How to Change Resource Limit in Primavera P6

in LESS THAN 4 MIN

Ahmad Setayandeh
@Global Project Control
03-Aug-2020
How to change resource limit in Primavera P6

My Current Resource Status Limit is below

PIC1: Resource Limit

Sunday to Wednesday = 12 Hours

Thursday to Saturday = 8 Hours

You should go to Resource > Detail Tab > Create Personal Calendar

PIC2

Date: 29-Jul-2020
Page 1 of 3
Prepared By: @YouTube/ Global Project Control
How to change resource limit in Primavera P6

Create your Individual Calendar to UPDATE resource limit by update Work Week
(see below pictures)

PIC3

PIC4

Date: 29-Jul-2020
Page 2 of 3
Prepared By: @YouTube/ Global Project Control
How to change resource limit in Primavera P6

Then back to Activity Sheet and push Resource Usage Profile

PIC5: Resource Limit Change to 12 Hours / day

Result : Resource Limit will be change based on Resource Calendar Weekly Hours
which setup on picture no. 4

KEEP IN TOUCH, I am always available for further information.


https://www.linkedin.com/in/ahmad-setayandeh

https://www.youtube.com/c/GlobalProjectControl

https://www.instagram.com/global_project_control/

Date: 29-Jul-2020
Page 3 of 3
Prepared By: @YouTube/ Global Project Control