Professional Documents
Culture Documents
net/publication/3928371
CITATIONS READS
39 424
2 authors:
Some of the authors of this publication are also working on these related projects:
European Research Infrastructure supporting Smart Grid Systems Technology Development, Validation and Roll Out (ERIGrid) View project
All content following this page was uploaded by Nikos D. Hatziargyriou on 31 May 2014.
reason, utility directives for the connection of DG adopt network) and DG power factor varying from 0.95 inductive to
simpler and more straightforward procedures. The evaluation 0.95 capacitive.
procedure of [6] is outlined in the following. It uses 10-min The above procedure is generally unsuitable for cases of
average voltage values. high DG penetration, multiple DG installations on the same
At a first stage, the maximum steady-state voltage change feeder or when generators are connected to long feeders
ε(%) at the PCC is evaluated and compared to the limit, using serving significant consumer load. In such cases, the resulting
the following relation voltage variations are caused by the aggregate effect of all
S 100 generating facilities and the existing (or planned) network
ε (%) ≅ 100 n cos (ψ k + φ ) = cos (ψ k + φ ) ≤ 3 % (1) loads. Therefore, load flow calculations are required, taking
Sk R
into account the actual network configuration and loads. Four
where Sn is the DG rated apparent power, Sk the network short basic load-generation combinations should be examined:
circuit capacity at the PCC, ψk the phase angle of the network A. Minimum load-Minimum generation
impedance and φ the phase angle of the DG output current. B. Minimum load-Maximum generation
R=Sk/Sn is the short circuit ratio at the PCC. C. Maximum load-Minimum generation
The 3% limit imposed (the German Guide [5] and other D. Maximum load- Maximum generation
European national regulations impose an even more stringent In typical rural overhead grids, case B yields the maximum
2% limit) is strict for two reasons. First, the grid voltage levels and case C the minimum voltage levels. The maximum and
are determined by the aggregate effect of all connected minimum voltages, Umax and Umin, of each node must be
consumers and generators and hence no single connection appropriately bounded. In [6] the following requirements are
could be allocated the full variation limit. Second, in order to set for the steady state voltage of all nodes:
achieve a ±10% variation limit at the LV level, the MV grid
voltage should be more narrowly bounded. The median voltage of each node should not deviate more
than ±5% from the nominal voltage, so that it can be
10.0 compensated by the fixed tap settings of the MV/LV
7.5
R=10 distribution transformers (-5% to +5%, in steps of 2.5%):
U + U max
5.0 R=20 0.95 ⋅ U n ≤ U med = min ≤ 1.05 ⋅ U n (2)
R=40 2
2.5
The variation of the voltage around its median value should
ε (%)
0.0
not exceed ±3% of the nominal voltage, so that the voltage
-2.5-180 -135 -90 -45 0 45 90 135 180
level at the LV network remains within the ±10% limit,
-5.0
after the median deviation has been corrected:
-7.5
2 ⋅ ∆U = U max − U min ≤ 0.06 ⋅ U n (3)
-10.0
ψ k +φ (deg)
It should be noted that each of the four load flow scenarios
has a certain probability of occurrence, which is difficult to
9 evaluate in real-world situations. Hence, common sense and
8 application of some engineering judgement are necessary, in
7 order to exclude improbable situations. Proper account must
PF=0.95 cap.
6 also be taken of the voltage regulating means of the network
5 (ULTCs of HV/MV transformers, line voltage regulators,
ε (%)
4
PF=1.0
switchable capacitors etc.), which normally operate on time
3 scales of 30 s-1 min and therefore affect the steady-state (10-
2 min average) voltage.
PF=0.95 ind.
