You are on page 1of 6

Special Report Plant Safety and Environment

D. SMITH and J. BURGESS, Smith & Burgess LLC,


Houston, Texas

Relief valve and flare action items:


What plant engineers should know
When most companies implement the process safety man- RELIEF SYSTEMS REVIEW METHODOLOGY
agement standard, they routinely or periodically review the Relief systems design basis reviews are typically performed
relief systems and flare systems design bases to ensure compli- by contractors that assist in developing project guidelines and
ance with corporate, industry and/or government standards, then collect the necessary information. After these initial ac-
hereafter referred to as Recognized And Generally Accepted tions, the contractors analyze the system’s design basis per the
Good Engineering Practices (RAGAGEP). To mitigate con- project guidelines and present a list of identified concerns to the
cerns before implementing projects, it is advisable for plant plant’s engineers and management. Prior to spending money to
engineers to consider several items when reviewing a con- upgrade the relief systems, a plant engineer familiar with the pro-
cerns list: cess unit should review the concerns list to ensure that:
1. Relief systems review methodology • Details of the study are reasonable
2. Relief systems review priorities • Assumptions of the study are reasonable
3. The process designer’s familiarity with the process and/ • Facility upgrades, not based on minimum compliance,
or plant when concerns are being reviewed have been thoroughly reviewed.
4. The plant engineer’s understanding of the differences By reviewing the concerns list with these suggestions, a
between compliance and best-in-class practices. plant engineer can ensure that costly changes have a basis in
An article published in 2000 concluded that up to 40% of sound engineering and that the expense is justified. Note that
the installations evaluated had unidentified concerns.1 Since no hierarchical order is implied in this list.
the publication of this article, many of these concerns have un- Typically, when a relief systems design basis project is un-
dergone a more detailed review showing that modifications to dertaken, the goal is to produce compliant documentation ef-
the facility were not required to address these concerns. ficiently and consistently. To do this, process designers must
The purpose of this article is to help the plant engineer re- base the analysis on a framework to minimize effort and ensure
view the concerns developed by the design engineer. Imple- consistency. This is a practical method for performing a large-
menting field modifications without performing such a review scale relief systems analysis; however, for any particular con-
is costly and exposes a facility to unjustified risks. cern, the framework may break down and suggest items that
For the purposes of clarity, the following terms used are not actually concerns.
throughout this article are defined as such: In a recent review project, approximately 40% of the listed
• Plant engineer—The facility or owner’s engineer who concerns were later found to be acceptable based on a detailed
is responsible for reviewing the concerns and determining if review. The following sections help walk a plant engineer
facility modifications should be implemented through a systematic process and give insight into how to re-
• Process designer—The individual who is responsible view the listing of concerns.
for analyzing the relief device and overpressure protection sys-
tem and developing the concerns Reviewing relief system study details. When the concerns
• Concerns—Items that are listed (prior to being fully re- are reviewed from the perspective of the process designer, the
viewed and accepted) as deviations from industry or company plant engineer can understand how the framework may have
standards. generated potential concerns. Understanding this process can
At the end of the relief systems design basis project, the help the plant engineer identify resolvable concerns by review-
process designer typically identifies many concerns. As most ing the design basis.
facilities want to comply with RAGAGEP, there is a mandate Understanding the process. When completing large-scale
to resolve these concerns, and their resolution can be costly. relief systems design basis documentation and design pro-
Generally, most facilities seek to comply with regulations cesses, the process designer is usually quite familiar with relief
for existing facilities and to potentially build new equipment systems design but may not be familiar with the particulars of
and facilities to a higher standard. This article includes exam- the process or unit. The process designer, therefore, may make
ples of how to review existing systems to determine if concerns unrealistic judgments about process upsets. The following are
justify field modifications. examples of these items:
Hydrocarbon Processing | NOVEMBER 201241
Plant Safety and Environment

