a. Battery capacity test


 Measure and record every battery voltage (per cell) and temperature before doing
the discharging test (the measurement point is on the battery cell directly)
 Connect the dummy load to the output terminal of battery, make sure the breaker
which connect the battery to the dummy load is open
 Check the battery polarity and switch on the breaker and start up the dummy load
 Keep a constant discharge current by adjusting resistance according to voltage dop
by time progress
 The discharge capacity test will be conducted by twelve hours rate
The dishearge current shall be as follows:

Capacity : Ah
Total battery : Ea
Voltage/ battery :V
Overall voltage :V
Duration test (hour) :h

Corrected current at t°C is calculated as follows:

( Ah) .(correction factor)


It=
h

It=discharge current at t ° C

Correction factor = refer t° table-1

Discharge time 0°C 5°C 10°C 15°C 20°C 25°C 30°C 35°C 40°C
10 minutes to 0.58 0.68 0.79 0.91 1 1.05 1.09 1.12 1.14
59 minutes
1 hour to 24 0.81 0.86 0.91 0.96 1 1.03 1.05 1.06 1.07
hours

 Measure the battery voltage and temperature of pilot cell every hour during
discharge test
 After 12 hours, shut down the dummy load and switch off the breaker
 Overall voltage of the battery should be greater than 104V (1V+104) after h hours
discharging

b. Battery recharging
 Check the battery polarity and connect to the charger, make sure the breaker is
switch off
 The charging mode used by floating charge. The current is limited to below 0.2CA (C
= battery capacity), the constant voltage is 3.35V/monomer, the charge time
depends on the depth of discharge, see table-2
Depth of discharge Constant-current Constant-voltage
Charge time (h)
(%) charge current charge voltage
0.1C 2.35 12
20
0.125C 2.35 10
0.1C 2.35 18
50
0.125C 2.35 16
0.1C 2.35 22
80
0.125C 2.35 20
0.1C 2.35 26
100
0.125C 2.35 24

CB commissioning
a. Simultaneity (synchronize) and close/open time
 Take off the CB module and reverse the position of the contact finger to outside
 Connect the control terminal to the panel
 Put on the measurement cable on every phases
 Start the breaker analyzer machine according to the close-open command
 Analize the result on the computer, the result will be shown in numeric and graphic
 Record also the cycle operating test open-close-open time
 Record pole discrepancy each contact