H.K. AL SADIQ SONS CONTRACTING CO.LTD.

RE-BOILER SHUTDOWN BASELINE SCHEDULE


Activity ID Activity Name Original Activity % BL Project Start BL Project Finis h Budgeted Max % Planned % Earned % Variance Schedule Start Finish 2018
Duration Complete Labor Wtg Wtg Wtg % Wt. Performance Index Sep 30 Oct 07 Oct 14 Oct 21
Units M T W T Fri S S M T W T Fri S S M T W T F S S M T
SP - 151100502 - RE-BOILER 26E50 A/B/C 378h 05-Oct-18 06:00 AM 22-Oct-18 10:00 AM 15673 100.00 0.00 0.00 0.00 0.00 05-O ct-18 06:00 AM 22-Oct- 18 10 :00 AM

SHUTDOWN WORKS 378h 05-Oct-18 06:00 AM 22-Oct-18 10:00 AM 15673 100.00 0.00 0.00 0.00 0.00 05-O ct-18 06:00 AM 22-Oct- 18 10 :00 AM

RE-BOILER 26E50 A 220h 05-Oct-18 06:00 AM 15-Oct-18 06:00 AM 4958 31.63 0.00 0.00 0.00 0.00 05-O ct-18 06:00 AM 15-Oct- 18 06 :00 AM
RE-BOILER REPLACEMENT 163h 05-Oct-18 06:00 AM 12-Oct-18 04:00 PM 2426 15.48 0.00 0.00 0.00 0.00 05-O ct-18 06:00 AM 12-Oct- 18 04 :00 PM
SD-RB-A-120 HKSS Obtain permit & Mobilize Logistics (500TN Crane) 6h 0% 05-Oct-18 06:00 AM 05-Oct-18 12:00 PM 20 0.13 0.00 0.00 0.00 0.00 05-O ct-18 06:00 AM 05-Oct- 18 12 :00 PM
SD-RB-A-130 Disconnection of Inlet and Outlet Flannges & Spools 6h 0% 05-Oct-18 01:00 PM 05-Oct-18 07:00 PM 51 0.33 0.00 0.00 0.00 0.00 05-O ct-18 01:00 PM 05-Oct- 18 07 :00 PM
SD-RB-A-131 Disconnection & Removal of existing pipe spools & channel covers 6h 0% 05-Oct-18 07:00 PM 06-Oct-18 02:00 AM 51 0.33 0.00 0.00 0.00 0.00 05-O ct-18 07:00 PM 06-Oct- 18 02 :00 AM
SD-RB-A-140 Shifting of 10" Steam Inlet Spool to HKSS yard for modification 2h 0% 06-Oct-18 02:00 AM 06-Oct-18 04:00 AM 76 0.48 0.00 0.00 0.00 0.00 06-O ct-18 02:00 AM 06-Oct- 18 04 :00 AM
SD-RB-A-132 Dismantling and Removal of Existing 26E50A 10h 0% 06-Oct-18 02:00 AM 06-Oct-18 12:00 PM 253 1.61 0.00 0.00 0.00 0.00 06-O ct-18 02:00 AM 06-Oct- 18 12 :00 PM
SD-RB-A-150 Modification of Existing 10" Steam Inlet Spool at Yard as per package 33h 0% 06-Oct-18 04:00 AM 07-Oct-18 04:00 PM 177 1.13 0.00 0.00 0.00 0.00 06-O ct-18 04:00 AM 07-Oct- 18 04 :00 PM
SD-RB-A-160 Lifting of Existing 26E50A and Load on trailer to shift to the yard (Tandem Lifting Required) 6h 0% 06-Oct-18 01:00 PM 06-Oct-18 07:00 PM 506 3.23 0.00 0.00 0.00 0.00 06-O ct-18 01:00 PM 06-Oct- 18 07 :00 PM
SD-RB-A-170 Surveying field preparation, new spr ing supports installation, leveling & clear site for new re-boiler in stallation