• When process flows can be blocked, or if the normal rate ther searching for process and/or equipment data. Often, this
is possible under upset conditions requires a call to an external supplier or technical body (e.g.,
• Use of the normal/design duty from a reboiler for relief the equipment manufacturer or national board).
rate estimation Other execution issues. The relief systems process typical-
• Equipment that is no longer in service is not properly ly uses a consistent basis that is often documented and referred
protected. to as site or project guidelines. These guidelines are beneficial,
To ensure the best possible analysis, each study should be as they provide a means for efficient and consistent execution
reviewed by personnel familiar with the process operation to and help ensure that both the process designer and plant en-
confirm that unique process characteristics are captured in the gineer are in agreement on the details of the analysis. When
relief systems documentation. these generic and prescriptively conservative guidelines gener-
Credibility of scenario or relief rate. For each overpres- ate concerns, it is imperative that the team generating the docu-
sure scenario that generates a concern, the plant engineer mentation reviews the fundamentals of the analysis to confirm
should give particular attention to ensure the credibility of the that the concern is a legitimate deviation from RAGAGEP and
scenario or required relief rate. Many times, an overpressure not just a result of the project execution process.
scenario or the estimated rate may not be credible. The follow-
ing are some examples: Reviewing relief system study assumptions. The typi-
• Pumps that can only pump to relief pressure if the up- cal execution method of a project tends to enforce consistent
stream system is also upset (however, a simultaneous upset assumptions. For most of the project, this ensures that the re-
would be considered double jeopardy) lief systems design basis is conservative and compliant with
• Systems where overpressure derives from heat input, RAGAGEP. To ensure that field modifications are for items
such that the relief temperature of the process fluid exceeds the that must be addressed, these assumptions may need to be
relief temperature of the utility fluid challenged when concerns are raised.
• Control valve failure calculations that are based on the ca- Standardization assumptions. Standard and generally
pacity of a control valve instead of on another limitation (e.g., a conservative assumptions are specified to ensure consistency
long section of piping or a pump). and efficiency. These assumptions help the relief systems
To ensure an accurate analysis, each concern should be re- documentation process run efficiently; however, if generic as-
viewed to verify that consideration has been given to the de- sumptions result in concerns, they should be revisited and up-
termination of the scenario applicability and that the relief rate dated. The following are some examples of these items:
estimate is reasonable for the particular process or unit. • Liquid levels for equipment
Gathering facility data. The relief systems analysis process • Control valve flow coefficients and trim sizes
typically limits the amount of places and time that the process • Utility pressures (e.g., steam, nitrogen, cooling water)
designer can search for process and equipment data. This limi- • Heat exchanger or pump capacities.
tation is usually defined as a project scope item and is used to To ensure the best possible analysis, the assumptions asso-
ensure that the project has boundaries. When reviewing con- ciated with each concern should be reviewed and, if possible,
cerns, the plant engineer must ensure that the process designer refined to be specific for that system.
has not identified concerns that can be readily resolved by fur- ‘Conservative’ assumptions. The authors of this article
have been carrying out relief systems analysis for multiple de-
System relief devices
CSO
cades and believe that “conservative assumption” is frequently
4 x 8-in. inlet flange, To flare
10-in. outlet flange, T orifice used as a phrase for a simplifying assumption that the process
External system feed
Pmax = 200 psig Overhead
designer invoked. Furthermore, this phrase typically has noth-
CSO cooler ing to do with being conservative. The following are examples
Offgas product of conservative assumptions:
• Normal flowrate was used instead of a reduced estimate
• Column tray or overhead flowrate was used instead of
Top pumparound Top reflux performing a simulation
Overhead • Multiple unrelated failures occurred simultaneously.
product
As previously stated, each “conservative assumption” should
be reviewed and refined so that it is specific for each system.
Bottom pumparound Mid-tower product Other assumptions. The design and analysis of relief sys-
tems is an art. Much of the analysis is based on the assumptions
that form the overall basis. Mathematical errors are rarely the
Fractionator cause of an incorrect analysis; usually, the cause is a problem
Bottom product with the basis. The basis for each system is stacked on top of a
Other process basis for another system. Once the assumptions are flushed out
heaters and determined to be correct, the mathematics are easy.
Fractionator example. In the past, the authors reviewed
Feed furnace a fractionator (FIG. 1), where the normal feed vapor rate was
specified as the relief rate for a power failure relief load (conser-
FIG. 1. Flow diagram of an example fractionator. vatively assumed). When the capacity of the feed furnace was
42NOVEMBER 2012 | HydrocarbonProcessing.com
The world’s largest hydrogen
pipeline network delivers...
The world’s most reliable
hydrogen supply.

