Professional Documents
Culture Documents
by Hassell E. Hunter
ABSTRACT
Three shafts, one ten feet in diameter and two six feet in diameter, were
successfully drilled to depths of 22431, 2188!and 21889respectivelyand cased with
hydrostaticdesigned steel casing. The largest shaft is to be used to handle muck
and water from stationexcavationand enlargementof the other two shafts.
A reverse circulation system with potassium chloride base mud was used for
drilling. The mud was cleaned by settling in steel lined tanks with assistanceby
cyclone type separators. Deviationwas monitored by gyroscopicsurveyingat 30 foot
intervalsand did not exceed 16 inches off plumb. Casing was designsd to withstand
hydrostatic pressures with a 1.5 safety factor to the large shaft and 1.25 safety
factor for the smaller shafts. All oaglng welds we= x-ray teated prior to lowering
the easing in the hole. Cementing the annular space completedthe operation.
The total time to mobilize,drill snd move off the three shafts was 363 days. The
drillingoperationwas completedahead of scheduleand under budget.
INTRODUCTION
PROJECTOBJECTIVES
The plan requiresthat one hole be used as a work shaft to enlarge the other two
holes which will become the main productionghaft and the ventilationsha~t.
Shaft No. 2 has been completed in a 72-inch diameter hole drilled to a depth of
2188 feet and caaed with 36-inch steel casing. This hole will be enlarged to a
finleheddiameternf 1E-feetto bacome the main productionshaft.
Shaft No. 3 has been completed in a 72-inch diameter hole drilled to a depth of
2188 feet and cased with 36-inch steel casing. This hole will be enlarged to a
finisheddiameterof 18-feetto bacome the ventilationshaft.
The three large diameter shafts drilled 100-feetapart will ba joined togetherat
the station level at abnut 2180-feet. All muck and water encounteredin enlarging
Shafts No. 2 and 3 will fall downward throughthe 36-inchsteel casing to the station
hft?l and thereafterbe removed throughShaft NO. 1 back to the surface for disposal.
120,
HOLE W HOLE 7Y HOLE I DEV.
SHAFT
MAIN
SHAFT
VENT.
SHAFT II
DEv.
SHAFT
MAIN
aHAFT
VENT.
SHAFT
I DEV.
SHAFT
MAIN
8HAFT
vENT.
SHAFT II
DEV.
SHAFT
MAIN
SHAFT ::::+1~
CROWNPOINT
SHAFT
DEVELOPMENT
CONCEPT
. ..-.., . ... . . . . .
Figure No. 1
546 1983 RETC PROCEEDINGS, VOLUME 1
DRILLINGMANAGEMENT
.wL@i3B&@.lJE.R-...
E.!!WK
.JML4WLWEE,!!
CROWNPOINT PROJECT
DRILLING ORGANIZATION
C4N1RAOS
I
1
_&!&A&&
mlm?MAN
“C-,ra.w -
I
I I
‘--- I L-1 I
f“-- C2M!.NTONG .. —-
M“o
..— -— — DIULLING
. . . . .. —-.
y’- 11”””--”
——
-’’---1
+>...
*-U
.......—
1:1 I -..-!.-.,!9----- &wNGJf!gl?Q
.“ -
.
mbJ,lL,z,w-_ ~r.sh
$.(.
W.nl..
T.d
I I - -1 v.”-.
c.Asww.&LEXALM_5
_EOW c*.E,a
Ii d
.AJR
_w.En.lQ#a WLL.CYLG_
L.CI+-8*PV. .- ImO!” -*. ..- A“
2. DrillingSuperintendent- W. E. CUIUIlnghSm
One or more of the above four persons were on locationat all times, The drilling
operation was supervised by P.E.S.around the clock, (24 hours a day/seven days a
week] for tbe durationof the Crownpnintdrilling.