8h 0% 06-Oct-18 01:00 PM 06-Oct-18 09:00 PM 76 0.48 0.00 0.00 0.00 0.00 06-O ct-18 01:00 PM 06-Oct- 18 09 :00 PM
SD-RB-A-180 Shifting and off-lo ading of new re-boiler 26E50A to the site 10h 0% 06-Oct-18 07:00 PM 07-Oct-18 06:00 AM 127 0.81 0.00 0.00 0.00 0.00 06-O ct-18 07:00 PM 07-Oct- 18 06 :00 AM
SD-RB-A-190 Rigging & Lifting of new Re-Boiler as per approved lifting plan (Tandem Lifting Required) 5h 0% 07-Oct-18 06:00 AM 07-Oct-18 11:00 AM 506 3.23 0.00 0.00 0.00 0.00 07-O ct-18 06:00 AM 07-Oct- 18 11 :00 AM
SD-RB-A-191 Perform Required NDT on 10" Inlet Steam Spool after repair work 4h 0% 07-Oct-18 04:00 PM 07-Oct-18 08:00 PM 51 0.33 0.00 0.00 0.00 0.00 07-O ct-18 04:00 PM 07-Oct- 18 08 :00 PM
SD-RB-A-192 Shifting of 10" Steam Inlet Spool back to site for Installation 3h 0% 07-Oct-18 08:00 PM 08-Oct-18 12:00 AM 76 0.48 0.00 0.00 0.00 0.00 07-O ct-18 08:00 PM 08-Oct- 18 12 :00 AM
SD-RB-A-193 Perform Verticality/Alignment Check (Leveling) of the re-boiler 11h 0% 11-Oct-18 09:00 AM 11-Oct-18 09:00 PM 127 0.81 0.00 0.00 0.00 0.00 11-O ct-18 09:00 AM 11-Oct- 18 09 :00 PM
SD-RB-A-195 Flange alignment and g asket installa tion 5h 0% 11-Oct-18 09:00 PM 12-Oct-18 03:00 AM 177 1.13 0.00 0.00 0.00 0.00 11-O ct-18 09:00 PM 12-Oct- 18 03 :00 AM
SD-RB-A-200 Bolt tightening & bolt torquing 6h 0% 12-Oct-18 03:00 AM 12-Oct-18 09:00 AM 127 0.81 0.00 0.00 0.00 0.00 12-O ct-18 03:00 AM 12-Oct- 18 09 :00 AM
SD-RB-A-210 Carryout Inspection for Exchanger / Re-Boiler 6h 0% 12-Oct-18 09:00 AM 12-Oct-18 04:00 PM 25 0.16 0.00 0.00 0.00 0.00 12-O ct-18 09:00 AM 12-Oct- 18 04 :00 PM
INSULATION & PIPE LINE MODIFICATION 171h 07-Oct-18 11:00 AM 15-Oct-18 06:00 AM 2532 16.16 0.00 0.00 0.00 0.00 07-O ct-18 11:00 AM 15-Oct- 18 06 :00 AM
PS-OF-130 Scaffolding Erection at Re-Boiler 26E50 A 10h 0% 07-Oct-18 11:00 AM 07-Oct-18 10:00 PM 127 0.81 0.00 0.00 0.00 0.00 07-O ct-18 11:00 AM 07-Oct- 18 10 :00 PM
PS-OF-140 Perform Insulation & Cladding at Re-Boiler 26E50 A (Partial 80%) 33h 0% 07-Oct-18 11:00 PM 09-Oct-18 10:00 AM 582 3.71 0.00 0.00 0.00 0.00 07-O ct-18 11:00 PM 09-Oct- 18 10 :00 AM
SD-RB-A-220 Lifting & Cutting of 10" Piping Spool for 1 Field Joint, to suit new nozzle elevation 9h 0% 12-Oct-18 04:00 PM 13-Oct-18 02:00 AM 253 1.61 0.00 0.00 0.00 0.00 12-O ct-18 04:00 PM 13-Oct- 18 02 :00 AM
SD-RB-A-240 Cutting of Pipeline 5h 0% 13-Oct-18 02:00 AM 13-Oct-18 07:00 AM 127 0.81 0.00 0.00 0.00 0.00 13-O ct-18 02:00 AM 13-Oct- 18 07 :00 AM