It’s the kind of massive project only a global leader would undertake.
Anticipating that hydrogen needs along the Gulf Coast of North America
will increase in the years ahead, Air Products expanded its hydrogen supply
network. By building a 180-mile (290-km)-long pipeline that connects our
existing Texas and Louisiana systems, we’ve united 22 hydrogen plants and
600 miles (965 km) of pipeline, with a total system capacity of over one billion
SCFD (1.3 million Nm3/hr). So if an event disrupts operations on one side of
the Gulf, hydrogen can keep flowing from the other, giving our refinery and
petrochemical customers the reliable, uninterrupted supply they need. With
this record-breaking network, Air Products continues to break new ground in
hydrogen supply. For videos and detailed information, visit our website.

tell me more
airproducts.com/H2pipeline

©2012 Air Products and Chemicals, Inc.

Select 67 at www.HydrocarbonProcessing.com/RS
Plant Safety and Environment

confirmed, the feed furnace could barely vaporize the normal have yet to find a single case of a slightly undersized relief de-
amount at the normal production rate and fractionator pres- vice resulting in an injury or loss of containment. There are,
sure. This particular power failure scenario specified the loss of however, countless records of injuries sustained from refinery
the pumparounds, which resulted in the loss of approximately modifications that can be found via Internet search.
80% of the crude preheat train duty. To illustrate this point, in a 2009 Chemical Safety Board
(CSB) video requesting that the city of Houston,
Texas adopt the American Society of Mechanical
Engineers (ASME) Pressure Vessel Code, the CSB
When properly reviewed, upgrades was unable to find instances resulting in loss of con-
tainment for pressure vessels for undersized relief
to the flare and relief system from a devices.3 The video cites three examples of vessel
relief systems analysis can improve failures from undersized relief devices. The first ex-
ample is a low-pressure tank with an undersized re-
the safety of an operating facility. lief device, and the other two examples have plugged
or isolated vent lines.4, 5, 6
For a plant engineer responsible for increasing
overall facility safety, it may be possible to defer
With the increase in pressure and cooler-than-normal feed modifications for the resolution of minor deviations until
temperature to feed furnace, the maximum vaporization would other equipment changes are required. This would be at the
be around 50% of the normal vapor rate. The argument for discretion of the facility, it would require a reasonable level
keeping the feed preheat was that it was conservative, as the of risk, and it could open up the facility to regulatory action.
heat input may not be lost. If this turned out to be the case, then
pumparounds would have continued, leading to a significantly FLARE SYSTEMS REVIEW METHODOLOGY
different outcome. Assumptions need to at least be internally The preceding section reviewed the typical methodology
consistent for each scenario. If the pumparound cooling is lost, that a process designer would use to generate a relief systems
then so is the feed preheat, and vice versa. design basis. This section is designed to help the plant engi-
neer understand how the individual relief systems loads are
Distinguishing minimum compliance from best developed and used to create an overall set of global scenarios,
practices. The final items that need to be reviewed by the which is then used to verify that the flare system and associated
plant engineer are any deviations from RAGAGEP (and not equipment are adequately designed. Several key topics will be
just deviations from best practices). Often, when completing further explored:
relief system projects, the team responsible for the design will, • Global load considerations
with the best of intentions, work into guidelines some require- • Reasonable and consistent assumptions
ments that go beyond RAGAGEP. • Advanced flare techniques.
While extra requirements may be justified based on the in- By reviewing the flare systems design concern list from
creased safety at nominal incremental costs in new construction, these three angles, a plant engineer can ensure that the basis for
these requirements can be quite expensive for existing facilities. costly changes is justified.
These additional requirements must be reviewed and possibly
excluded from items that need to be retrofitted. Regulatory re- Global load considerations. When a relief systems design
quirements may require additional documentation to ensure project is undertaken, the individual relief device loads are
that not making modifications presents an acceptable risk.2 typically gathered first. Once these loads are known, they are
Gray areas for modification. Often, items may not be ab- entered into a hydraulic analysis tool, and then the flare system
solutely correct, but they also may not rise to a level requiring is analyzed. However, as with the individual load determina-
field modification. An example is when current corporate stan- tions, there are areas that a plant engineer should review.
dards exceed the standards to which a unit was built. This situ- Credibility of the scenario. In global scenarios, the process
ation is particularly relevant when a facility is acquired, thus designer typically will review power failures (both a total loss
creating a situation where a facility was constructed to one set of power and partial power failures), utility failures and large-
of corporate standards but is now operating with a new corpo- scale liquid pool fires. All of these scenarios affect multiple
rate standard in effect. systems of equipment and should be considered. The process
In these cases, a process designer should investigate any designer for each individual scenario looks at the underlying
deviations and document why these deviations are accept- scenario to ensure that it is credible. For example:
able. For cases where past designs do not meet the current • Is a large-scale liquid pool fire possible, and to what extent?
RAGAGEP standards, but the deviations are deemed to be mi- • Is a total utility failure possible, or does the utility feed all
nor, management at some facilities may choose to have more the listed equipment systems?
regulatory risks than safety risks. • Does one utility failure lead to another utility failure (e.g.,
Consideration of risk to make changes. Fixing issues loss of steam resulting in the loss of the turbine-driven instru-
with equipment design, especially when the facility is running ment air compressor)?
or even in turnaround, must be carried out with great care. In As previously stated, “conservative assumptions” for scenar-
the past three or four years of literature searches, the authors ios that are not controlling or that do not have concerns may be
44NOVEMBER 2012 | HydrocarbonProcessing.com
Since 1968
2012
Regular Washers improve Torque and Tension Accuracy
(ASME & TUV)

