RA INTERNATIONAL

Snag List

CONTRACT UNICEF OFFICE AND CONFERENCE CENTRE CONTRACT No LLTS-42409323


SNAG LIST
CLIENT UNICEF, MIA GREEN ZONE, SOMALIA Fire System-01 (Intermediate)
REFERENCE No
STRUCTURE / SECTION GROUND & FIRST FLOOR- FIRE SPRINKLER / SYSTEM DATE 08-10-2020

The items listed below are either incomplete or unacceptable and corrective action are to be implemented not later than the date indicated, prior to closing out of this SNAG LIST.
NCRs are to be completed for serious/ major nonconformities and the system followed.

TARGET ACTUAL
DESCRIPTION COMPLETION COMPLETION SIGNATURE SIGNATURE
ITEM
DATE DATE RA CIENT
01 Buffer Zone – Ground Floor
200 mm Line – Tie rod diameter is wrong – should be 12.7 mm ( Installed 10 mm)
63 mm Line – Tie rod diameter is wrong – should be 9.5 mm ( Installed 8 mm)

02 Pump Room
63 mm Line – Tie rod diameter wrong – Should be 9.5 mm ( Installed 8 mm)

03 General
Penetrations through walls required to be sealed.

First floor -opened ceiling boards, none of the above deviations found. Testing for, and commissioning still to
Note
be done
The above works are completed and are ready for final inspection prior to handover/close out.
SNAG LIST PREPARED BY:
NAME DESIGNATION SIGNATURE DATE:
For RA International
For Client

RA-QMS-PMC-FOR-009 Rev 0 – Snag List [Feb 2020]


Page 1 of 2