1
0 III. RAPID VOLTAGE CHANGES - FLICKER
0 10 20 30 40 50
Short circuit ratio R
According to the EN 50160 definition, rapid changes of the
voltage are fast variations of its rms value between two
Fig. 1. Voltage change ε(%) as a function of angle ψk+φ, for three values of consecutive levels, which are sustained for a certain
the short circuit ratio R (top diagram) and ε(%) as a function of R, for
three power factor values of the DG (bottom diagram). (unspecified) duration. For consistency with the slow voltage
changes definition, it is assumed that the rapid changes are
Eq. (1) is accurate enough for most practical purposes (its much faster than the 10-min averaging interval.
error being less than 0.5% for R ≥15). Depending on the grid Rapid voltage changes are induced either by switching
angle ψk and the power factor angle φ of the installation, operations within the premises of the DG installation (usually
short-circuit ratios down to 15 or even lower may be start/stop operations of equipment), or by the variability of the
acceptable, as illustrated in the top diagram of Fig. 1. The output power during normal operation. The magnitude of the
effect of the DG power factor on the voltage variations is also change and the resulting flicker emissions should be limited,
important, as it is evident in the bottom diagram of Fig. 1, to avoid disturbing other nearby installations. Measures of the
drawn for ψk.≈55o (corresponding to ACSR-95 MV overhead
3
flicker emissions are the short term, Pst, and long term, Plt, are set, which are the overall disturbance limits allowed at the
flicker severity indices ([10-12]). planning stage (generally lower than the compatibility levels).
Regarding switching operations, the limits imposed depend Indicative values for the planning levels in MV systems,
on the voltage level (LV or MV) where the customer is according to IEC 61000-3-7, are:
connected, the size of the equipment and the frequency of the Pst ≤ 0.9 and Plt ≤ 0.7
operations. Taking into account the requirements of the The allocation of the above limits to individual producers is
relevant IEC documents, [12-16], the following limits are set made according to the principles presented in the next section
in [6] for the relative (%) voltage change: for harmonics (equations similar to (10) and (12) are applied)
TABLE I and takes account of the following:
RAPID VOLTAGE CHANGE MAGNITUDE LIMITS • Voltage flicker at the MV network is the combined result
Frequency of switching operations, r of emissions from loads connected at this voltage level and
(h-1: per hour, d-1: per day) flicker transferred from the HV grid.
r > 1 h-1 2 d-1 < r < 1 h-1 r < 2 d-1
• The flicker emissions from individual installations are
LV
TABLE 2
PLANNING LEVELS FOR LV, MV AND HV NETWORKS (IEC 61000-3-6, [24])
Odd harmonics ≠3k Odd harmonics = 3k Even harmonics
Order Harmonic voltage (%) Order Harmonic voltage (%) Order Harmonic voltage (%)
h LV MV HV h LV MV HV h LV MV HV
5 6 5 2 3 5 4 2 2 2 1.6 1.5
7 5 4 2 9 1.5 1.2 1 4 1 1 1
11 3.5 3 1.5 15 0.3 0.3 0.3 6 0.5 0.5 0.5
13 3 2.5 1.5 21 0.2 0.2 0.2 8 0.5 0.4 0.4
17 2 1.6 1 >21 0.2 0.2 0.2 10 0.5 0.4 0.4
19 1.5 1.2 1 12 0.2 0.2 0.2
23 1.5 1.2 0.7 >12 0.2 0.2 0.2
25 1.5 1.2 0.7
>25 0.2+ 0.2+ 0.2+
1.3⋅ 25 25 25
0.5⋅ 0.5⋅
h h h
THD: 8 % at LV, 6.5 % at MV, 3% at HV
Uh = a ∑U
i
a
hi or I h = a
∑I i
a
hi (11)
ZS
ΖΤ
Other feeders
DG
IEC 61000-3-6, [24], suggests: a=1 for h<5, a=1.4 for Aggregate
5≤h≤10 and a=2 for h>10, since harmonics of higher order Capacitance
tend to have random phase angles. Sk
From GhMV, the voltage distortion limit EUhi for an
individual installation can then be determined, in proportion to
Fig. 2. MV network equivalent for simplified harmonic emission evaluation.
its rated power, Sn,i:
S For systems without significant capacitance and no PFC
EUhi = GhMV a n ,i = GhMV a si (12)
St correction capacitors or filters in the DG installations:
where St is the total «feeding capacity» of the network (e.g. Zh ≈ h ⋅ X k (14)
equal to the rated MVA of the feeding transformer). The ratio where Xk is the fundamental frequency inductive component
si can also be interpreted as the ratio of the connected of the short circuit impedance at the PCC.