Find out what’s new in Washers at www.HYTORC.com/Washer


Select 160 at www.HydrocarbonProcessing.com/RS

acceptable. A plant engineer should review the scenario basis or detrimental effects is more muted. The following are some
for any global scenarios with concerns. Additionally, the “con- examples of “buried” assumptions typically used:
servative assumptions” associated with the sizing of the relief • Heat exchanger duty based on service overall heat trans-
device may not be consistent or even possible, given the spe- fer coefficient and area (UA) instead of the clean and new UA
cific global scenario being evaluated. • Level control valves hold level in process vessels
Credibility of the rates. Global overpressure scenarios are • Airfin coolers retain some fractional cooling capacity
often a compilation of relief rates specified as closely related • Operations personnel do not simultaneously open de-
individual relief device scenarios. While these scenarios may pressuring valves with utility failures unless directed to in op-
have been conservatively estimated and may have generated no erational procedures.
concerns, summing multiple systems with conservative rates The plant engineer and process designer should work with
may result in problems. personnel that operate the units, and they should review sce-
In a presentation to the 6th Global Congress on Process nario basis and loads for any global scenarios with concerns.
Safety, Dustin Smith reported on a refinery-wide review that Consistent assumptions. In the definition of global over-
resulted in a 40% reduction in the design relief rate by review- pressure scenarios and associated rates, the need to ensure con-
ing the specified relief loads and eliminating overly conserva- sistency is paramount. Many times, the process engineer will as-
tive assumptions.7 A plant engineer should ensure that the pro- sume for one equipment system that a pump was in operation
cess designer does not simply create a global scenario on the and has failed, while, in the next equipment system, the failure
basis of multiple conservative calculations; the designer must pump was spared and the alternative pump was in operation. For
also review the system to ensure that rates are reasonable and these analyses, consistency across the facility is required, as the
defensible (and not excessive due to assumptions). goal is to analyze the flare system (vs. the individual relief devic-
es). Some assumptions can result in system-wide inconsistencies:
Reasonable and consistent assumptions. As with the in- • When a pump is spared and used for multiple equipment
dividual relief systems analysis, the scenario assumptions and systems, the scenario should specify which pump has failed for
those used to generate the relief rates make a tremendous impact all systems
on the adequacy of the flare system and associated equipment. • The effects of the failures must be considered for systems
‘Buried’ assumptions. When sizing individual relief de- with heat integration
vices, RAGAGEP require that the process designer assumes • Utility failures that result in cascading losses must be ex-
that the worst case occurs and that all related failures, pump amined consistently.
lineups and control valve responses are either neutral or detri- The plant engineer should review the controlling global
mental. For global scenarios, the process designer must assume scenarios to ensure that the assumptions used are internally
that the global failure occurs, but the requirement for neutral consistent.
Hydrocarbon Processing | NOVEMBER 201245
Plant Safety and Environment

