Professional Documents
Culture Documents
ON BUILDING
SERVICES
HVAC SERVICES
A properly designed HVAC system performs three basic
functions:
1) Controls temperature and humidity to provide thermal
comfort.
2) Distributes adequate amounts of outdoor air to meet
ventilation needs.
3) Isolates and removes odors and pollutants through
pressure control, filtration, and exhaust fans.
REQUIREMENTS
• Duct supports, preferably in the form of angles of mild steel • Cooling towers are installed at a place where free flow
supported using stud anchors shall be provided on the ceiling of atmospheric air is available.
slab from the drilled hole. • Range of a cooling tower is defined as temperature
• Alternately, duct supports may be fixed with internally threaded difference between the entering and leaving water.
anchor fasteners and threaded rods without damaging the slabs • Structural provision for the cooling tower shall be taken
or structural members. into account while designing the building. Vibration
isolation shall be an important consideration in
• If false ceiling is provided, the supports for the duct and the false structural design.
ceiling, shall be independent. • Provision for make-up water tank to the cooling tower
• Collars for grilles and diffusers shall be taken out only after false shall be made. Make-up water tank to the cooling
ceiling/boxing framework is done and frames for fixing grilles and tower shall be separate from the tank serving drinking
diffusers have been installed. water.
• Make-up water having contaminants or hardness,
• Where a duct penetrates the masonry wall it shall either be which can adversely affect the refrigeration plant life,
suitably covered on the outside to isolate it from masonry, or an shall be treated.
air gap shall be left around it to prevent vibration transmission.
• Cooling tower should be so located as to eliminate
Further, where a duct passes through a fire resisting
compartment/barrier, the annular space shall be sealed with fire nuisance from drift to adjoining structures.
sealant to prevent smoke transmission.
FIRE FIGHTING SERVICES
BUILDING PLANNING CONSIDERATIONS FOR FIRE PREVENTION –
1. PASSIVE FIRE PROTECTION
• All enclosed staircases shall have access through self-closing door of one-hour fire resistance
• The staircase enclosures on the external wall of the building shall be ventilated to the atmosphere at each landing.
• There shall be no glazing or the glass bricks in any internal closing wall of staircase
• If the staircase is in the core of the building and cannot be ventilated at each landing, a positive pressure of 5-mm. e.g. by electrically operated
blower/blowers shall be maintained.
• Provision of the lifts shall be made for all multistoried building having a height of 15.0 m. and above.
• All the floors shall be accessible for 24 hrs. by the lift. The lift provided in the buildings shall not be considered as a means of escape in case of
emergency
• Grounding switch at ground floor level to enable the fire service to ground the lift car in case of emergency shall also be provided
• Walls of lift enclosures shall have a fire rating of two hours. Lift shafts shall have a vent at the top of area not less than 0.2 sq m.
• Landing door in lift enclosures shall have a fire resistance of not less than one hour.
FIRE FIGHTING SERVICES
BUILDING PLANNING CONSIDERATIONS FOR FIRE PREVENTION –
• Every high rise building Have minimum 2 number of Staircases.
• The number of lifts in one lift bank shall not exceed four. A wall of two hours fire rating shall separate individual shafts in a bank.
• For buildings 15.0 m. and above in height, collapsible gates shall not be permitted for lifts and solid doors with fire resistance of at least one hour
shall be provided.
• If the lift shaft and lobby is in the core of the building a positive pressure between 25 and 30 pa shall be maintained in the lobby and a possible
pressure of 50 pa shall be maintained in the lift shaft.
• The mechanism for the pressurization shall act automatically with the fire alarm/sprinkler system and it shall be possible to operate this mechanically
also.
• Entrance to the fire escape shall be separate and remote from internal staircase.
• The route to fire escape shall be free of obstructions at all times except the doorway leading to the fire escape
• Fire escape stairs shall have straight flight not less than 125 cm wide with 25 cm treads and risers not more than 190 mm.
4. FIRE DAMPERS
• These shall be located in air ducts and return air ducts/passages
• The dampers shall operate automatically and shall simultaneously switch off the air- handling fans. Manual operation facilities shall also be provided.
• In case of buildings more than 24 m. in height, in non-ventilated lobbies and corridors, smoke extraction shaft should be provided.