SD-RB-A-250 Beveling of Pipeline 5h 0% 13-Oct-18 02:00 AM 13-Oct-18 07:00 AM 127 0.81 0.00 0.00 0.00 0.00 13-O ct-18 02:00 AM 13-Oct- 18 07 :00 AM
SD-RB-A-260 Fit-up of Pipeline 6h 0% 13-Oct-18 07:00 AM 13-Oct-18 02:00 PM 253 1.61 0.00 0.00 0.00 0.00 13-O ct-18 07:00 AM 13-Oct- 18 02 :00 PM
SD-RB-A-271 Welding of Pipeline 6h 0% 13-Oct-18 02:00 PM 13-Oct-18 08:00 PM 506 3.23 0.00 0.00 0.00 0.00 13-O ct-18 02:00 PM 13-Oct- 18 08 :00 PM
SD-RB-A-280 NDT/RT of Pipeline 3h 0% 13-Oct-18 08:00 PM 14-Oct-18 12:00 AM 127 0.81 0.00 0.00 0.00 0.00 13-O ct-18 08:00 PM 14-Oct- 18 12 :00 AM
SD-RB-A-281 Inspection of Pipeline 1h 0% 14-Oct-18 12:00 AM 14-Oct-18 01:00 AM 25 0.16 0.00 0.00 0.00 0.00 14-O ct-18 12:00 AM 14-Oct- 18 01 :00 AM
SD-RB-A-290 Remaining Insulation 22h 0% 14-Oct-18 01:00 AM 15-Oct-18 01:00 AM 380 2.42 0.00 0.00 0.00 0.00 14-O ct-18 01:00 AM 15-Oct- 18 01 :00 AM
SD-RB-A-291 Final Inspection for Insulation 5h 0% 15-Oct-18 01:00 AM 15-Oct-18 06:00 AM 25 0.16 0.00 0.00 0.00 0.00 15-O ct-18 01:00 AM 15-Oct- 18 06 :00 AM
RE-BOILER 26E50 B 277h 05-Oct-18 06:00 AM 17-Oct-18 08:00 PM 4958 31.63 0.00 0.00 0.00 0.00 05-O ct-18 06:00 AM 17-Oct- 18 08 :00 PM
RE-BOILER REPLACEMENT 220h 05-Oct-18 06:00 AM 15-Oct-18 06:00 AM 2426 15.48 0.00 0.00 0.00 0.00 05-O ct-18 06:00 AM 15-Oct- 18 06 :00 AM
SD-RB-B-120 HKSS Obtain permit & Mobilize Logistics (500TN Crane) 16h 0% 05-Oct-18 06:00 AM 06-Oct-18 12:00 AM 20 0.13 0.00 0.00 0.00 0.00 05-O ct-18 06:00 AM 06-Oct- 18 12 :00 AM
SD-RB-B-130 Disconnection of Inlet and Outlet Flannges & Spools 6h 0% 07-Oct-18 11:00 AM 07-Oct-18 06:00 PM 51 0.33 0.00 0.00 0.00 0.00 07-O ct-18 11:00 AM 07-Oct- 18 06 :00 PM
SD-RB-B-131 Disconnection & Removal of existing pipe spools & channel covers 6h 0% 07-Oct-18 06:00 PM 08-Oct-18 01:00 AM 51 0.33 0.00 0.00 0.00 0.00 07-O ct-18 06:00 PM 08-Oct- 18 01 :00 AM
SD-RB-B-140 Shifting of 10" Steam Inlet Spool to HKSS yard for modification 2h 0% 08-Oct-18 01:00 AM 08-Oct-18 03:00 AM 76 0.48 0.00 0.00 0.00 0.00 08-O ct-18 01:00 AM 08-Oct- 18 03 :00 AM
SD-RB-B-132 Dismantling and Removal of Existing 26E50A 10h 0% 08-Oct-18 01:00 AM 08-Oct-18 11:00 AM 253 1.61 0.00 0.00 0.00 0.00 08-O ct-18 01:00 AM 08-Oct- 18 11 :00 AM
SD-RB-B-150 Modification of Existing 10" Steam Inlet Spool at Yard as per package 33h 0% 08-Oct-18 03:00 AM 09-Oct-18 03:00 PM 177 1.13 0.00 0.00 0.00 0.00 08-O ct-18 03:00 AM 09-Oct- 18 03 :00 PM