Advanced flare analysis techniques. API Standard 521 al- TAKEAWAY


lows for the consideration of positive action of instrumentation, When reviewing concerns generated from the relief system
operations or other favorable items, as long as the failure of these or flare design and documentation process, the plant engineer
items is considered.8 Prior to making costly flare system modi- must ensure that each concern is valid and that any resolution
fications, the plant engineer should review more complex flare requiring physical changes is a justified investment of a facil-
system analysis tools to ensure that modifications are justified. ity’s capital. To properly perform this task, it is recommended
Flare load probability analysis. In a presentation to the 6th that a plant engineer understand how a process designer per-
Global Congress on Process Safety, Dustin Smith reported on a forms the study and review the concerns prior to making physi-
method to estimate the flare loading probability.7 This method cal changes to the facility.
determines the likelihood of loads to the flare system,
and it can be used to target instrumented responses
and piping modifications. This method demonstrates By reviewing the concerns list, a plant
that analysis of the effects of safeguards and the proba-
bility of failure on demand (PFD) of these safeguards engineer can ensure that costly changes
can be used to develop the system loading as a func-
tion of probability/frequency. Using this information have a basis in sound engineering and
and given an acceptable time frame (e.g., 1 in 100,000
years), the expected flare load is lower than the worst-
that the expense is justified.
case scenario.
The authors recently reviewed a refinery where
the likelihood of a “worst-case” load, if a total power failure oc- When properly reviewed, upgrades to the flare and relief
curred, was approximately 1 in 100 million years. The design system from a relief systems analysis can improve the safety of
load for 1 in 100,000 years was a fraction of the total load, and an operating facility.
it was more consistent with the complexity of the plant, along
with the DCS programming and the safety instrumented func- LITERATURE CITED
1
Berwanger, P. C., R. A. Kreder and W. S. Lee, “Analysis Identifies Deficiencies in
tions and interlocks recently installed. Existing Pressure Relief Systems,” Process Safety Progress, Vol. 19, 2000.
Flare quantitative risk assessment. Flare quantitative risk 2
Smith, D. and J. White, “Ensuring safe operations when fulfilling action item
assessment is a way to review each scenario and the perturba- requirements,” Hydrocarbon Processing, March 15, 2010.
3
tions of these scenarios to determine the likelihood of vessel “Without Safeguards, Pressure Vessels Can Be Deadly,” US Chemical Safety
9 Board, Video, 2009.
overpressure as a function of frequency. This varies from the 4
Poje, G. V., A. K. Taylor and I. Rosenthal, “Catastrophic Vessel Overpressurization,”
flare loading probability in that the statistical analysis and hy- US Chemical Safety and Hazard Investigation Board, Report No. 1998-002-I-
draulic analysis are coupled; whereas, in the flare loading prob- 5
LA, 2000.
ability, the flare loading statistical analysis is separate from the D. D. Williamson & Co. Inc., “Catastrophic Vessel Failure,” US Chemical Safety
and Hazard Investigation Board, Report No. 2003-11-I-KY, 2004.
hydraulic analysis. In both cases, the plant engineer must en- 6