DRILLINGSHAFT NO. 1
CROWNPUINT PROJECT
eOTTO+.4 HOLE ORILLING ASSEMBLY
e4’< m 0’ w*ts
120” Da e,t
I II
m
+-’
mm
1
,
‘[-
L— ——-.. —__L L+.—. -L .\-
1
“-q=— + “<” —
Figure No. 3
548 1983 RETC PROCEEDINGS, VOLUME 1
Drilling Equipment
The basic rig consistedof a 112 ft. maat with a hook load capacityof 1,000,000
lbs. The substructurewas 6-1/2 ft. high with sliding rotary beams that enable the
bit and bottom hole drilling aasembly to be pulled thrnugh the substructureinto the
mast.
The 120 inch bettom hole drilling assembly was degigned to accomplish two basic
purposee. To apply weight to the bit and to keep the hole straight. Both purposes
are accomplishedby use of an extremely heavy drill collar assembly having a weight
in mud of about 360,000 lbs. Figure No. 3 illustrates two different. bottom hole
assembly arrangements used in the drillingShaft No. 1 and Shafts 2 & 3.
The prime mover for the drill rig consistsof two CaterpillarD-379 turbo-charged
diesel engines rated at 615 hoigting horsepower each. These engines drive the
drawworks and rotary table througha torque cawerter and a compound.
Weight on the hit and rotary speed are controlled drilling parameters by the
Canoco drilling supervisor. The shale formations are the hardest to drill so the
highest weight on the bit will be used with a RPM to run smooth without excessive
vibrationor bit chatter.
The sand formations drill quite rapidly and u9ually penetrationrates had to be
held to 4 to 5 feet per hour to prevent overloading the circulation system with
excessivedrilled cuttings. The RPM sometimes was also slowed down as a vibration
limitingfactor.
Hole straightnessand Penetrationrate are controlledby weight on the bit and the
gpeed of rotation. The objective at Crownpoint was to achieve a reasonable
penetration rate while keeping the hole as perpendicular as possible. This ie
accomplishedby Uging a heavy bottom hole assembly and using approximately30$ or tne
Weight of the drill collar as weight on the bit and the remaining 70$ acting like a
pendulumto keep the hole straight.
PenetrationRates
There were twelve bit runs made on Shaft No. 1 to a total depth of 2243’ RKB
measurements. The rotatinghours during the drilling of the hole was 2294.75hours
or 96 days out of a total of 129 drilling days. This amounts for about 70$ of the
time on bottom rotating. Average penetrationrate was 0.98 feet per hour or 17.39
feetperdayoverall.
SHAFT CONSTRUCTION AT CROWNPOINT, NM 549
There were nine bit runs made on Shaft No. 2 to a total depth of 2188! RKB
measurements. The rotatinghours during the drillingof the hole was 1212 hours or
51 days out of a total of 62 drillingdays. This amounts for about 80$ of the time
on bottom rotating. Average penetrationrate was 1.8feet per hour or 36.46feet per
day overall.
There were eleven bit runs made on shaft No. 3 to a total depth of 2188? RKB
mea.vurements.The rotatinghour.vduring the drillingof the hole was 1258.5hours or
52 days out of a total of 66 drilling days. This amounts for about 79$ of tbe time
on bottOm rotating. Averagepenetrationrate was 1.7feet per hour or 34.Ig feet per
day overall.
Mud
The top portion of Shaft No. 1 was drilled using a freshwatergel mud. This was
done in the interest of economy. The mud system wag converted to a potassium
chloride system at 638 feet before enteringinto the Mancos Shale. The Mancos is a
bentonlticshale that swells and heaves upon contact with freshwater. A KCL system
is the best drillingfluid to inhibit this swelling situation.
The entire mud plan was predicated on inhibiting shale swelling. Hole
stabilizationwas the objectiveof the mud program. The hole could hsve been drilled
with water bad it not have been necessaryto stabilizethe walls of the bole.
Drilling
progessis shownin TableNo. 1 showing the time to drill Shaft No. 1.