SD-RB-B-160 Lifting of Existing 26E50A and Load on trailer to shift to the yard (Tandem Lifting Required) 6h 0% 08-Oct-18 11:00 AM 08-Oct-18 06:00 PM 506 3.23 0.00 0.00 0.00 0.00 08-O ct-18 11:00 AM 08-Oct- 18 06 :00 PM
SD-RB-B-170 Surveying field preparation, new spr ing supports installation, leveling & clear site for new re-boiler in stallation
8h 0% 08-Oct-18 11:00 AM 08-Oct-18 08:00 PM 76 0.48 0.00 0.00 0.00 0.00 08-O ct-18 11:00 AM 08-Oct- 18 08 :00 PM
SD-RB-B-180 Shifting and off-lo ading of new re-boiler 26E50A to the site 10h 0% 08-Oct-18 06:00 PM 09-Oct-18 05:00 AM 127 0.81 0.00 0.00 0.00 0.00 08-O ct-18 06:00 PM 09-Oct- 18 05 :00 AM
SD-RB-B-190 Rigging & Lifting of new Re-Boiler as per approved lifting plan (Tandem Lifting Required) 5h 0% 09-Oct-18 05:00 AM 09-Oct-18 10:00 AM 506 3.23 0.00 0.00 0.00 0.00 09-O ct-18 05:00 AM 09-Oct- 18 10 :00 AM
SD-RB-B-191 Perform Required NDT on 10" Inlet Steam Spool after repair work 4h 0% 09-Oct-18 03:00 PM 09-Oct-18 07:00 PM 51 0.33 0.00 0.00 0.00 0.00 09-O ct-18 03:00 PM 09-Oct- 18 07 :00 PM
SD-RB-B-192 Shifting of 10" Steam Inlet Spool back to site for Installation 3h 0% 09-Oct-18 07:00 PM 09-Oct-18 10:00 PM 76 0.48 0.00 0.00 0.00 0.00 09-O ct-18 07:00 PM 09-Oct- 18 10 :00 PM
SD-RB-B-193 Perform Verticality/Alignment Check (Leveling) of the re-boiler 11h 0% 14-Oct-18 12:00 AM 14-Oct-18 11:00 AM 127 0.81 0.00 0.00 0.00 0.00 14-O ct-18 12:00 AM 14-Oct- 18 11 :00 AM
SD-RB-B-195 Flange alignment and g asket installa tion 5h 0% 14-Oct-18 11:00 AM 14-Oct-18 05:00 PM 177 1.13 0.00 0.00 0.00 0.00 14-O ct-18 11:00 AM 14-Oct- 18 05 :00 PM
SD-RB-B-200 Bolt tightening & bolt torquing 6h 0% 14-Oct-18 05:00 PM 15-Oct-18 12:00 AM 127 0.81 0.00 0.00 0.00 0.00 14-O ct-18 05:00 PM 15-Oct- 18 12 :00 AM
SD-RB-B-210 Carryout Inspection for Exchanger / Re-Boiler 6h 0% 15-Oct-18 12:00 AM 15-Oct-18 06:00 AM 25 0.16 0.00 0.00 0.00 0.00 15-O ct-18 12:00 AM 15-Oct- 18 06 :00 AM
INSULATION & PIPE LINE MODIFICATION 185h 09-Oct-18 10:00 AM 17-Oct-18 08:00 PM 2532 16.16 0.00 0.00 0.00 0.00 09-O ct-18 10:00 AM 17-Oct- 18 08 :00 PM
PS-OF-150 Scaffolding Erection at Re-Boiler 26E50 B 10h 0% 09-Oct-18 10:00 AM 09-Oct-18 09:00 PM 127 0.81 0.00 0.00 0.00 0.00 09-O ct-18 10:00 AM 09-Oct- 18 09 :00 PM
PS-OF-160 Perform Insulation & Cladding at Re-Boiler 26E50 B (Partial 80%) 33h 0% 09-Oct-18 09:00 PM 11-Oct-18 09:00 AM 582 3.71 0.00 0.00 0.00 0.00 09-O ct-18 09:00 PM 11-Oct- 18 09 :00 AM
