INDWeLL CONSTrUCTIONS PrIVATe LIMITeD

Unit # 1x800 MW,Stage-V


Dr. Narla Tatarao Thermal Power Station,Vijayawada, Andhra Pradesh,
DAILY PROGRESS REPORT
DATE: 02 Aug 2017
Pre-Assembly Plcmnt in Position Alignment Weld/bolt/fix NDT/SR/HT
Srl Date ON PgmaNo DuNo
Qty Wt. in Kgs Qty Wt. in Kgs. Qty Wt. in Kgs Qty Wt. in Kgs Qty Wt. in Kgs
1 01/08/2017 35-130 003 1.00 12887.646 1.00 12887.646 0.00 0.000 0.00 0.000 0.00 0.000
Sub Total 12887.646 12887.646 0.000 0.000 0.000
1 01/08/2017 35-322 079 1.00 1420.460 1.00 1420.460 0.00 0.000 0.00 0.000 0.00 0.000
2 01/08/2017 35-322 093 1.00 477.890 1.00 477.890 0.00 0.000 0.00 0.000 0.00 0.000
3 01/08/2017 35-322 106 2.00 116.110 2.00 116.110 0.00 0.000 0.00 0.000 0.00 0.000
4 01/08/2017 35-322 107 3.00 219.610 3.00 219.610 0.00 0.000 0.00 0.000 0.00 0.000
5 01/08/2017 35-322 114 1.00 154.490 1.00 154.490 0.00 0.000 0.00 0.000 0.00 0.000
6 01/08/2017 35-322 120 1.00 171.380 1.00 171.380 0.00 0.000 0.00 0.000 0.00 0.000
7 01/08/2017 35-322 127 1.00 225.410 1.00 225.410 0.00 0.000 0.00 0.000 0.00 0.000
8 01/08/2017 35-322 141 1.00 100.700 1.00 100.700 0.00 0.000 0.00 0.000 0.00 0.000
9 01/08/2017 35-322 142 1.00 122.430 1.00 122.430 0.00 0.000 0.00 0.000 0.00 0.000
10 01/08/2017 35-322 143 1.00 97.420 1.00 97.420 0.00 0.000 0.00 0.000 0.00 0.000
Sub Total 3105.900 3105.900 0.000 0.000 0.000
1 01/08/2017 35-452 006 1.00 2769.380 1.00 2769.380 0.00 0.000 0.00 0.000 0.00 0.000
2 01/08/2017 35-452 007 1.00 2049.900 1.00 2049.900 0.00 0.000 0.00 0.000 0.00 0.000
3 01/08/2017 35-452 013 1.00 1297.410 1.00 1297.410 0.00 0.000 0.00 0.000 0.00 0.000
4 01/08/2017 35-452 019 1.00 1409.650 1.00 1409.650 0.00 0.000 0.00 0.000 0.00 0.000
Sub Total 7526.340 7526.340 0.000 0.000 0.000
Day Total in MT 23.520 23.520 0.000 0.000 0.000
Total for the Month in MT 23.520 23.520 0.000 0.000 0.000
Cumulative Total in MT 1305.717 1305.717 656.342 257.002 0.000

Page 1 of 3
Wt. in Kgs

Page 2 of 3
INDWeLL CONSTrUCTIONS PVT LIMITeD
APGENCO, STAGE-V, 1 X 800 MW, Dr.NTTPS IBRAHIMPATNAM
DAILY PROGRESS REPORT(SUMMARY)
Report Date: 02-Aug-17
Erected on: 01-Aug-17

WEIGHT AS THS MONTH


WEIGHT
PER CUMMULATIVE
Sl.No CATEGORY UPTO LAST
CONTRACT IN MT
MONTH MONTH
(MT) DAY WISE
WISE

1 Structures 12673.71 1282.197 23.520 23.520 1305.717


2 Pressure Parts 11635.47 0 0 0.000
3 Non-Pressure Parts 4973.2 0 0 0.000
4 Rotating Equipments 1992.64 0 0 0.000
Rotating Machine Handling
5 45.1 0 0 0.000
Equipments
Grand Total 31320.12 1282.197 23.52 23.520 1305.717
Note:
1 Proper road approach is required in site for marching hydra
2 Area Is not avialble for pre assembly
3 Area not provided to tie gai rope for column alignment

2 Erection Progress affected due to heavy rain on 20.07.2017 from 6:00 PM to 7:30 PM

MANPOWER REPORT AS ON 02.08.2017

Sl.No Designation Total Workmen Present Absent

1 Staff 20 19 1
2 Foremen 3 3 0
3 Skilled 48 36 12
4 Semi Skilled 18 18 0
5 Un skilled 7 6 1
6 Operators 10 8 2
Total 106 90 16