You are on page 1of 4

Microsoft Project 2003 – Planning Resources

5. Enter an initial for the resource in the 6. Type as a percentage, the number of units
Working with Resources Resource Initial column (optional). of this resource that you want to assign to
the task.
Resources are the people, equipment and 6. Enter a category to classify the resource
materials that are used to perform the project (eg, Internal, External, Contractor) in the 7. Type a closing square bracket ( ] ).
tasks. In Project, you can add resources, assign Group column (optional).
8. Press Enter.
them to tasks, add cost and scheduling
7. Enter the availability of the resource in the
information for the resources, and then monitor
Max. Units column. Project uses this figure Tip: To enter multiple resources by this method, type a
the work and the costs of each resource.
to determine the maximum amount of work comma to separate them.
There are two types of resources, work that a resource can do in a day. It will then Toolbar Button:
resources and material resources. A work give you a warning if you plan too much
work for (over-allocate) a resource. 1. Select on the Gantt chart table, the task that
resource is a person/skill or piece of equipment
5. Select the name of the resource. you want to resource.
that uses effort to complete a task. A material
In the case of individual resources (Tom,
resource is a supply or other consumable item 6. Click into the Units column. 2. Click the Assign Resources button on the
Kate, Jo), it is advisable to keep this figure
used to complete a task. Work resources affect
at 100%. In the case of groups of resources 7. Enter as a percentage, the number of units
the scheduling of tasks (ie. get the work done Standard toolbar .
(eg. Consultant, IT Team, Typist), multiply of this resource that you want to assign to
more quickly) whereas material resources do not.
the number of resources by 100. For the task. 3. In this dialog box, click in the Units column
example if you have a group of 6 of the resource that you want to assign to
Creating a Basic Resource List consultants working on the project, enter a Project uses this figure to calculate how the task.
Max. Unit of 600%. Project will then much effort (manhours) the resource needs
Resources are created in the Resource Sheet 4. Enter as a percentage, the number of units
calculate that the Consultant resource can to work on the task. For example, if you
View, which displays resource information in a of this resource that you want to assign to
do 6 x 8 hours work/day (48hrs). assign 100% units of Tom to a task, Project
table format. In this view, each column the task.
will calculate that Tom is required to work
represents a different field in which you can enter Max. Units are not entered for material on the task 100% of his time. If, therefore,
data and each row represents a different resources. Project assumes an infinite Tom works an 8hr day and Tom is assigned
resource entry. supply of these!! to a 5-day task, Project will calculate that
Entries into other columns of the Resource Sheet Tom needs to perform 5 x 8 hours (40
will be covered later in this guide. manhours) work on the task.
8. If necessary, repeat steps 4 - 7 above in
Assigning Resources to Tasks other rows of the Resource Name/Units
columns, to assign more resources to the
This can be done in a variety of ways. Three of tasks.
the more popular methods are given below:
9. Click OK when finished.
Task Information Dialog Box:
Although the most time-consuming, this is the Resource Name column:
To create a pool of resources to use on your preferred method because it offers the most 1. In the Gantt Chart View, drag the split bar
project. control over how the data is entered and makes it between the table and the chart across to 5. Click Assign.
1. Click View, Resource Sheet. easier to add multiple resources. the right to reveal the Resource Name
column. 6. Repeat steps 2 - 4 above to assign more
2. Enter a name for the resource in the first 1. Double-click the name of the task that you resources to your plan.
row of the Resource Name column. This want to assign resources to. 2. Click into the resource name
can be an individual person (eg. Tom, Kate, cell for the task that you want Tip: The Assign Resources dialog box does NOT have to
2. Click the Resources tab. to assign a resource to. be closed each time a resource is assigned. Keep it open
Jo) or a generic name for a group of
resource (eg. Consultant, IT Team, Typist). 3. Click into the first row of the Resource for as long as you need to use it.
3. Click the down-arrow at the
Name column. right of the cell. Tip: Use the Ctrl key to select multiple tasks or resources
3. Specify whether the resource is Work to assign simultaneously.
(contributes effort to getting the work done) 4. Click the drop-down list. 4. Select the name of the resource from list.
or Material (supplies or components) in the Scheduling Resource Assignments
Type column. NB In order for this list to be populated, you must have set
up the resource sheet first. Microsoft Project uses Effort Driven Scheduling.
4. If the resource type is material, enter the This means that when you change the resource
5. Type an opening square bracket ( [ ).
unit that the material is used (eg. Tons, units assigned to a task, Project has to keep the
Boxes, Each) in the Material Label column. amount of work fixed and therefore changes the
duration of the task.