FIRE FIGHTING SERVICES
BUILDING PLANNING CONSIDERATIONS FOR FIRE PREVENTION –
5. AIR CONDITIONING
• Escape routes like staircase, common corridors, lift lobbies; etc. should not be used as return air passage.
• Wherever the ducts pass through fire walls or floor, the opening around the ducts should be sealed with fire resisting material of same rating as of
walls/floors.
• The material used for insulating the duct system (inside or outside) should be flame resistant and non- conductor of heat.
• In case of buildings more than 24 m. in height, in non-ventilated lobbies and corridors, smoke extraction shaft should be provided.
6. REFUGE AREA
• The refuge area shall be provided on the periphery of the floor & open to air at least on one side protected with suitable railing.
• For floors above 24m & up to 39m one refuge area on the floor immediately above 24m.
• For floors above 39m one refuge area on the floor immediately above 39m & so on after 15m refuge area shall be provided.
7. SERVICE DUCTS
• All the services ducts, if provided, should have to be enclosed by walls of at least 2 hour fire resistance & should have to be sealed at every alternate floor with
non-combustible materials having at least 2 hour fire resistance. The sealing at floor level is to prevent travel of smoke & fire to the upper floors through the
ducts.
8. FIRE EXITS
• Exit-that unobstructed component of means of egress which is between
the exit access and the exit discharge or public way. Exit components
include exterior exit doors at the level ofexitdischarge, interior exit
stairways, exit passageways, exterior exit stairways and exterior exit
ramps.
FIRE FIGHTING SERVICES
BUILDING PLANNING CONSIDERATIONS FOR FIRE PREVENTION –
9. FIRE FIGHTING SHAFTS
• Firefighting shaft (fire tower)—an enclosed shaft having protected area of 120 min fire resistance rating comprising protected lobby, staircase
and fireman’s lift, connected directly to exit discharge or through exit passageway with 120 min fire resistant wall at the level of exit discharge to
exit discharge.
• These shall also serve the purpose of exit requirement/ strategy for the occupants. The respective floors shall be approachable from fire-fighting
shaft enabling the fire fighters to access the floor and also enabling the fire fighters to assist in evacuation through fireman’s lift. The firefighting
shaft shall be equipped with 120 min fire doors. The firefighting shaft shall be equipped with firemen talk back, wet riser and landing valve in its
lobby, to fight fire by fire fighters.
• Sprinklers may connect to main water tank & pump, but capacity of the tank & pump shall be increased in that proportionate.
Transformer:
Demand Factor = 0.6
Power Factor = 0.95
Maximum demand calculated as 1563 kVA
Therefore we recommend for two Transformers of
1000 kVA each.
Design Considerations :-
• ½´´ → 16 mm
• ¾´´ → 20 mm STANDARD MOUNTING HEIGHTS OF WIRING
• 1´´ → 25mm ACCESSORIES
• 1¼´´→ 32 mm
• 2´´ → 50 mm • All switches → 1250 mm
• 3´´ → 75 mm • AFFL (After Finish Floor Level) Light , fan , w/h , w/m
• 4´´ → 100 mm .Sockets →450 mm
Note • AFFLTel/sockets →450 mm
• ½ ´´conduits are not recommended • AFFLSockets in kitchen → 250 mm above kitchen plat form
• ¾´´ (20 mm) 0r 1´´ (25 mm) conduit can be • s/o for w/h , w/m , A/C , near theequipment
use for wiring lighting.
• 1´´ (25 mm) or (32mm) conduit can be used for
wiring of s/o , w/h , w/m , c/r , pumps and low
current system like fire alarms wires , CCTV
telephone and TV wires.
MECHANICAL SERVICES
ELEVATORS
GENERAL TERMS
• Hoisting Beam - A beam, mounted immediately below the machine room
ceiling/machinery space ceiling, to which lifting tackle can be fixed for raising
or lowering parts of the lift machine.
• Landing Door - The hinged or sliding portion of a lift well enclosure, controlling
access to a lift car at a lift landing.
• Lift Well - The unobstructed space within an enclosure provided for the vertical
movement of the lift car(s) and any counterweight(s), including the lift pit and
the space for top clearance.
• Lift Pit - The space in the lift well below the level of the lowest lift landing
served.
• Rated Load (Lift) - The maximum load for which the lift car is designed and
installed to carry safely at its rated speed.
• Rated Speed (Lift) - The mean of the maximum speed attained by the lift car in
the upward and downward direction with rated load in the lift car.