TABLE 1. DrillingProgressShaft No. 1
TiMe to Complets
Mobilization 12 days
Drill 120n hole from bb~ to 22Q3V 129 days
PrepareRig To Run 85 inch Casing 5 dayg
Run 85 inch Casing to 2194 G .L. 21 days
Cement Casing 10 days
CIRCULATINGSYS’E14
All large diameter drilling operations require some type of air assiet method.
The rever9efluid air s.vsistcirculationsystem used on the CrownpolntProject is the
siMplCStof all air assist circulationmethods. No fluid pumps are used.
The hole is kept full througha gravityreturn line from the pits. Circulationis
createdby injectingair into a 3 l/~ line suspendedinside the drill pipe below the
hole fluid level in the annulus at about 32o feet. The column of fluid inside the
drill pipe is aerated md the 00IuMn Of fluid in the ann”lu~ is not aerated. The
Unequal hydrostatic heads of fluid inside and outside the drill pipe at the bit
result in a reverse flnw across the face of the bit. Cuttings are picked up and
returned to the surface at a velocity of about TOO feet per minute. At tbe
CrOWUpOiUtProject,air injectedat the rate of 2000 cfmproduced mudreturngof river
4000gpm.
The cuttings are dischargedout the blooie line into the working pits wherethe
cuttings
areremoved andhauled awayt,o a Wast,edi.epogalarea. CuttineaF-o-1 ‘“om
the~Ud is largely due to s~tt~ing in tne surface working puts and removed with a
crane and clamshell. Further cuttingsremoval is made with cyclone typs separators.
The air lift pump may be describedin its most basic terms as a ‘U” tubs havinE
unequal legs as shown in Figure No. 4. If the ‘UW tube is submerged in a tank Of
water as in Figure No. 4 where the shorter leg of the tube IS flooded, and air is
injected at some point into an outlet on ths longer leg, flOw will OcOur uP tbe
longer leg to en elevatedpoint. F1OW win occur only if the hydrostaticpressureOf
550 1983 RETC PROCEEDINGS, VOLUME 1
AIR INLET
I
< _@’1 o—
0 0
Q
0
0
0
0 0
0
0
8
0
0
0° 0 ~
u-TuBE Vd Vc
L EGENO
Figure No. U
There are two types of air lift pump systems but the pumping principleis the sane
as the U-tube, as illustratedin Figure No. 4. One system requires an outside air
line which is run in the annular space batween the hole and the tubing. The Outside
air line sygtem, or VA gystem, has the air flow line and the production tubing
SHAFT CONSTRUCTION AT CROWNPOINT, NM 551
running side by side in the well. Because of the nature of this parallel tubing
configuration, this system is not conducive to rotation of the tubing that is
required in a drillingsystem. While this, the VA type, is slightlymore efficient
than the other concentricstring tyw system (VC), it will not be stressed in this
paper. The second type is the concentricstring type, or VC eystem, where the air
line is suspendedinside the productiontubing becomes drill pipe in a rotatingmode.
The suspendedair line string should have left hand thread to lessen the possibility
of backingoff the couplingas the drill etring rotates to the right. The VC system
ie ellgbtly less efficient than the VA system because of the increased friction
caused by the concentricstrings having less then the full open diameter In the VA
type. However, the VC system lends itself to rotation and is used by most
contractorswho are engaged in drillinglarge diameter holes. It was with this type
circulatingsystem that the Atomic EnergyCommissiondrilleda 90* diameterhole to a
depth of 6200!in a single pass. This is the deepest large diameter hole that has
been drilled to date. The same gystem was used to drill 10 foot diameter hole to
5500 feet.
Figure NO. 5
Terminology
Level ie the leVel of the discharge pipe above the ground. This is the
Discharge
height of ~ooseneck attached to the swivel in the suspensionsystem, and varies
in height above ground level as the kelly is raised and lowered.
StaticFluid Level is the distancefrom ground level to the fluid surface in a etatic
air T=atic fluid level ghould be near ground level.
552 1983 RETC PROCEEDINGS, VOLUME 1
Pumpln&Fluid
.— Level is the same as the Static Fluid Level except in unusual
conditions such ag lost circulation. Hole i9 kept full by either pumps or gravity
flow return lines.