1
Microsoft Project 2003 – Planning Resources
If, for example, you initially assigned 100% of the 2. Click into the resource name cell for the 2. Click the option button. Five different combinations can be set by making
Tom resource (who works an 8-hour day) to a 5- task for which you want to modify the changes to the Task Type list and the Effort
day task, Project calculated that the task requires resources. 3. Select a different option from the list for how Driven check box. The behaviour of each is
8 x 5 hours work (40 manhours). If you then you wish the task to be re-scheduled. outside the scope of this guide, but by clicking
assign 100% units of a second resource to the 3. Click into the Entry Bar the Help button at the bottom left of the
same task, Project has to keep the work at 40 Advanced tab, useful explanations and
hours but in order to do that, has to reduce the information about the options available can be
duration of the task to 2.5 days. To put it more . accessed.
simply, Project works of the premise that two
4. Make changes as necessary. Tip: Set all your tasks to Fixed Duration, not Effort Driven
people can do the same amount of work as one NB The indicator and option button will disappear as soon
BEFORE starting to enter them in your project plan by
person in half the time. 5. Press Enter on the keyboard (or click the as you make other changes to the plan, so it must be used
clicking Tools, Options..., Schedule tab. Select Fixed
as soon as possible.
The formula used for this calculation is: blue tick ). Duration in the Default task type: box and uncheck the
Method B - Override with a Manual Change New tasks are effort driven: box.
Work = Duration x Units Toolbar Button:
1. Select on the Gantt chart table, the task that If you make a change to the assigned units for a Identifying Resource Overallocations
If a change is made to the units of that formula, task and Project re-calculates the duration,
Project keeps the work fixed and changes the you want to modify the resource(s) for.
simply click into the duration column for the task Overallocation occurs when you assign more
duration. 2. Click the Assign Resources button on the that has been affected and type the duration work to a resource than he/she/it can do in one
back to whatever you wish it to be. day.
For further information and explanation of this
Standard toolbar .
and other scheduling issues, search for “About Method C - Changing the Task Type Project will not stop or warn you that resources
effort-driven scheduling” in Microsoft Project 3. Select in this dialog box, the name of the are over-allocated, but will instead just highlight
The manner in which the Work = Duration x
Help. resource that you want to modify (it will them in red on the Resource Sheet.
Units calculation behaves, can be permanently
have a check mark at the changes for individual tasks by changing the task
Modifying Resource Assignments type.
left).
Once you have assigned resources to tasks, you 4. To remove the resource, click the Remove A popular setting for this that will always allow
may have to make changes. This can be done in the duration of the task to remain unchanged
a variety of ways. Three of the more popular button.
when the units assigned to it are modified, is to The simplest way of answering the question:
methods are given below: 5. To replace the resource with a different make it Fixed Duration and not Effort Driven. “Why, where and when are my resources
Task Information Dialog Box: one, click, the Replace... button. 1. Double-click the task for which you want to overallocated,” is by using the Resource Usage
change the task type. view. This is the closest that Project can get to
1. Double-click the name of the task for which 6. To modify the units for a resource, click in showing you a timesheet. The view breaks down
you want to modify the resources. the Units column for the resource that you 2. Click the Advanced tab. the work being done for each resource on a day-
2. Click the Resources tab. want to modify and type or spin to a by-day basis.
different percentage of units. 3. Click the Task Type: drop-down list.
3. Add additional resources and their 1. Click the View menu.
4. Select Fixed Duration.
respective units to the next available row in Changing the Scheduling Method
2. Select Resource Usage.
the table. 5. Click the Effort Driven: box to remove the
As described earlier in this guide, by default, check mark. 3. Observe the overallocated resources (they
4. Remove existing resources by clicking onto Microsoft Project uses effort-driven scheduling. will be in red).
the name of the resource that you want to This can, however, be changed so that when an 6. Click OK.
remove and pressing Delete on the edit is made to the assigned units of a tasks,
keyboard. Project carries out a different calculation to the
5. Replace existing resources and units by Work = Duration x Units formula.
clicking into the appropriate cell of the table This can be achieved in three ways:
and typing, selecting from the drop-down list
or clicking the spin button. Method A - Option Button
6. Click OK when finished. When a change is made to either the units
assigned, or the duration of a task, a green
Resource Name column: “indicator” appears in the top left-hand corner of
1. In the Gantt Chart View, drag the split bar the cell .
between the table and the chart across to
1. Point at the cell and an option button will
the right to reveal the Resource Name
column. appear at the left .