• Safety Gear - A mechanical device attached to the lift car or counterweight or
both, designed to stop and to hold the car or counterweight to the guides in
the event of free fall, or, if governor operated, of over- speed in the descending
direction. Any anticipated impact force shall be added in the general drawing
or layout drawing.
• Sheave - A rope wheel, the rim of which is grooved to receive the suspension • Interval (INT) - Time period between successive car arrivals at
ropes but to which the ropes are not rigidly attached and by means of which the main terminal floor with cars loaded to any value.
power is transmitted from the lift machine to the suspension ropes. • Nominal Travel Time (NTT) - The nominal travel time is
• Suspension Ropes - The ropes by which the car and counter weight are defined as the time it would take to run a distance of the total
suspended. travel at the rated speed of the lift without taking into account
• Total Headroom - The vertical distance from the level of the top lift landing to the acceleration and deceleration of the car or the
the bottom of the machine room slab. intermediate stops of real runs. Round Trip Time
• Travel - The vertical distance between the bottommost and topmost lift • (RTT) - The average time taken by a single lift to make a trip
landings served by the lift. from the main terminal back to the main terminal, starting
• Elevators Handling Capacity (HC) - The number of passengers that a lift from the time the car doors open at the main terminal until the
system can theoretically transport during the up-peak traffic condition with car car doors re-open at the main terminal after serving all
occupancy of 80 percent of the actual capacity expressed as a percent of the demand along the way.
total building population.
MECHANICAL SERVICES
ELEVATORS
DESIGN CONSIDERATIONS
There are many variables which affect elevator system design. However,
the key ones to be specified are:
.
MECHANICAL SERVICES
TRACTION ELEVATORS HYDRAULIC ELEVATORS
.
.
.
.
MECHANICAL SERVICES
FREIGHT ELEVATORS
.
MECHANICAL SERVICES
PANORMIC ELEVATORS
.
MECHANICAL SERVICES
DUMB WAITERS
.
MECHANICAL SERVICES
ESCALATORS
TYPES OF ESCALTORS
• Moving walkways
• Paired Discontinuous Escalator
• Paired Continuous Escalator
• Single Discontinuous Escalator
• Single Continuous Escalator
• Crossing Escalator
COMPONENTS OF ESCALATOR
• Landing platforms
• Truss
• Tracks
• Steps
• Handrail
MECHANICAL SERVICES
ESCALATORS
DESIGN CONSIDERATIONS
OPTIMAL SPEED
The free overhead clearance at every point along To ensure safe use of the escalators and moving walks, sufficiently large free
the step/pallet band must be at least 2.3 m. spaces must be provided at the upper and lower landings (see the figure for
According to ANSI the dimension is 7 ft minimum dimensions according to EN 115).
(2130 mm). For moving walks that are expected to have a high traffic volume and that are
also designed for transporting shopping and baggage carts, the free spaces
SAFETY CLEARANCE should have a length of at least 5 m. If the carts are pushed into one another
when transported on the moving walks, the free spaces are to be adapted
The horizontal clearance from the outer edge of accordingly (see also Moving walk operation with shopping carts). Safety,
the handrail to the walls or other obstacles must regulation-compliant Balustrade height.
always be at least 80 mm. This clearance must Balustrades are available in heights of 900, 1000 and 1100 mm. The advantage of
be maintained up to a height of at least 2.1 m 900-mm balustrades is that even small children can easily reach the handrail. For
above the step/pallet band. With vertical walls, greater fall heights we recommend balustrades with a continuous height of 1000
all Schindler escalators and moving walks provide mm. A balustrade height of 1100 mm is also available if required under national
the specified safety clearance of 80 mm. regulations.
MECHANICAL SERVICES
ESCALATORS
PLUMBIMNG SERVICES
Distribution Systems in Multi-Storeyed Buildings
There are four basic methods of distribution of water to a multi-storeyed buildings.
a) Direct supply from mains to ablutionary taps and kitchen with WCs and urinals supplied by overhead tanks.
b) Direct Pumping Systems
c) Hydro-Pneumatic Systems
d) Overhead Tanks Distribution
This system is adopted when adequate pressure is available round the clock at the topmost floor. With limited pressure available in
most city mains, water from direct supply is normally not available above two or three floors.