equipment rated power to the total capacity of the distorting The aggregate capacitance in Fig. 2 accounts for the single
equipment in the network. parallel resonance with the upstream system (but not for other
It is common practice in harmonic studies to regard the possible higher order resonances). If all resistances and
connected equipment as harmonic current sources (although system loads in Fig. 2 are ignored, the resonant frequency fr
this may not be correct in certain cases), whereas the limits and the respective harmonic order hr (not necessarily integer)
discussed previously refer to the harmonic distortion of the are given by
system voltage. In order to relate these quantities, the system S f S kS
harmonic impedance Zh at the PCC is needed. Then: f r = f1 kS ⇒ hr = r = (15)
Qc f1 Qc
5
where SkS is the short circuit capacity at the MV busbars of the of future DG penetration, such as tariffication policies,
HV/MV substation and Qc is the total capacitive reactive metering practices, pricing of power quality characteristics
power of the MV network. A rough and conservative etc.
estimation of Zh (usually providing results on the safe side) is
then given by the “envelope impedance curve” of IEC 61000- VI. REFERENCES
3-6, shown in Fig. 3. The resonant amplification factor, kr, of [1] R.B. Alderfer, M.M. Eldridge, T.J. Starrs, “Making Connections: Case
the system impedance at the PCC typically varies between 2 Studies of Interconnection Barriers and their Impact on Distributed
and 5 in public distribution networks ([24]), depending mainly Power Projects”. NREL Report SR-200-28053, July 2000.
on the damping effect of the system loads. [2] IEEE Std. P1547: Distributed Resources Interconnection with Electrical
Power Systems. (Under preparation by IEEE/SCC21).
Zh [3] IEEE Std. 929 (2000): Recommended Practice for Utility Interface of
Photovoltaic Systems.
[4] “Recommendation for the Connection and Parallel Operation of
Z hr Generating Facilities at the MV Network”, VDEW, 2nd Edition, 1998
kr =
Zhr hr ⋅ X kV (in German).
[5] “Recommendation for the Parallel Operation of Generating Facilities at
the LV Network of Electric Utilities”, VDEW, 3rd Edition 1991 –
Revised 1996 (in German).
[6] “Technical requirements for the interconnection of independent
hr⋅XkV
generation to the grid”. Public Power Corporation (PPC) of Greece,
2001.
Order h [7] European Norm EN 50160, “Voltage characteristics of electricity
supplied by public distribution systems”. CENELEC, 1999.
0 hr 1.5hr [8] N.Hatziargyriou, T.Karakatsanis, M.Papadopoulos, “Probabilistic load
flow in distribution systems containing dispersed wind power
Fig. 3. System harmonic impedance approximation, using the «envelope
generation”, IEEE Trans. Power Systems, Vol. 8, No. 1, February 1993.
impedance curve» (IEC 61000-3-6, [24]).
[9] N.G. Boulaxis, S.A. Papathanassiou, M.P. Papadopoulos, “Wind
turbine effect on the voltage profile of distribution networks”. To
For installations with filters or significant PFC capacitance, appear in Renewable Energy.
in more complex networks or when there are resonances in the [10] IEC 868-0 (1991), Part 0: Evaluation of flicker severity.
HV network, the approach presented above may not be [11] IEC 868 (1986): Flickermeter. Functional design and specifications.
Amendment No. 1 (1990).
suitable. Manual computation of Zh is possible in certain cases [12] IEC 61000-4-15 (1997), Part 4: Testing and measurement techniques –
(IEC 61000-3-6 provides relevant examples) but the Section 15: Flickermeter-Functional and design specifications.
application of harmonic load flow software is recommended, [13] IEC 61000-3-3 (1994), Part 3: Limits – Section 3: Limitation of voltage
since the harmonic distortion of the voltage may be maximum fluctuations and flicker in low-voltage supply systems for equipment
with rated current ≤ 16Α.
at points other than the equipment PCC. [14] IEC 61000-3-5 (1994), Part 3: Limits – Section 5: Limitation of voltage
fluctuations and flicker in low-voltage power supply systems for
equipment with rated current greater than 16 Α.
V. CONCLUSIONS [15] IEC 61000-3-11 (2000), Part 3: Limits – Section 11: Limitation of
voltage changes, voltage fluctuations and flicker in low voltage supply
In this paper a presentation of the technical requirements systems for equipment with rated current < 75 Α and subject to
for the connection of new distributed generation resources to conditional connection.