2
Microsoft Project 2003 – Planning Resources
4. Scroll the “timesheet” until you get to where Tip: You can view graphs for other resources by clicking the Project provides a variety of views so that you
the figures show in red. This will indicate on horizontal scroll bar at the bottom left of the resource graph can see and print out cost information.
which days the overallocation(s) occur. view or pressing the up/down arrow keys on the keyboard.
Entering Resource Cost Information
5. Note the date of the overallocation(s) by Resolving Overallocations
reading the timescale at the top of the In order for Project to calculate resource costs:
“timesheet.”. Once an overallocation is identified, it must be
decided what to do about it. As mentioned, 1. Click the View menu.
6. Note what the total hours assigned to the previously, Microsoft Project does not stop you
resource on that day are. working normally with the software even if 2. Click Resource Sheet.
7. Note which tasks are causing the problem. overallocations exist. Some possible solutions, 3. In the Resource Name column, select the
It’s usually because the resource has been however, are: resource that you want to apply a cost to.
assigned too many tasks at the same time. 1. Do nothing. If the overallocations are few or 4. In the Std. Rate column, type the resource
Another useful view when identifying and very small, they will normally balance rates. Press TAB to move to these fields if
analysing overallocations is the Resource themselves out when it comes to 8. Click the Level Now... button. they are not visible.
Graph. This shows a stacked column chart for implementing the project.
each resource, plotted against a timescale. To see which tasks have been delayed or split 5. In the Ovt. Rate column, enter an overtime
2. Increase the Max. Units for the and to ascertain how the project has been cost for the resource.
overallocated resource(s). The Resource affected by the levelling, use the Leveling Gannt
Graph will show how many you need on any View. 6. In the Cost/Use column, enter a fixed
particular day. amount that is chargeable whenever the
9. Click the View menu. resource works on a task. This would be
3. If the overallocation is being caused by a used in cases where there is a one-off ”call
resource being assigned to too many 10. Select More Views.... out fee” or agency charge applicable.
simultaneous tasks, replace the resource
on some of the tasks with underallocated 11. Select Leveling Gantt. 7. In the Accrue At column, enter how the
ones. 12. Click Apply. cost of the resource is incurred (this is
required for cashflow analysis). Use:
4. Change the dependencies of the tasks The Leveling Gantt show two bars for each task,
causing the overallocation so that they don’t one green and the other black. The green bars a) Start – if the full cost for the resource
conflict. This will invariably delay the project shows where the tasks were scheduled before is incurred as soon as the resource
but that is a price you may have to pay for leveling. The black bars show where the tasks starts work on a task (“cash up front”).
ensuring that the work is carried out have been re-scheduled to after leveling.
On days when the column is blue, there is no effectively and in a quality manner. b) Prorated – if the cost of the resource
problem with overallocations. On days when the Leveling is too detailed a subject to be covered is spread on a day-by-day basis over
column has a red section in it, there is a problem. 5. Use Microsoft Project’s “Leveling” feature. fully in this brief guide. For further information the total duration of the tasks that the
(see below). and explanations, search for “About resource resource works on.
1. On the Resource Sheet or Resource Usage leveling” in Microsoft Project Help.
View, click the name of the resource for Levelling a Project c) End – if the cost of the resource is
which you want to see the Resource Graph. incurred as soon as the resource ends
You can use the Project’s leveling feature to Working with Costs work on a task.
2. Click View. alleviate resource overallocations. Leveling re-
schedules by adding delay to tasks and/or by You can get Project to calculate out some basic
3. Click Resources Graph.
splitting tasks until the resources assigned to costs for the tasks and resources of your project
By reading the height of the various column these tasks are no longer overloaded. Because by four methods:
sections, you can ascertain: If you want to enter more than one standard rate
of these changes to the tasks, leveling can
a) Getting it to multiply the amount of and overtime rate for each resource (if for
extend the project's finish date. When leveling, work being done by each resource by
a) Total height of column - How many instance there is a pay rise in the offing):
Project does not change who is assigned to
units of the resource you need on a their rate of pay.
tasks and only work resources (people and 1. Double-click the resource name for the
particular day.
equipment) are leveled, not material resources. b) Using a fixed, “Cost per Use” for each resource that you want to enter more rates
b) Blue section of column - How many resource. for.
To carry out simple levelling:
units of the resource you have
c) Entering a “Fixed Cost” for each task 2. Click the Costs tab.
available on a particular day. 6. Click the Tools menu.
to cover things such as overheads and
c) Red section of column - How many materials. 3. Click the A (Default) tab in the Cost rate
7. Select Level Resources....
units you are overallocated by on a tables section.
d) A combination of all the above.
particular day.