Water is pumped directly into the distribution system without the aid of any overhead tank, except for flushing purposes. The pumps
are controlled by a pressure switch installed on the line. Normally a jockey pump of smaller capacity installed which meets the
demand of water during low consumption and the main pump starts when the demand is greater. The start and stop operations are
accomplished by a set if pressure switches are installed directly on the line. In some installation, a timer switch is installed to restrict
the operating cycle of the pump.
Direct pumping systems are suitable for buildings where a certain amount of constant use of water is always occurring. These
buildings are all centrally air conditioned buildings for which a constant make up supply for air conditioning cooling towers is
required.
The system depends on a constant and reliable supply of power. Any failure in the power system would result in a breakdown in the
water supply system.
The system eliminates the requirements of overhead tanks for domestic purposes (except for flushing) and requires minimum
space.
HYDRO-PNEUMATIC SYSTEMS
Hydro-pneumatic system is a variation of direct pumping system. An air-tight pressure vessel is installed on the line to regulate the
operation of the pumps. The vessel capacity shall be based on the cutin and cut-out pressure of the pumping system depending
upon allowable start/stops of the pumping system. As pumps operate, the incoming water is the vessel, compresses the air on top.
When a predetermined pressure is reached in the vessel, a pressure switch installed on the vessel switches off the pumps. As
water is drawn into the system, pressure falls into the vessel starting the pump at preset pressure.
PLUMBIMNG SERVICES
The air in the pressure tank slowly reduces the volume due to dissolution in water and leakages from pipe lines. An air compressor
is also necessary to feed air into the vessel so as to maintain the required air-water ratio. The system shall have reliable power
supply to avoid breakdown in the water supply.
This is the most common of the distribution systems adopted by various type of buildings. The system comprises pumping water to
one or more overhead tanks placed at the top most location of the hydraulic zone. Water collected in the overhead tank is
distributed to the various parts of the building by a set of pipes located generally on the terrace.
SANITATION SERVICES
It is the arrangement provided in a house or building for collecting or conveying waste water through drain pipes, by gravity, to join
either a public sewer or a domestic septic tank is termed as house drainage or building drainage.
In sanitation system pipes is designated upon their functions .
1:- Soil pipe-carrying human waste from wc.
2- waste pipe- pipe carrying sullage
3- vent pipe –it is a pipe installed to provide flow of air to or from the drainage system or to provide circulation of air in the drainage
system.
4- Anti siphonage pipe- it is the pipe which is installed to preserve the water seal in the trap through proper ventilation
5- Rain water pipe- a pipe carrying rain water only .
TYPES OF TRAPS
P-TRAP
Q-TRAP S-TRAP
Based on the Use, the traps are classified as:
• Floor Traps (Nahni Trap)- This trap is generally used to admit sullage from the floors of rooms, bathrooms, kitchen etc.
• Gully Traps- A Gully trap or gully is provided at a junction of a roof drain and other drain coming from kitchen or bathroom.
• Intercepting Traps- Intercepting traps is provided at junction of a house sewer and muncipal sewer for preventing entry of foul
gases
SANITATION SERVICES
PIPE SYSTEM
ONE PIPE FULLY VENTILATED ONE PIPE PARTIALLY VENTILATED SINGLE STACK SYSTEM
SYSTEM SYSTEM
SANITATION SERVICES
SANITATION SERVICES
SANITARY FITTINGS
Rainwater mixes with both soluble and insoluble materials from the
surfaces on which it lands and collects dust and pollutants as it flows
down through the atmosphere. Contaminants may be plants, fungi, and
other organic materials, as well as inorganic substances such as
dissolved minerals, metals, chemicals, or water-soluble paints. Although
collected rainwater does not need a high degree of purity for garden or
agricultural applications, rainwater collected from unclean surface
runoffs is not suitable for drinking or cooking. Separation of the first
flush of rainwater from the roof, gutters, and other collection surfaces
can improve water quality in the rainwater storage tank.
RAINWATER HARVESTING
DESIGN CONSIDERATIONS
• Design your roof well for rainwater collection
A flat roof can be gently sloped to drain water towards the storage system. A 'nahani trap' or 'floor trap' can be placed at the
time of casting the roof just near the inlets of the down water pipes.
Sloping roofs should have a gutter of PVC or zinc sheet to collect water & channel it to the down water pipe system.
Roofs should be uncluttered & should be easy to clean by sweeping & swabbing if necessary.