SD-RB-B-220 Lifting & Cutting of 10" Piping Spool for 1 Field Joint, to suit new nozzle elevation 9h 0% 15-Oct-18 06:00 AM 15-Oct-18 04:00 PM 253 1.61 0.00 0.00 0.00 0.00 15-O ct-18 06:00 AM 15-Oct- 18 04 :00 PM
SD-RB-B-240 Cutting of Pipeline 5h 0% 15-Oct-18 04:00 PM 15-Oct-18 09:00 PM 127 0.81 0.00 0.00 0.00 0.00 15-O ct-18 04:00 PM 15-Oct- 18 09 :00 PM
SD-RB-B-250 Beveling of Pipeline 5h 0% 15-Oct-18 04:00 PM 15-Oct-18 09:00 PM 127 0.81 0.00 0.00 0.00 0.00 15-O ct-18 04:00 PM 15-Oct- 18 09 :00 PM
SD-RB-B-260 Fit-up of Pipeline 6h 0% 15-Oct-18 09:00 PM 16-Oct-18 04:00 AM 253 1.61 0.00 0.00 0.00 0.00 15-O ct-18 09:00 PM 16-Oct- 18 04 :00 AM
SD-RB-B-271 Welding of Pipeline 6h 0% 16-Oct-18 04:00 AM 16-Oct-18 10:00 AM 506 3.23 0.00 0.00 0.00 0.00 16-O ct-18 04:00 AM 16-Oct- 18 10 :00 AM
SD-RB-B-280 NDT/RT of Pipeline 3h 0% 16-Oct-18 10:00 AM 16-Oct-18 02:00 PM 127 0.81 0.00 0.00 0.00 0.00 16-O ct-18 10:00 AM 16-Oct- 18 02 :00 PM
SD-RB-B-281 Inspection of Pipeline 1h 0% 16-Oct-18 02:00 PM 16-Oct-18 03:00 PM 25 0.16 0.00 0.00 0.00 0.00 16-O ct-18 02:00 PM 16-Oct- 18 03 :00 PM

Primary Baseline Critical Remaining Work Summary Proposed Baseline Schedule- Rev.
REPLACEMENT OF REBOILER 26E50 A/B/C
Date Revision Checked Approved
Actual Work Baseline Milestone SAUDI PETROCHEMICAL COMPANY - SALT PLANT - SADAF
14-May-18 12... Proposed Baseline Schedule- Rev.00 SS SA
Remaining Work Milestone Page 1 of 2
H.K. AL SADIQ SONS CONTRACTING CO.LTD.
RE-BOILER SHUTDOWN BASELINE SCHEDULE
Activity ID Activity Name Original Activity % BL Project Start BL Project Finis h Budgeted Max % Planned % Earned % Variance Schedule Start Finish 2018
Duration Complete Labor Wtg Wtg Wtg % Wt. Performance Index Sep 30 Oct 07 Oct 14 Oct 21
Units M T W T Fri S S M T W T Fri S S M T W T F S S M T
SD-RB-B-290 Remaining Insulation 22h 0% 16-Oct-18 03:00 PM 17-Oct-18 03:00 PM 380 2.42 0.00 0.00 0.00 0.00 16-O ct-18 03:00 PM 17-Oct- 18 03 :00 PM
SD-RB-B-291 Final Inspection for Insulation 5h 0% 17-Oct-18 03:00 PM 17-Oct-18 08:00 PM 25 0.16 0.00 0.00 0.00 0.00 17-O ct-18 03:00 PM 17-Oct- 18 08 :00 PM
RE-BOILER 26E50 C 334h 05-Oct-18 06:00 AM 20-Oct-18 10:00 AM 4958 31.63 0.00 0.00 0.00 0.00 05-O ct-18 06:00 AM 20-Oct- 18 10 :00 AM
RE-BOILER REPLACEMENT 277h 05-Oct-18 06:00 AM 17-Oct-18 08:00 PM 2426 15.48 0.00 0.00 0.00 0.00 05-O ct-18 06:00 AM 17-Oct- 18 08 :00 PM