Kelly-Down la the distance the kelly travels while drilling down a joint of drill
Pipe while circulatingat rated capacityfrom the static or pumpingfluid level.
Minimum PumpinE Lift ia the distanoe from the static water level to the top of the
gooseneckdiachar~utlet when the kelly is in the down pnsition.
l.laximum
Pumpin& Lift la the digtancefrom the pumping fluid level to the top of the
gooseneckdischar~outlet when the kelly is in the up position.
Minimum Submergence is the distance from the pumpingfluid level to the air inlet
level when the kelly ie in the up position.
Maximum Submergenceis the distance Prom the pumping fluid level to the air inlet
level when the kelly is in the down position.
Notations:
B . Atmosphericpressure,psi A
c = EfficiencyConEtant
s = Pumpingsubmergence,ft.
$s = Percent
pumping
submergence,
S
~ : WdnIum eutme,gence,ft.
T= Totalfreeairrequired,
cfm
‘a = Quantity
of freeairrequired
pargal.,cfmlgpm
Vd = Dischargevelocity,ft.frain.
Ve : rntranoe
velocity,
ft./rein.
SHAFT CONSTRUCTION AT CROWNPOINT, NM
Basic Equations:
SS = 100s (Eq. 1)
E
r, (.052)(fQ)(S) + 1 (ml. 3)
B
%= (Eq. 4)
&
Qa2 = T (Eci. 5)
Qal = ~ (Eq. 6)
P
(Eq. 7)
pm = (.052)(~)(~) + f (Eq. 8)
Ps = (.052)(~)(S) (Eq. 9)
Dischargevelocity,fpm
Entrancevelocity,fpn
Quantity
of free air rewired, cfmlg!m
‘a =
c ,Cg,o <s+ = i’s (Eq. 12)
Sasic Thecry
fluid level.
The depth of submergenceis the next item that must be determined. Submergenceis
usually expressedas a per~ntage of the total length of the air line tubing. Thus,
so sir line string 200 feet long with 140 feet submerged below the ststic or pumping
fluid level with 60 ak+ve the fluid level would have a submergencepercentageof 70$
as calculatedby Equation 1.
The amount of Free air required in cubic feet of air per gsllan of fluid pumped
can k estimatedempiricallyfrom Equation 12.
The air volume requirementEquation 12 above can ba modified ’20)to account for
higher fluid densitiesaggociatedwith the lifting of the drilling mud and outtingg
for large diameterrotary drilled holes. The modifled equationis as follows:
c ‘og’o(?)
Equation 13 was used to caloulate the cubic feet of air required to produce a
gallon of drillingfluid on the CrownWint Project.
Tha ConstantC in Equation 12 & 13 may be taken from the Table No. 2, balou:
From Loomis(2)
Allen[ 20) noted that. the Constant ‘Cw changes to a 10wer value with increases in
air volume and further, that the system efficiency
*llen( factorthe
20) ca~a~lated is value
not applicable
of factorfor
“C”
drilling operationsat great depths.
with air volumes of 1000 cfm, 1500 cfm and 2000 Cfm in the fOllOwingTable No. 3:
SHAFT CONSTRUCTION AT CROWNPOINT, NM 555
Frem Allen(20)
Mud Weight = 9.o ppg
Drill Pipe = 13 3/8n O.D.
Inside Air Line
Submergenae$: 50 55 60 65 70 75 80 85 90
nCn Value
—— : 250 285 316 337 335 310 265 219 205
Submergence: 50 55 60 65 70 75 80 85 90
-cm Value
—— : 200 217 230 238 237 222 193 172 185
submergence%: 50 55 60 65 70 75 80 85 90
‘C” Value
—— : 158 173 182 186 181 170 155 139 125
This unreliabilityof the factor nCn was noted further in the Crownunintdrillinu
as it was calculateddaily. Time does not permit a thoroughanalysis kf Equation 1>
& 13 with the publicationof this report, but it is suggestedthat further study is
neca9.9aryto determinethe effect of frictionin the circulatingsystem.