[16] IEC 61000-3-7 (1996), Part 3: Limits – Section 7: Assessment of
the distribution networks has been made, including assessment emission limits for fluctuating loads in MV and HV power systems –
methodologies suitable for practical applications. The criteria Basic EMC publication.
and procedures presented are part of the Greek utility guide, [17] IEC 61400-21 (CDV 2000): Measurement and assessment of power
[6], and are largely based on the set of relevant IEC quality characteristics of grid connected wind turbines.
[18] IEC 61000-1-1 (1992), Part 1: General – Section 1: Application and
publications. The requirements and evaluation procedures interpretation of fundamental definitions and terms.
introduced ensure that the connection of DG resources will [19] M.P. Papadopoulos, S.A. Papathanassiou, S.T. Tentzerakis, N.G.
not adversely affect the power quality and safety of operation Boulaxis, “Investigation of the Flicker Emission by Grid Connected
of the grid. Here the emphasis is placed on power (voltage) Wind Turbines”. Proc. of 8th IEEE Int. Conf. on Harmonics and Quality
of Power, Athens, 1998.
quality issues, including steady state and rapid voltage [20] S.A. Papathanassiou, S.J. Kiartzis, M.P. Papadopoulos, A.G. Kladas,
variations, flicker and harmonic emissions. “Wind turbine flicker calculation using neural networks”. To appear in
It is expected that technological advancements in the Wind Engineering.
following years will call for another (probably more radical) [21] ANSI/IEEE Std. 519 (1992): Recommended Practice and Requirements
for Harmonic Control in Electric Power Systems.
update of the evaluation methodologies. For instance, active [22] IEC 61000-3-2 (2000), Part 3: Limits – Section 2: Limits for harmonic
front end converters, with load balancing, flicker cancellation current emissions (equipment input current ≤ 16Α per phase).
and active filtering capabilities, will soon find their way in [23] IEC 61000-3-4 (1998), Part 3: Limits – Section 4: Limitation of
emission of harmonic currents in low -voltage power supply systems
commercial DG equipment. The grid operating principle will
for equipment with rated current greater than 16Α.
also evolve, permitting the exploitation of distributed [24] IEC 61000-3-6 (1996), Part 3: Limits – Section 6: Assessment of
generation resources for providing back-up power to parts of emission limits for distorting loads in MV and HV power systems.
the grid during power failures, increasing thus the service [25] IEC 61000-2-2 (1990), Part 2: Environment – Section 2: Compatibility
levels for low-frequency conducted disturbances and signalling in
reliability. Apart from the core technical issues, several other public supply systems.
market and regulatory factors will affect critically the degree
6
[26] IEC 725 (1981): Considerations on reference impedances for use in Nikos D. Hatziargyriou was born in Athens,
determining the disturbance characteristics of household appliances and Greece, in 1954. He received the Diploma in
similar electrical equipment. Electrical and Mechanical Engineering from
NTUA, Athens, Greece, in 1976 and M.Sc and
Ph.D. degrees from UMIST, Manchester, UK, in
VII. BIOGRAPHIES
1979 and 1982, respectively. He is currently
Stavros Papathanassiou (S’1993, M’1998) was born Professor at the Power Division of the Electrical
in Thesprotiko, Greece, in 1968. He received the and Computer Engineering Department of NTUA.
Diploma in Electrical Engineering from the National His research interests include Dispersed
Technical University of Athens (NTUA), Greece, in Generation and Renewable Energy sources,
1991 and the Ph.D. degree in 1997 from the same Dynamic Security and Artificial Intelligence techniques. He is member of
University. Currently, he is with the Distribution CIGRE SC38, member of the Technical Chamber of Greece, senior IEEE
Department of the Public Power Corporation of member and currently Chairman of the IEEE Greek Power Chapter.
Greece, engaged in power quality and dispersed
generation issues. His research mainly deals with
wind turbine modeling and control, electric machines
and drives and the integration of dispersed generation to the grid. He is a
member of the IEEE and a registered professional engineer and member of the
Technical Chamber of Greece.