SD-RB-C-120 HKSS Obtain permit & Mobilize Logistics (500TN Crane) 16h 0% 05-Oct-18 06:00 AM 06-Oct-18 12:00 AM 20 0.13 0.00 0.00 0.00 0.00 05-O ct-18 06:00 AM 06-Oct- 18 12 :00 AM
SD-RB-C-130 Disconnection of Inlet and Outlet Flannges & Spools 6h 0% 09-Oct-18 10:00 AM 09-Oct-18 05:00 PM 51 0.33 0.00 0.00 0.00 0.00 09-O ct-18 10:00 AM 09-Oct- 18 05 :00 PM
SD-RB-C-131 Disconnection & Removal of existing pipe spools & channel covers 6h 0% 09-Oct-18 05:00 PM 10-Oct-18 12:00 AM 51 0.33 0.00 0.00 0.00 0.00 09-O ct-18 05:00 PM 10-Oct- 18 12 :00 AM
SD-RB-C-140 Shifting of 10" Steam Inlet Spool to HKSS yard for modification 2h 0% 10-Oct-18 12:00 AM 10-Oct-18 02:00 AM 76 0.48 0.00 0.00 0.00 0.00 10-O ct-18 12:00 AM 10-Oct- 18 02 :00 AM
SD-RB-C-132 Dismantling and Removal of Existing 26E50A 10h 0% 10-Oct-18 12:00 AM 10-Oct-18 10:00 AM 253 1.61 0.00 0.00 0.00 0.00 10-O ct-18 12:00 AM 10-Oct- 18 10 :00 AM
SD-RB-C-150 Modification of Existing 10" Steam Inlet Spool at Yard as per package 33h 0% 10-Oct-18 02:00 AM 11-Oct-18 02:00 PM 177 1.13 0.00 0.00 0.00 0.00 10-O ct-18 02:00 AM 11-Oct- 18 02 :00 PM
SD-RB-C-160 Lifting of Existing 26E50A and Load on trailer to shift to the yard (Tandem Lifting Required) 6h 0% 10-Oct-18 10:00 AM 10-Oct-18 05:00 PM 506 3.23 0.00 0.00 0.00 0.00 10-O ct-18 10:00 AM 10-Oct- 18 05 :00 PM
SD-RB-C-170 Surveying field preparation, new spr ing supports installation, leveling & clear site for new re-boiler in stallation
8h 0% 10-Oct-18 10:00 AM 10-Oct-18 07:00 PM 76 0.48 0.00 0.00 0.00 0.00 10-O ct-18 10:00 AM 10-Oct- 18 07 :00 PM
SD-RB-C-180 Shifting and off-lo ading of new re-boiler 26E50A to the site 10h 0% 10-Oct-18 05:00 PM 11-Oct-18 04:00 AM 127 0.81 0.00 0.00 0.00 0.00 10-O ct-18 05:00 PM 11-Oct- 18 04 :00 AM
SD-RB-C-190 Rigging & Lifting of new Re-Boiler as per approved lifting plan (Tandem Lifting Required) 5h 0% 11-Oct-18 04:00 AM 11-Oct-18 09:00 AM 506 3.23 0.00 0.00 0.00 0.00 11-O ct-18 04:00 AM 11-Oct- 18 09 :00 AM
SD-RB-C-191 Perform Required NDT on 10" Inlet Steam Spool after repair work 4h 0% 11-Oct-18 02:00 PM 11-Oct-18 06:00 PM 51 0.33 0.00 0.00 0.00 0.00 11-O ct-18 02:00 PM 11-Oct- 18 06 :00 PM
SD-RB-C-192 Shifting of 10" Steam Inlet Spool back to site for Installation 3h 0% 11-Oct-18 06:00 PM 11-Oct-18 09:00 PM 76 0.48 0.00 0.00 0.00 0.00 11-O ct-18 06:00 PM 11-Oct- 18 09 :00 PM