Va . 60
320 10g ,0 140 + 34
3Q )
. 0.26 Cfm/ISPM
This estimate does not consider friction and the air required (cfm/gpm) will be
increaseddue to the high volume and high velocitycreated in a drillingapplication.
P~ . (.052)(~)(S)
, (.052)(9)(140) (Eq. 8)
= 66 psi
The CrounpointCirculatingSygtem
The collar shaft was completedto a depth of approximately60,in all three shafts
when the concretefoundationfor the rig was constructedby others. The working pits
were lined with steal plate into 8 separatecompartmentscontaininga total volume of
10,150 barrels. The hole is kept full of fluid through a 30” PiPe with cOnnects
between the last working pit compartmentand the hole.
When the ken y is drilled down, the maximum submergencepumping air Pressure is
estimatedwith Equation 9.
556 19S3 RETC PROCEEDINGS, VOLUME 1
Pm. (.052)(Mw)(SW)
+f (Eq. 9)
: (.052)(9)(180) + 10
, 90 psi
The loss of preseure due to the friction of gas flowing through the pipe can be
calculated from the basic Fanning equation. In the preceding example, the air
friction pre.saurelo.vse.s
were estimated at 10 psi. Conversely,the drill pipe and
air line SiZe9 should ba selected to keep the frl~tion IOS,SeSbetween 5 ~d Io p.gi.
Sizing of the drill pipe is an im~rtant function in the design of the efficient
operationof a reverse fluid air assist circulatingsystem. There are two types of
losses in the pipe; (1) the slippage of air through the drilling fluid and, (2)
norimalfriction losees of the drilling fluid with the pipe. As the fluid velocity
increases,the air slippagethrough the fluid will deoreaseand frictionlosses will
increase. The reverse is true as velocity deoreaseg, Friction losses will decrease
and air slippagewill increaseuntil at some pnint heading or intermittentunloading
will occur. This 19 an undesirable situation and adjustments are necessary to
increase velocity to obtain a steady flow. A constantpipevelocitycannotbe
achieved becauge velocitieswill increasefrom the fOotpieceto the eurface beca”~e
of the expansionof the injected air bubbles, The footpieceat the end of the air
line is essentiallya perforatednipple that dispersesthe injectedair into ae many
small bubbles as ie possible. Friction losses can W reduced by the use of larger
diameterdrill pipa oppositethe lengthof maximum air line submergence. The hole is
always the same level as the fluid level in the last pit.
BLOOIE LINE<
STEEL PITA
GROUND LEVEL PITSA
CROWNPOINT CONCEPT
REVERSE FLUID AIR ASSIST
CIRCULATING SYSTEM
FLOW DIRECTION
+
13 3/8”
Figure NO. 6
The air was suppliedby 3-AtlaS COPCYJrOtarY screw compressorsrated at 1200 cfm
at 310 psig. ~ch ~tary ~mpressor ie powered by a G.M. 16V-71internalcOmbustiOn
engine rated at 532 brake horse~wer. At the Crown@nt altitudeeach oonpressorbad
an output of ~~ut 1000 Cfm at tbe 170 psi operating pressure required ‘o activate
the circulatingsystem.
557
SHAFT CONSTRUCTION AT CROWNPOINT, NM
Two oompre9sors were used to activate the circulatingsystem while the third
compressorwas standbycapabilitywhen either of the other two compressorswere down
for any reason.
The Crownpoint PrOjOCt was carefully planned where fluid returns in the
circulatingsystem could be accurately measured. In fact, this is the first time
that mud returns, air input and pressurehave bsen accurately❑ easured on any large
diameterhole.
The fluid or mud returns from the hole carrying drilled cuttings first passed
through a mud-air sepsrator to remove aa much air as possible before the cutting
laden drilling fluid entered tbe fA.rstcompartment in the working pits. The flow
from one compartment to another was through a 1* x 5* ❑easuring weir. By measuring
the height of the fluid flowing throughthe weir.,the volume of fluid returningfrom
the hole could be accuratelymeasured.
