Professional Documents
Culture Documents
The attempted solution below are in response to the written assignment for unit 6 focusing on determining the
relevant cash flows, depreciation, payback period, net present value, IRR and ARR.
1|Page
Value
Total Cash flows
(93,786) (10,586) 2,560 35,650 43,683 51,553 72,466
Working 1. Depreciation
Depreciation = Cost - Salvage Value / Useful Life Depreciation = Cost - Salvage Value / Useful Life
= 85,000-13,000 / 7years = 65,000-0 /7 years
2. 9,286
VIABLE.
outflows. It’s usually expressed in years. When deciding between two or more competing projects, the usual
decision is to accept the one with the shortest payback period. Payback method is used as a first screening method.
Therefore, for the case of this Company project Option 2 should be selected since it has the shortest payback period
2|Page
of 7 years 9 months as compared to Option 1 whose Payback period is after the project’s useful life of 7 years. This
means the project will not be able to recover the investments during its implementation. However, The Company
cannot base its decision on the payback period alone as it does not consider the time value of money. The cash flows
are not discounted. It also ignores the timing of the cash flows within the payback period, cash flows after the end
Net Present Value (NPV) OPTION 1 Net Present Value (NPV) OPTION 2
Years Net PV PV cash Years Net cash PV PV cash
cash factors flows flows factors flows
flows 8% 8%
0 1 (65,000) 0 1
(65,000) (85,000) (85,000)
1 0.926 (89,799) 1 0.926
(96,986) (93,786) (86,836)
2 0.857 (16,362) 2 0.857 (9,075)
(19,086) (10,586)
3 0.794 2,978 3 0.794
3,751 2,560 2,032
4 0.735 19,494 4 0.735
26,523 35,650 26,203
5 0.681 33,505 5 0.681
49,228 43,683 29,731
6 0.630 29,483 6 0.630
46,784 51,553 32,488
7 0.584 25,878 7 0.584
44,349 72,466 42,284
(59,824)
(48,173)
NPV = (59,824) NPV = (48,173)
Net
discounting all cash outflows and inflows of a capital investment project by a chosen discount rate (target rate of
return) or cost of capital. The NPV method compares all present value of all the cash inflows from an investment
with the present value of all the cash outflows from the same investment, considers time value of money that a sum
of money received now is worth more than the same amount of money received in the future, considers all cash
flows in the investment unlike the payback period which only considers cash flows before the end of the payback
period. However, it’s a more sophisticated technique that may not be easily understood by especially non-financial
managers.
3|Page
A positive NPV means that the cash inflows from a capital investment will yield a return in excess of the cost of
capital and so the project should be undertaken if the cost of capital is the organization’s target rate of return. A
negative NPV means that the cash inflows from a capital investment will yield a return below the cost of capital and
so the project should not be undertaken if the cost of capital is the organization’s target rate of return. Therefore,
Is used to calculate the exact discounted cash flow from yield or rate of return that a project is expected to achieve.
IRR is also the rate of return at which NPV is zero. If the expected rate of return or IRR exceeds the target rate of
return, the project is worth undertaking (ignoring the risk and uncertainty factors). It’s fairly easy to understand and
interpreted by non-financial managers. However, its complex to compute and thus it requires the use of an expert, it
ignores the relative size of investments and in case of non-conventional cash flow patterns and the IRR method can
NPV=t=0∑n/(1+r) tCFt
Where:CFt=net after-tax cash inflow-outflows duringa single period tr=internal rate of return tha
t could be earned inalternative investmentst=time period cash flow is receivedn=number of indi
vidual cash flows
In the above case, all option’s IRR is below zero meaning that the IRR is below the Required rate of return of 8%
and the projects are not viable.
4|Page
ARR = 101,540/ 7 = 54564/ 7
= 14507 7,795
14507/85000 X 100 = 7795/65000 X 100
17% 12%
Average accounting profit is the arithmetic mean of accounting income expected to be earned during each year of
the project's lifetime. Average investment may be calculated as the sum of the beginning and ending book value of
the project divided by 2. Another variation of ARR formula uses initial investment instead of average investment.
Like payback period, this method of investment appraisal is easy to calculate and it recognizes the profitability
factor of investment. However, it ignores time value of money. Suppose if we use ARR to compare two projects
having equal initial investments. The project which has higher annual income in the latter years of its useful life may
rank higher than the one having higher annual income in the beginning years, even if the present value of the income
generated by the latter project is higher. It can be calculated in different ways. Thus, there is problem of consistency
and it uses accounting income rather than cash flow information. Thus, it is not suitable for projects which having
high maintenance costs because their viability also depends upon timely cash inflows.
REFERENCES
5|Page
Correia, C., Flynn, D., Uliana, E., Wormald, M. & Dillon, J. (2015). Financial
Management. 8th ed. Cape Town: Juta & Co Ltd.
Das, S. (2016). A banquet of Consequences: The reality of our unusually uncertain
economic future. Edinburg, UK: Pearson Education Limited.
Deloitte International Tax Source (2017). Taxation and Investment in China 2017.
https://dits.deloitte.com.Accessed 2017/07/12.
GrantThornton (2016). Deductibility of interest expenses.
http://www.taxplanningguide.ca/tax-planning-guide/section-3-investors/deductibility-interest-
expense. Accessed 2017/07/0.
6|Page