SD-RB-C-193 Perform Verticality/Alignment Check (Leveling) of the re-boiler 11h 0% 16-Oct-18 02:00 PM 17-Oct-18 02:00 AM 127 0.81 0.00 0.00 0.00 0.00 16-O ct-18 02:00 PM 17-Oct- 18 02 :00 AM
SD-RB-C-195 Flange alignment and g asket installa tion 5h 0% 17-Oct-18 02:00 AM 17-Oct-18 07:00 AM 177 1.13 0.00 0.00 0.00 0.00 17-O ct-18 02:00 AM 17-Oct- 18 07 :00 AM
SD-RB-C-200 Bolt tightening & bolt torquing 6h 0% 17-Oct-18 07:00 AM 17-Oct-18 02:00 PM 127 0.81 0.00 0.00 0.00 0.00 17-O ct-18 07:00 AM 17-Oct- 18 02 :00 PM
SD-RB-C-210 Carryout Inspection for Exchanger / Re-Boiler 6h 0% 17-Oct-18 02:00 PM 17-Oct-18 08:00 PM 25 0.16 0.00 0.00 0.00 0.00 17-O ct-18 02:00 PM 17-Oct- 18 08 :00 PM
INSULATION & PIPE LINE MODIFICATION 199h 11-Oct-18 09:00 AM 20-Oct-18 10:00 AM 2532 16.16 0.00 0.00 0.00 0.00 11-O ct-18 09:00 AM 20-Oct- 18 10 :00 AM
PS-OF-170 Scaffolding Erection at Re-Boiler 26E50 C 10h 0% 11-Oct-18 09:00 AM 11-Oct-18 08:00 PM 127 0.81 0.00 0.00 0.00 0.00 11-O ct-18 09:00 AM 11-Oct- 18 08 :00 PM
PS-OF-180 Perform Insulation & Cladding at Re-Boiler 26E50 C (Partial 80%) 33h 0% 11-Oct-18 08:00 PM 13-Oct-18 08:00 AM 582 3.71 0.00 0.00 0.00 0.00 11-O ct-18 08:00 PM 13-Oct- 18 08 :00 AM
SD-RB-C-220 Lifting & Cutting of 10" Piping Spool for 1 Field Joint, to suit new nozzle elevation 9h 0% 17-Oct-18 08:00 PM 18-Oct-18 06:00 AM 253 1.61 0.00 0.00 0.00 0.00 17-O ct-18 08:00 PM 18-Oct- 18 06 :00 AM
SD-RB-C-240 Cutting of Pipeline 5h 0% 18-Oct-18 06:00 AM 18-Oct-18 11:00 AM 127 0.81 0.00 0.00 0.00 0.00 18-O ct-18 06:00 AM 18-Oct- 18 11 :00 AM
SD-RB-C-250 Beveling of Pipeline 5h 0% 18-Oct-18 06:00 AM 18-Oct-18 11:00 AM 127 0.81 0.00 0.00 0.00 0.00 18-O ct-18 06:00 AM 18-Oct- 18 11 :00 AM
SD-RB-C-260 Fit-up of Pipeline 6h 0% 18-Oct-18 11:00 AM 18-Oct-18 06:00 PM 253 1.61 0.00 0.00 0.00 0.00 18-O ct-18 11:00 AM 18-Oct- 18 06 :00 PM
SD-RB-C-271 Welding of Pipeline 6h 0% 18-Oct-18 06:00 PM 19-Oct-18 01:00 AM 506 3.23 0.00 0.00 0.00 0.00 18-O ct-18 06:00 PM 19-Oct- 18 01 :00 AM
SD-RB-C-280 NDT/RT of Pipeline 3h 0% 19-Oct-18 01:00 AM 19-Oct-18 04:00 AM 127 0.81 0.00 0.00 0.00 0.00 19-O ct-18 01:00 AM 19-Oct- 18 04 :00 AM
SD-RB-C-281 Inspection of Pipeline 1h 0% 19-Oct-18 04:00 AM 19-Oct-18 05:00 AM 25 0.16 0.00 0.00 0.00 0.00 19-O ct-18 04:00 AM 19-Oct- 18 05 :00 AM
SD-RB-C-290 Remaining Insulation 22h 0% 19-Oct-18 05:00 AM 20-Oct-18 05:00 AM 380 2.42 0.00 0.00 0.00 0.00 19-O ct-18 05:00 AM 20-Oct- 18 05 :00 AM
