The contents contained in this document may not be reproduced in any form or by any means, without the written permission of VIT, other than for the purpose for which it has been supplied. VIT and its logo are trademarks of Victorian Institute of Technology.
Planned Value • Planned Value (PV) is the authorized budget assigned to work to be accomplished for an activity or WBS component • Total Planned Value for the project is known as Budget at Completion (BAC). • Planned Value is also referred to as Budgeted Cost of Work Scheduled (BCWS). • Formula for Planned Value (PV) – The formula to calculate Planned Value is simple. Take the planned percentage of the completed work and multiply it by the project budget and you will get Planned Value. – Planned Value = (Planned % Complete) X (BAC) • Example of Planned Value (PV) – You have a project to be completed in 12 months and the total cost of the project is 100,000 USD. Six months have passed and the schedule says that 50% of the work should be completed.
– You have a project to be completed in 12 months and the total cost of the project is 100,000 USD. Six months have passed and 60,000 USD has been spent, but on closer review you find that only 40% of the work has been completed so far. • What is the project’s Actual Cost (AC)? – Actual Cost is the amount of money that you have spent so far. – In the question, you have spent 60,000 USD on the project so far. – Hence, the project’s Actual Cost is 60,000 USD.
• Earned Value is the value of the work actually completed to
date. If the project is terminated today, Earned Value will show you the value that the project has produced. • As per the PMBOK Guide, “Earned Value (EV) is the value of work performed expressed in terms of the approved budget assigned to that work for an activity or WBS component.” • Although all three elements have their own significance, Earned Value is more useful because it shows you how much value you have earned from the money you have spent to date. • Earned Value is also known as Budgeted Cost of Work Performed (BCWP).
There is a difference between Planned Value and Earned
Value. Planned Value shows you how much value you have planned to earn in a given time, while Earned Value shows you how much value you have actually earned on the project. • Formula for Earned Value (EV) – The formula to calculate Earned Value is also simple. Take the actual percentage of the completed work and multiply it by the project budget and you will get the Earned Value. – Earned Value = % of completed work X BAC
• You have a project to be completed in 12 months and the
total cost of the project is 100,000 USD. Six months have passed and 60,000 USD has been spent, but on closer review you find that only 40% of the work has been completed so far. • What is the project’s Earned Value (EV)? – In the above question, you can clearly see that only 40% of the work is actually completed, and the definition of Earned Value states that it is the value of the project that has been earned. – Earned Value = 40% of the value of total work – = 40% of BAC – = 40% of 100,000 – = 0.4 X 100,000 – = 40,000 – Therefore, the project’s Earned Value (EV) is 40,000 USD.
– It is very important for you to keep your project on schedule. Not only does it help you complete your project on time, but it also helps you avoid unnecessary cost overruns due to slippage of schedule, because as you go over the stipulated time, your costs start rising exponentially. – For example: you have rented some equipment for a specified duration of time. However, if you need this equipment for some additional time, and you may end up paying more because the equipment may not be available at the previously negotiated price, or you may need to rent this equipment from other suppliers on an urgent, short term contract at a higher price. – Schedule Variance is a very important analytical tool for you. This tool gives you information needed to determine if you are ahead of schedule or behind the schedule in terms of dollars.
• Cost Variance can be calculated by subtracting actual cost
from earned value. • Cost Variance = Earned Value – Actual Cost • CV = EV – AC • From the above formula, we can conclude that, – If Cost Variance is positive, this means you are under budget. – If Cost Variance is negative, this means you are over budget. – If Cost Variance is zero, this means you are on budget.
• The Schedule Performance Index indicates how efficiently
you are actually progressing compared to the planned project schedule. • As per the PMBOK Guide, “The Schedule Performance Index (SPI) is a measure of schedule efficiency, expressed as the ratio of earned value to planned value.” • The Schedule Performance Index gives you information about the schedule performance of the project. It is the efficiency of the time utilized on the project.
• Formula for the Schedule Performance Index (SPI)
– The Schedule Performance Index can be determined by dividing earned value by planned value. • Schedule Performance Index = (Earned Value)/(Planned Value) • SPI = EV/PV
• With the above formula you can conclude that:
– If the SPI is greater than one, this means more work has been completed than the planned work. In other words, you are ahead of schedule. – If the SPI is less than one, this means less work has been completed than the planned work. In other words, you are behind schedule. – If the SPI is equal to one, this means work is being completed at about the same rate as planned, you are on time. – While calculating the Schedule Performance Index, make sure that you consider all tasks. Sometimes you may only consider the tasks on the critical path while ignoring the rest, this will cause an erroneous result. Therefore, ensure that non-critical activities are included.
• The Cost Performance Index helps you analyze the
efficiency of the cost utilized by the project. It measures the value of the work completed compared to the actual cost spent on the project. • As per the PMBOK Guide, “The Cost Performance Index (CPI) is a measure of the cost efficiency of budgeted resources, expressed as a ratio of earned value to actual cost.” • The Cost Performance Index specifies how much you are earning for each dollar spent on the project. The Cost Performance Index is an indication of how well the project is remaining on budget.
• The Cost Performance Index can be determined by dividing
earned value by actual cost. – Cost Performance Index = (Earned Value)/(Actual Cost) – CPI = EV/AC • With the above formula you can conclude that: – If the CPI is less than one, you are earning less than the amount spent. In other words, you’re over budget. – If the CPI is greater than one, you are earning more than the amount spent. In other words, you are under budget. – If the CPI is equal to one, this means earning and spending are equal. You can say that you are proceeding exactly as per the planned budget spending, although this rarely happens.
• A consistently high or low value of SPI or CPI is an
indication that something is wrong with your planning and/or cost estimates. If this is the case, check all assumptions and estimates for accuracy and take corrective action as needed. • What is the difference between Cost Variance, Schedule Variance and Cost Performance Index, and Schedule Performance Index? – After studying the variances and indexes, you might be thinking that if both sets of equations (i.e. variances and indexes) provide the same information, why not discard one set of equations? Why not take only variances into account, or just performance indexes?
– In fact, both are required, because there is a difference between
variances and indexes. With variances you find the difference between the two values. With indexes, you get the ratio between the two values. – In cost or schedule variance, the result comes in dollar form. If this number is negative, you say that the project is in bad shape. However, if this number is positive, you say that the project is in good shape. The problem with variance is that you cannot compare the health of the project with another project if your organization has many projects. – Therefore, you use the Performance Indexes to compare the health of the project among many projects. The Performance Index is the ratio between the parameters, and only a glimpse of these ratios will be sufficient to determine health of the project. This makes it easier for you to compare the relative health of all projects. – Moreover, to get the efficiency, you need indexes.
7 Secrets of Highly Effective Social Impact Communicators How To Grow Your Influence To Solve Societys Most Pressing Challenges 1St Edition Nate Birt Full Chapter