Snag List
The items listed below are either incomplete or unacceptable and corrective action are to be implemented not later than the date indicated, prior to closing out of this SNAG LIST.
NCRs are to be completed for serious/ major nonconformities and the system followed.
TARGET ACTUAL
DESCRIPTION COMPLETION COMPLETION SIGNATURE SIGNATURE
ITEM
DATE DATE RA CIENT
01 Buffer Zone – Ground Floor
200 mm Line – Tie rod diameter is wrong – should be 12.7 mm ( Installed 10 mm)
63 mm Line – Tie rod diameter is wrong – should be 9.5 mm ( Installed 8 mm)
02 Pump Room
63 mm Line – Tie rod diameter wrong – Should be 9.5 mm ( Installed 8 mm)
03 General
Penetrations through walls required to be sealed.
First floor -opened ceiling boards, none of the above deviations found. Testing for, and commissioning still to
Note
be done
The above works are completed and are ready for final inspection prior to handover/close out.
SNAG LIST PREPARED BY:
NAME DESIGNATION SIGNATURE DATE:
For RA International
For Client