SD-RB-C-291 Final Inspection for Insulation 5h 0% 20-Oct-18 05:00 AM 20-Oct-18 10:00 AM 25 0.16 0.00 0.00 0.00 0.00 20-O ct-18 05:00 AM 20-Oct- 18 10 :00 AM
DEMOBILIZATION OF 500TN CRANE 48h 18-Oct-18 03:00 PM 20-Oct-18 07:00 PM 559 3.57 0.00 0.00 0.00 0.00 18-O ct-18 03:00 PM 20-Oct- 18 07 :00 PM
SD-CR-100 Demobilization of Heavy Cran es for Re-Boilers 48h 0% 18-Oct-18 03:00 PM 20-Oct-18 07:00 PM 559 3.57 0.00 0.00 0.00 0.00 18-O ct-18 03:00 PM 20-Oct- 18 07 :00 PM
WALKTHROUGH & PUNCHLISTING 158h 15-Oct-18 06:00 AM 22-Oct-18 10:00 AM 240 1.53 0.00 0.00 0.00 0.00 15-O ct-18 06:00 AM 22-Oct- 18 10 :00 AM

26E50A: WALKTHROUGH & PUNCHLISTING 44h 15-Oct-18 06:00 AM 17-Oct-18 06:00 AM 80 0.51 0.00 0.00 0.00 0.00 15-O ct-18 06:00 AM 17-Oct- 18 06 :00 AM
26E50A-WP-100 Walk-through, PSSR & Listing of "A" Punch items 11h 0% 15-Oct-18 06:00 AM 15-Oct-18 06:00 PM 50 0.32 0.00 0.00 0.00 0.00 15-O ct-18 06:00 AM 15-Oct- 18 06 :00 PM
26E50A-WP-110 Correction of Punch Items & Clearance 33h 0% 15-Oct-18 06:00 PM 17-Oct-18 06:00 AM 30 0.19 0.00 0.00 0.00 0.00 15-O ct-18 06:00 PM 17-Oct- 18 06 :00 AM
26E50B: WALKTHROUGH & PUNCHLISTING 44h 17-Oct-18 08:00 PM 19-Oct-18 08:00 PM 80 0.51 0.00 0.00 0.00 0.00 17-O ct-18 08:00 PM 19-Oct- 18 08 :00 PM
26E50B-WP-100 Walk-through, PSSR & Listing of "A" Punch items 11h 0% 17-Oct-18 08:00 PM 18-Oct-18 08:00 AM 50 0.32 0.00 0.00 0.00 0.00 17-O ct-18 08:00 PM 18-Oct- 18 08 :00 AM
26E50B-WP-110 Correction of Punch Items & Clearance 33h 0% 18-Oct-18 08:00 AM 19-Oct-18 08:00 PM 30 0.19 0.00 0.00 0.00 0.00 18-O ct-18 08:00 AM 19-Oct- 18 08 :00 PM
26E50C: WALKTHROUGH & PUNCHLISTING 44h 20-Oct-18 10:00 AM 22-Oct-18 10:00 AM 80 0.51 0.00 0.00 0.00 0.00 20-O ct-18 10:00 AM 22-Oct- 18 10 :00 AM
26E50C-WP-100 Walk-through, PSSR & Listing of "A" Punch items 11h 0% 20-Oct-18 10:00 AM 20-Oct-18 10:00 PM 50 0.32 0.00 0.00 0.00 0.00 20-O ct-18 10:00 AM 20-Oct- 18 10 :00 PM
26E50C-WP-110 Correction of Punch Items & Clearance 33h 0% 20-Oct-18 11:00 PM 22-Oct-18 10:00 AM 30 0.19 0.00 0.00 0.00 0.00 20-O ct-18 11:00 PM 22-Oct- 18 10 :00 AM

Primary Baseline Critical Remaining Work Summary Proposed Baseline Schedule- Rev.
REPLACEMENT OF REBOILER 26E50 A/B/C
Date Revision Checked Approved
Actual Work Baseline Milestone SAUDI PETROCHEMICAL COMPANY - SALT PLANT - SADAF
14-May-18 12... Proposed Baseline Schedule- Rev.00 SS SA
Remaining Work Milestone Page 2 of 2