• Down water pipes should be designed well
90mm dia. PVC pipes resistant to UV rays appear to be the best bet as downwater pipes. Of course, this depends upon the
roof area to be drained.
3 to 4 downwater pipes seem sufficient for 1000 to 1200 sft area
• Filter the rainwater before storage
Filtering can be as basic as a floor trap placed before the water enters the downwater pipe or a piece of sponge placed at the
inlet of the downwater pipe. PVC bucket with gravel, sand & charcoal is a good filter before rainwater is stored or a small two
chamber inspection/ filter tank can also be devised.
• Locate the storage system properly
Roof level storage tanks may need to be at the rear of the house or on the sides so that it is neither obtrusive nor visually
offensive.
Ground level drums or tanks occupy space and should not hinder movement or appear unsightly.
Below the ground sump is a good option since most new constructions in Bangalore go in for sumps anyway. Sumps are
hidden from view, less costly to build and do not obstruct movement.
• Always provide for an outlet for excess collection of water from the storage system
RAINWATER HARVESTING
The size of the tank is dependent of the amount and purpose Average rate of rainfall in mm/h
of the water but also of the annual rainfall and the size of the Diameter
roof. A normal sized tank for a roof of 20 to 40 square of pipe 50 75 100 125 150 200
metres is 10 cubic metres. (mm)
50 13.4 8.9 6.6 5.3 4.4 3.3
WATER TANK DESIGN REQUIREMENTS
65 24.1 16.0 12.0 9.6 8.0 6.0
• A solid secure cover
75 40.8 27.0 20.4 16.3 13.6 10.2
• A coarse inlet filter
• An overflow pipe 100 85.4 57.0 42.7 34.2 28.5 21.3
• A manhole, sump, and drain to facilitate cleaning
• An extraction system that does not contaminate the water; 125 - - 80.5 64.3 53.5 40.0
e.g., a tap or pump
• A soak away to prevent spilled water from forming puddles 150 - - - - 83.6 62.7
near the tank
mm/h :- millimetre per hour
COMPONENTS OF RAINWATER TANK
• CONDUIT :- Conduits are pipelines or drains that carry • FILTER :- The filter is used to remove suspended
rainwater from the catchment or rooftop area to the pollutants from rainwater collected over roof. A filter unit
harvesting system. Conduits can be of any material like is a chamber filled with filtering media such as fibre
polyvinyl chloride (PVC) or galvanized iron (GI), materials coarse sand and gravel layers to remove debris and dirt
that are commonly available. from water before it enters the storage tank or recharge
structure. Charcoal can be added for additional filtration.
RAINWATER HARVESTING
RECHARGE STRUCTURES
In this case the rooftop runoff is not directly led into the
service tubewells, to avoid chances of contamination of
groundwater. Instead rainwater is collected in a recharge
well, which is a temporary storage tank (located near the
service tubewell), with a borehole, which is shallower than
the water table. This borehole has to be provided with a
casing pipe to prevent the caving in of soil, if the strata is
loose. A filter chamber comprising of sand, gravel and
boulders is provided to arrest the impurities.
RAINWATER HARVESTING
RECHARGE STRUCTURES
A recharge pit is 1.5m to 3m wide and 2m to 3m deep. The A recharge trench is a continuous trench excavated in the
excavated pit is lined with a brick/stone wall with openings ground and refilled with porous media like pebbles,
(weep-holes) at regular intervals. The top area of the pit can be boulders or broken bricks. A recharge trench can be 0.5 m
covered with a perforated cover. Design procedure is the to 1 m wide and 1 m to 1.5 m deep. The length of the
same as that of a settlement tank. recharge trench is decided as per the amount of runoff
expected. The recharge trench should be periodically
5. SOAKAWAYS / PERCOLATION PIT cleaned of accumulated debris to maintain the intake
capacity. In terms of recharge rates, recharge trenches
Percolation pits, one of the easiest and most effective means are relatively less effective since the soil strata at depth of
of harvesting rainwater, are generally not more than 60 x 60 x about 1.5 metres is generally less permeable. For
60 cm pits, (designed on the basis of expected runoff as recharging through recharge trenches, fewer precautions
described for settlement tanks), filled with pebbles or brick have to be taken to maintain the quality of the rainfall
jelly and river sand, covered with perforated concrete slabs runoff. Runoff from both paved and unpaved catchment
wherever necessary. can be tapped.
7. RECHARGE TROUGHS