Assignment II

TM-4116
Peningkatan Perolehan Minyak (Enhanced Oil Recovery)
“Two Dimensional Displacement”

QUESTIONS
1. Water injection at constant rate 1000 B/D/well with a direct-line drive pattern have fluid and rock
properties as follows
Ø = 0.18 Swc = 0.20 Sor = 0.20
μo = 5 cp μw = 0.5 cp kro and krw (use data from assignment 1)

And the geometry of injection data:

• Dip angle = 00
• Reservoir thickness = 40 ft
• Distance between injection wells = 625 ft
• Distance between injection and production well = 2000 ft

p p p
Assume diffused flow condition and injection begins at the same time with oil producing from reservoir,
calculate:
a. BT (breakthrough) time.
b. Cumulative oil production as a function of cumulative water injection and time.
2. Water injection is conducted to a single layer of oil reservoir with 5-spot injection pattern. The dip of
the layer is negligible. The area of one pattern unit is 50 acres and thickness are 20 ft. The petrophysical
and fluid data are as follows:

Ø = 0.18 Sg = 0.02 Bo = 1.25 BBL/STB

Swc = 0.20 Sgc = 0.025 Bw = 1 bbl/STB

Sor = 0.18 μo = 10 cp μw = 0.5 cp

Kw (@ Sw = 0.82) = 40 mD

Ko (@ Sw = 0.20) = 80 mD

Make a forecast for the reservoir behavior by plotting he cumulative oil production as a function of the
quantity of cumulative water injection (Wp) and the water-oil ratio at the surface (WORs