3
Microsoft Project 2003 – Planning Resources
4. In the Standard Rate and Overtime Rate In both of the above cases, re-apply the Entry To view on the Gantt Chart the non-working
columns, type the resource rates. table to view general (default) information about Working with Resource times for a particular resource:
your tasks and resources. Calendars 1. Click Format.
5. In the next row, type for each column a
value or percentage change from the To view the total costs for the project:
previous rate.
When starting a new project, you would normally 2. Select Timescale….
1. Click Project. set up a standard, project calendar. This
6. In the Effective Date column, enter the date determines the default working days and times 3. Click the Non-working time tab
the rate change takes effect. 2. Click Project Information…. for the majority of tasks and resources (See the
4. Select the resource name from the
3. Click the Statistics… button in the bottom Project 2003 – Task Planning Quick Reference Calendar: list.
Guide).
left.
5. Click OK.
When you create resources for your project,
Project assumes that the resources will work the Vertical bands will appear on the Gantt Chart
same days and times as shown in the standard, “greying out” the resource’s non-working days.
project calendar. It therefore assigns a copy of
this calendar to the resource. TIP: Reset the timescale to display non-working times for
the Standard calendar when finished.
If, however, the resource works to different days
and times, the resource’s calendar needs to be
edited so that Project schedules the resource’s
4. Observe the Cost section of the window. work into the correct days and times when they
5. Click Close when finished. are available to do it.
7. To enter additional sets of pay rates for the To edit a resource calendar:
resource, click the B tab, and then repeat Entering Task Fixed Cost Information
steps 7-9. 1. Click View.
In addition to, or as an alternative to, resource-
Viewing Cost Information 2. Select Resource Sheet.
based costs, you can enter a single cost for each
task. 3. Double-click the name of the resource
To view the calculated resource costs of the whose calendar you wish to edit.
project: 1. Click View.
4. Click the Working Time tab.
1. Click View. 2. Select Gantt Chart.

2. Select Resource Sheet. 3. Click View again.

3. Click View again. 4. Select Table: Entry .

4. Select Table: Entry . 5. Select Cost from the side menu.

5. Select Cost from the side menu. 6. Click into the Fixed Cost column for the
task that you want to add the cost to.
6. Observe the second column of the table
(Cost). This shows the total project cost of 7. Type the cost.
each resource.
8. Click in the Fixed Cost Accrual column.
To view the calculated task costs of the project: 5. Make changes in the same manner as you
9. Select Start, Prorated or End, depending on would for the standard project calendar, ie.
1. Click View. how you want the cost incurred for cash enter non-working days, make non-working
flow purposes. day into working days, etc. (See the Project
2. Select Gantt Chart. 2003 – Task Planning Quick Reference
View the total cost for each task in the fourth
3. Click View again. Guide).
column of the Cost table.
4. Select Table: Entry . 6. Click OK.
As with most resourcing topics, costs can be a
5. Select Cost from the side menu.
complex and diverse subject. For further TIP: As a shortcut, you can access a resource calendar
information and explanations, search for “Costs” from the Gantt Chart view by clicking Tools, Change
6. Observe the fourth column of the table in Microsoft Project Help. Working Time… and selecting the resource name from the
(Total Cost). This shows the total project For: list at the top of the dialog box.
cost of each task.

You might also like