“The Goodyear Tire and Rubber Company,” US Chemical Safety and Hazard
sure that the scenario initiating event frequencies and the PFD Investigation Board, Report No. 2008-06-I-TX, 2011.
7
of safeguards are reasonable and defensible. Smith, D., “System Limited Flare Design: A Flare Load Mitigation Technique
(with a QRA Case Study),” 6th Global Conference on Process Safety, 2010.
Flare load dynamic simulations. Offering and requesting 8
ANSI/API Standard 521, “Pressure-Relieving and Depressuring Systems,”
dynamic flare system designs are becoming increasingly com- American Petroleum Institute, 2008.
mon. Like the other advanced flare analysis techniques, this one 9
Kreder, R. A. and P. C. Berwanger, “Quantitative Analysis—A Realistic Approach
increases the complexity of the analysis, thus requiring the facility to Relief Header and Flare System Analysis,” 2005.
10
Chen, F. F. K., R. A. Jentz and D. G. Williams, “Flare System Design: A Case for
to increase its understanding of the effects of assumptions on the Dynamic Simulation,” Offshore Technology Conference, Houston, May 1992.
final answer.10 The basic premise of dynamic simulation is that, by 11
Burgess, J., “Flare Header Debottlenecking,” Design Institute for Emergency
combining the effects of the staged timing of releases and the dy- Relief Systems, Spring Meeting, 2006.
namic pressurization of the flare system, the peak loads and back
DUSTIN SMITH, PE, is the co-founder and principal consultant of
pressures on system components are reduced. In this method, the Smith & Burgess LLC, a process safety consulting firm based in
plant engineer must ensure that the fundamental assumptions af- Houston, Texas. As a consultant, Mr. Smith has extensive
fecting the timing of each system or release are reasonable and experience with helping refineries and petrochemical facilities
defensible, thereby ensuring that the system is properly modeled. maintain compliance with the PSM standard. He has more than a
decade of experience in relief systems design and PSM
Other techniques. Other methods to analyze flare systems are compliance. His experience includes both domestic and
proprietary to operating companies. All of these methods are de- international projects. Mr. Smith is a chemical engineering graduate of Texas A&M
signed to account for the probability that either operator interven- University and a licensed professional engineer in Texas.
tion or instrumentation will operate, or fail to operate, as desired.
JOHN BURGESS, PE, is the co-founder and principal consultant
Any method of flare header analysis that is not a worst-case of Smith & Burgess LLC, a process safety consulting firm based
analysis must, therefore, establish some reasonable means of ac- in Houston, Texas. Mr. Burgess is a consultant who specializes in
counting for the positive action of instrumentation or operator helping refineries and petrochemical plants meet the PSM
intervention to mitigate the worst-case load. The delicate bal- standard. His experience includes more than 10 years in relief
systems and PSM compliance, for both domestic and
ance between realism and conservativism in flare header design international projects. Mr. Burgess has BS and MS degrees in
is paramount in creating a safely designed flare header at a rea- chemical engineering from both Texas Tech University and the University of
sonable cost.11 Missouri, and he is a licensed professional engineer in Texas.

46NOVEMBER 2012 | HydrocarbonProcessing.com

You might also like