Solids Removal
Further solids removal was achieved through the use of hydrocyclnne type
separators. At first Only one 1fJwLinatex 9eparatorwas used on Shaft #1. This was
increased to 3 units on Shafts #2 h #3. Each hydrocyolone separator bad an input
slurry capacity of 730-910 gpm. This solids removal equipment effectivelyremoved
fine particlesfrom the aystem helping the mud weight low.
Table 4 and Figure 7 shows the results of this flow test during routine drilling
operationsat a depth of 1958feet. The depth of submergence(S)of the air line was
337 feet and lift (L) was 32 feet above hole annulus fluid level. Percent
submergencewas 91g.
Constant
cm GM PSI CFWGPM ncm
It should ba noted tht the increasein air volume and horsewwer by a faCtOr Of 3
prodUCed only a 355 increase in drilling fluidreturns.Note,also, that Constant
.CW in Equstion 1 and 2 does not correlatewith data from Tables 2 and 3.
558 1983 RETC PROCEEDINGS, VOLUME 1
CROVVNPOINT
PROJECT
Fbw Rata Test
C.F.M. shaft No. 3
2-27-SI
5000
cm!
4000
3000
200D
1000 3260
0
0 1000 2000 3000 4000 5(
G.P.M.
Figure NO. ~
Design consideration for collapse are determined by the thicknessof the steel
plate,the casingdiameter- plate thicknessratio, the strengthof the material,out
of the roundness tolerance, the height and length of the stiffener rings and the
spacingof the stiffenerrings.
The 85-inchcaging weight in air waa over 3,000,000pounds. The ca.eingdesign was
later modified in part in order to expeditetimely delivery.
The entire casing string is run into the drilledhole before any oementingnperatinns
are commenced.
The welding contractorarranges the casing into its running sequenceduring grnut
line guide installation. He furnishesa crane and Low-boy truck to transport the
casing from the storageyard to the rig.
The welding contractors crane places one set of casing elevatnrsonto the casing
joint in front nf tbe rig and lifts the Joint into the V-donr whereby the rig crew
can attach tbe elevatorslings to the elevator.
The rig hoists tbe casing into a vertical positionwhile the welders crane holds
the oppositeend of the casing. Alignmentof the casing joint is the naxt task after
up-ending the caging. The closure pass or root bead is the first weld. The root
bead is inspactedusing radiographicproceduresbefore further welding is permitted.
The circumferentialweld is completedusing seven weldersworking simultaneously.
After the weld is cnmplete and the casing elevatoris removed from the joint that
has just been welded, four splice joints are placed in the area occupied by the
elevatorsto make each grout line guide continuous.
A fifth grOUt line guide is welded in place near one of the other grout line
guides.
The purpose of the fifth line is to prnvide free and independentaccess to the
annulus for the Nuclear AnnuluS InvestigationLog which is run on a wireline during
cementingoperations.
The hole is kept full of drilling fluid during the entire casing operation. As
the forty foot joint is lowered in the hole, the casing string will gain buoyancy
which is equal to the weight of the fluid which has been displacedfrom the hole into
the pits.
When the casing is lowered 40 ft., about 120,000lbs, of buoyancy is gained per
joint, thereby reducingthe rig load. Thereafter,water is added inside the casing
to cancel out the buoyancy effect and bring the rig back to a pick up load of
approximately
330,000
lbe.
The casing strongbackis a structuralbox with a cover Plate u~n which the casinS
elevatormust bear.
560 1983 RETC PROCEEDINGS, VOLUME 1
LOGGING
There are two types of geophysicalelectric logs used in large diameter drilling.
A CaliPer log is run upon reaching total depth of the hole. The purpose of the
caliper log is to determinehole configurationand hole volume.
