Winding Copper
Field Winding Checks for poor connections and breaks. X X X X X
Res.
Field Inter-Turn
AC Impedance Turn shorts and speed sensitive turn shorts X X X X X
Insulation
OPTIONAL TESTS
Air Gap Flux Probe Field Inter-Turn Insulation Shorted turns at operating speed. X X X R R
Bore Pressure Test Chevron Seals Sealing capability of the Chevron seals. X X O O
Air – Air Cooled Generator HYD – Hydrogen Cooled Generator LCSW – Hydrogen Cooled Generator with Liquid Cooled
Winding
O - Optional Test X - Pertains only to type of unit R - These tests are performed while the unit is running.
selected
Note: Gas cooled bars use the hydrogen column. During high voltage testing the hollow conductors should be shorted to copper strand
© 2012 General Electric Company. All Rights Reserved. This material may not be copied or distributed in whole or in part, 7