 1
1
• Estimated cost 2
• USD 2.25 Bn • Unnecessary • Efforts were
of USD 5.5 bn. claim against use of costly driven towards
• Initial Cost Eutotunnel by technologies in settlemnt of
Estimates were contractor was some cases like claims rather
not detailed not anticipated grouting. than analysing
out. • Use of • Wrong on sources of
• Financing sophesticted selection of cost overrun.
arranged via equipment not TBM.
equity and anticipated
capital market
Quality Management
Rating :
5
5
5
Inception Development Implementation Closeout
4 5
• Difference in • Good PAC was • Stringent • Quality
standards -> framed. requirements parameters
Higher • No margin for from IGC achieved
standard errors • Very high were above
• Latest laser • Formation of accuracy industry
and computer IGC maintained. average.
technology
proposed to
bore the
tunnel.
Human Resources Management
Rating :
3
3 2
Inception 3 Development Implementation Closeout
3
• Team work • Every British • Managed • Most of the
envisaged team member 15,000 workers persons were
• Good structure had French in good demotivated
with proper counter part manner due to non
responsibilities • Workers from settlement of
formed. different claims.
cultures were • Win-win
engaged with situation was
high level of lost
efficiency
Communications Management
Rating :
2
Inception 3 Development 2
Implementation Closeout
3 1
• Difference in • Limited • Delay in • Negotiations
languages of communication communication not proper at
two countries between two regarding Closeout since
teams since specification bankers did not
both of them change. settle for
were trying to claims.
meet in
middle.
• This lead to
difference of
opinion at later
stages
Risk Management
Rating :
2
2
Inception Development Implementation Closeout
2 2
2
• Technical risk only • Over management • Fast tracking of • Courts ruled in
considered of risk – advanced design and favour of
• Process and techniques construction contractor.
approval risk were considered processes done
not envisaged • Contingencies and without risk
• Both governments margins were analysis.
denied to provide barest mimimum. • New unproven
financial • Contractors forced technology
guarantee. to consider best increased risk
• Social cost benefit situation. • Banks were
analysis not done. • Risk assessment involved for
plan was not minimising the
made. risk, however IGC
was controlling.
Procurement Management
Rating :
2
2
2
Inception 2 Development Implementation Closeout
3
• Rigorous time • Procurement • Fixed price • Cascading effect
constraints delayed since contracts with of
caused hasty scope/ several implementation
procurement specification was contractors created 17
plan/contracts. changing. • Differences in months delay.
• Procurement of goals since many • Non settlement
rolling stock and contractors were of extra claims
associated major having equity.
equipment
finalised on cost
plus percentage
fee basis
Integration Management
Rating :
3
2 3
Inception Development Implementation Close out
3 2
• Various • 46 contractors • Huge resources, • Teams not
international were deployed for huge scope of integrated due to
agencies took part design work were poor
for • 7 Lakh managed in best communication.
conceptualisation. shareholders, 220 of industry • Each party tried to
• Mistrust among Lending banks standards. focus on their own
agencies since were involved for • Logistical and interests.
both govts didn’t financing. communication • International
provide guarantee challenges. chamber of
but placed commerce
requirements. engaged for
dispute resolution
Rating Scale - Summary
Project Inception Developme Implementa Closeout Average
Management Area Phase nt Phase tion Phase Phase
Scope Mgt 2 2 2 2 2
Time Mgt 3 3 2 2 3
Cost Mgt 1 2 2 1 2
Quality Mgt 4 5 5 5 5
HRM 3 3 3 2 3
Communications
3 3 2 1 2
Mgt
Risk Mgt 2 2 2 2 2
Procurement Mgt 2 2 3 2 2
Integration Mgt 2 3 3 2 3
1975 A UK–France government backed scheme that started in 1974 was cancelled
British & French govt. agreed to common safety, environmental & security
1984
concern, prior opening up the project to bidder
1985 British & French govt. asked for proposals.
Project awarded to Eurotunnel on BOOT basis with 55 year concession
1986
period with initial cost of US$ 5.5 billion.
June 1988 In France, first tunneling was started
December
Tunneling operation was started in UK
1988
Tunnel was formally inaugurated & started functioning. Project was
May 1994
completed with cost & time over run.
Major Area of Strength Managing this Project
• Key learnings