SURVEYING
HorizontalDisplacement
Feet
— Direction e
Shaft No. 1 1.03~ S30 Deg. 171W 22U3t
Shaft No. 2 1.331 S21 Deg. 1’7!W 2188’
Shaft No, 3 0.84* s75 Deg. 38*u 2188~
CQ4ENTING
Three types of cement slurries were used. Chem ComP is a cement which axpands
when setting UP. The expanding cement was used on all three shafte to cover The
Westwatar Formation and other sand sections in the hole. The objective of the
expandingcament was to achievea good bond in the 9hale sectionsbetween major sand
formations. Prehydated2% gel cement was used on Shaft No. 1 on stagea requiring
only a filler cement. Neat aement was used as a filler cement on Shafta No. 2 and 3.
The cementing plan called for one cementing stage per day. The amount Of cement
that could be pumped in 2 1/2 hours was about 6500 sacks or 1550 barrals of cement
slurry per stage. Satting time for the cement was five hours. Only 1/2 of the time
was used for pumping and the other 1/2 of the time was used in pulling the four
tubing lines out and above the cement level in the annulua.
All cement slurries were displaced throush four 1.9 inch O.D. tubing lines
simultaneously. The tubing was rwn inside the 3 1/2 inch O.D.grout line guides that
were att.sohedto the casing when the casing was welded and run into the hola. The
5th 6r0ut line guide was used to run a wireline Nuclear !+nnulusInvestigationLog
(NAIL)to monitor the location of’the interface between the cement slurry and the
drilling fluid in the hole during cementing operations. Figure 8 illustrate the
second stage of cement in procese. The 1.9 inch tubing is pulled up and above the
cement level when each stage 19 complete.
The time between stages was used to refill the cement bulk storage bins on
location. Two 9tages of bulk cement were maintained on location fnr flexibilityin
case of interruptionsin logistice or weather. The cementing contractorfurniabed
15,500cubic feet of bulk gtorage space for the cement. Often, half of the storage
was filled with Chem CemP and Type I Class A in the other half.
SHAFT CONSTRUCTION AT CROWNPOINT, NM 561
CROWNPONW PROJECT
CEMENTING
\ ----
‘r
I 85 I.D. CASING
1-
OUTSIDE
GROUTING LINES
TOP
OF
I
SECOND&
SUBSEQUENT
CEMENTING
STAGES
. HEMISPHERICAL
. HEAO
Figure No. 8
The snurry volume requiredto cement the annulus of Shaft No. 1 wag 55,160cubic
feet; Shaft No. 2 was 42,5U7 cubic Peet; Shaft No. 3 was 44,047 cubic feet.
PUMPINGAND BAILINGCASING
Upon completion of the cementing operation, the inside of the large diameter
casing is full of fresh water. The final operationto ha performedis the removal of
water from the casing.
DRILLINGSHAFT NO. 2
The drill pad was releasedto the drilling contractoron September 30, 1980. Ris
Up was complete an~ Shaft No. 2 was 9pudded ‘n ‘Ctober 6’ ‘980” ‘rilling commenced
at a depth of zg feet rotary kelly bushingmeasurement(RKB)o
Using a drill
The 72 inch bottom hole drilling assembly shnwn in FiW’e No. 3-
abut 260,000lbs. only about Its of this
collar.assembly having a weight in mud
to Of
achieve a satisfactorypenetrationrate.
weight is used for weight on the bit
562 1983 RETC PROCEEDINGS, VOLUME 1
Shaft No. 2 was drilled to a total depth of 2188’RKB. Thereafter, 36 inch ring
gtiffened casing was run to a setting depth Of 2146! RKB (2132 ground level)
measurement and the annul us was cemented back into the collar shaft. Casing design,
running and welding casing and cementingcasing were similar to that discussedabove
fop Shaft No. 1.
The caaing design for Shafts No. 2 and 3 had a unique feature that was different
from Shaft No. 1. Off the shelf 36n line pipe complying to API 5L, Grade B,
standardswas ring stiffenedwith A-36 steel. The orlzinalcaairuz -. specificationsare
tabulated in Table 6.
After cementingoperationhad been completed,the casing was pumped and bailed dry
of fluid.
