Professional Documents
Culture Documents
Professional Practice - Carlo
Professional Practice - Carlo
“GISRIP”, “BBCC”
Methods of Compensation
1. Percentage of Construction
2. Multiple Direct Personnel Expense MDPE
Architect = NTRMf
Consultant = NTRMf
Staff = NTRMf
------------------------------
E = Direct Cost
E + MP + RE = Project Cost; where MP (Marginal Cost = 30%), RE
(Reimbursable Expense)
Project Cost + AE = Professional Fee: where AE = Architect & Engineer Fee
N–
T–
R–
Mf – Min. Fee = 2.0 – 2.5 as Multiplier
3. Lump Sum/ Fixed Fee
4. Per Diem Plus Reimbursable Expense
5. Combination
6. Professional Fee and Expenses
7. Turn Key
Reimbursable Expenses
Conditions:
Schedule of Payments
CONTRACTOR
1. Downpayment - 20 – 50% of Project Cost
2. Progressive Billing – base on percentage of completion (not more than 1 month)
3. Final Billing/Payment - 98% Complete
4. Guarantee Bond – enforced for 1 year
ARCHITECT
1. Proposal Fee – 5%
2. Schematic Design– 15%
3. Design Dev’t - 15%
4. Contract Docs - 50%
5. Retention - 15% = Liability 10%, Supervision 5%
*Under Contract Doc. Phase (Refer to UAP Doc 301 General Conditions of a Contract)
“GASSD”
“RERCF”
5 M’s of Construction
1. M-achines
2. M-oney
3. M-anpower
4. M-aterial
5. M-inutes
PROJECT CLASSIFICATION
UAP – degree of difficulty/complexity of design
FCP – risk of occurrence of Fire
NCP – use and occupancy
“SMERM” “RHEAC”
“PILAC”
“FC”
a. Billing of Tenants
b. Security and Janitorial Services (Monitoring)
c. Local Ordinances
Detailed Functions
a. Pre-Construction Phase
b. Construction Phase
Proj. Const. Cost. in addition to Architects fee for Regular Design Services (UAP 202)
10% (if residential proj.) + 7% = 17%
a. Lump Sum
b. If the cost is exceeded by not more than 10% it is divided = bet. Architect and
Client. However if the excess is more than 10% the Architect pays for all extra
cost of the 10%
1. Direct Selection
2. Indirect
a. Referral from satisfied client
b. Recommendation form another Architect
c. Comparative Selection
3. Design Competition
Illustration:
UAP Doc 301 General Conditions of a Contract
“TEMPACIL”*
a. Office – bedroom for Architect
b. Quarters – for staying workers
c. Warehouse – storage
d. Accessway – road ways, bridge, hoist (elevator)
e. Enclosure
f. Signage
g. Trial usage
*contractors expense
Section 5 – Protection
a. Property (work area)
b. Adjacent Property and Existing Utilities
c. Life, work, and Property during emergencies
Labor – characteristics/quality
No. /quality, no. of workers signed by YOU
Work – duration and deadlines; if delay P20,000 per day. Liquidated Damages =
0.01 of the Contract Sum “by the government”
Payments
Contractor
1. Progressive Billing – partial % of Completion
2. Request for inspection
Illustration:
PD – Presidential Decree
BP – Batas Pambansa
EO - Executive Order
LOI – Letter of Instruction
RA – Republic Act
Additional Terms:
1. According to RA9266 – all projects either big or small must have a contract.
LAWYER – NOTARY – REGISTER OF CONTRACT
2. Contractor – pays for the Building Permit (cannot be reimbursed, not included
in Estimates)
3. Architect cannot be a Contractor at the same time.
4. Contractor is profit motivated; Builder is completion motivated; Contractor
holds the money; Builder doesn’t hold the money. 15 days can a contractor,
atter giving due notice to the owner/architect suspend work or terminate a
contract. Responsible for the payment of insurance for personal injury and to
property; Responsible for the As-Built Plans of the Project
5. 2% per annum – Interest (if money is not fully collected)
6. TOR – Terms of Reference
7. Building Permit – validity 120 days, valid 12 months if constructed has not
commenced; exception government structure; excepted if P15,000 proj. cost
8. Notary – to legalize document with series no., document no., etc.
9. Arbitration – can file a case after 30 days
10. Specifications – are printed documents stipulating the procedural aspects of
the contract
11. Variance – is the minimum possible deviation from standards which is
permitted to make a highly beneficial housing project.
12. Project duration is computed immediately from the receipt date of the NTP
13. Design of any religious structures is assessed professional fees
14. Competitive bidding is mandatory for public work projects
15. 7 Days – affectivity of a Construction contract from receipt of Notice of Final
Payment
16. Civil Code – liability of Architect for Regular Design of structures – 15 years
17. PERT – Prog. Evaluation Review Technique
18. CPM – Critical Path Method