Time to
Shaft No. -2
—— Complete
DRILLINGSHAFT NO. 3
The drill pad was released to the drilling contractoron Decembsr 27, 1980. Rig
up was completeand Shaft No. 3 wasspudded cm January1, 1981at 0700hours.
SHAFT CONSTRUCTION AT CROWNPOINT, NM 563
Time to
Shaft No. .3
—— Complete
FISHING
There were two quickly solved fishing jobs. The 3 l/~ air line separated and
dropped on Shaft No. 1 and a cutter was lost off the bit on Shaft No. 2.
The air injection line on Shaft No. 1 separated at the gooaeneok and dropped
inside the drill pipe to the bit. The 3 1/2” tubing was recoveredwith an overshot
run on 2-7f8W tubing. The fishing job was oomplete In nine houre includingdelivery
time of the rented overshottool.
A cutter was lost at 1406~in shaft No. 2 due to a bit saddle failure. A 66-inch
rotating side door basket was fabricatedon the Crownpoint site. The cutter and
broken saddle were recoveredon the first fishingrun into the hole. The fishingjob
required 75 hours to complete including the time to acquire the steel plate and
rolling the plate into a 66 inch tube. Welding consumed about 28 hours of the time
to fabricatethe fishing basket. The run into the hole to catch the fish and come
out of the hole coneumed eight hours.
drillIng constructionwas finished 205 days ahead of the project plan schedule and
19.6$under budget.
Percent
Of Total
——
Shsft #1 53
Shaft #2 24
shaft #3 ~
Total 100 $
Acknowledgement
REFERENCES
1. O!Neil, F. W., 1960,
mCompressed Air Data,w Editor, Fifth Edition, Ingersoll-
Rand Company, New York, Chapter VII, page 113.
2. Loomis, A. U., 1980, ‘CompressedAir and Gas Data,m Third Edition, IngersOll-
Rand company,Washington,New Jersey,Chapter 31,page 31-1.
6. Hunter,H. E.,1974,‘LargeDiameterDrilledShafte,Conoco*sFlorencePilot
COPper Mine:,”PSSReportD-21-74,October,
ConOCoInc.,unpublished.
7. Hunter, H. E., 1976, “ReverseFluid-Air Assist CirculatingSystem,“ PES Report
T-1-76, February, Conoco Inc., unpublished.
8. Hunter, H. E,, 1977, ‘Specifications for 12 1/2 Foot Diameter Shaft, Crownpoint
Project,”PES ReportT-4-’I7, October,COnOOOInc.,Umpubliehed.
9. Hunter, H. E., 1978, ‘Rig Selection Procedure, Part I,” PES RePOrt T-2-?8>
March, Conoco Inc.,unpublished.
SHAFT CONSTRUCTION AT CROWNPOINT, NM 565
10. Hunter, H. E., 1978, ‘Rig Selection Procedure, Part II,” PES Report T-3-78,
Awust , Conoco Inc., unpublished.
15. Hunter, H. E., 1980, “Specifications for Welding services on 36-inch Casing,
CrownPointProject,tiPSS Report T-3-80,October,Conoco Inc.,unpublish
ed.
16. Hunter, H. E., 1981, ‘Drilling Record, Shaft No. 1, Crownpoint Project,n PES
Repnrt T-1-81, June, Conooo Inc.
17. Hunter, H. E., 1981, ‘Drilling Record, Shaft No. 2, Crown point Project,w PES
Report T-2-81, June, Conoco Inc.,unpublished.
18. Hunter, H. E., 1981, ‘Drilling Record, Shaft No. 3, Crownpoint Project,n PES
Report T-3-81, June, Conoco Inc.,unpublished.
19. Lackey, M. D.(Duane),1980, “Big Hole Drilling at the Nevada Test Site,” 1980,
Drilling TechnologyConferenceof the InternationalAssociationof Drilling
Contractors,March, Dallas, Texas.
20. Allen, J. H., 1976, “Improvements in BottomHole Cleaning ?or Large Diameter
Rotary Drilling Bits,nPh.D.dissertation,
Dscember, Sii Smith Tool Co.