KARTINI REACTOR OPERATION
I. Purpose of Experiment
Participants could perform operation checklist including start up check list, power
check list and also shut down check list.
Participant could know the phenomena of nuclear research reactor operation.
II. Theory
Kartini reaktor is a TRIGA mark II type research reactor that has been operated since
1979 with maximum power of 100 kW. As a research reactor, Kartini reactor are used for
irradiation services/ neutron irradiation, gamma irradiation experiment, training and
education and also research on nuclear technology. For the purpose of services, Kartini
reactor has several irradiation facility such as Lazy Susan (LS) iradiation facility which can
contain 40 samples in a circular position outside the reactor core; Pneumatic transfer system
in F-13 ring; one thermal column and also 4 beamport. At 100kW power, the magnitude of
neutron flux in the LS irradiation facility is 2.5 x 1011 n / cm2 s in averages. In routine
circumtances, Kartini reactor is operated on average for 6 hours in a working day/ hour, but
may also operated for a longer period depend on request. Physical phenomenon that happen
inside reactor core during power operation is fission reaction between neutron and U235 fuel
in such a way that it produce (2 – 3 ) new neutrons, accompanied by an average energy (heat)
180 MeV and also a simultaneous radiation of ((alpha), (beta), (gamma).
Some of the fission reaction processes that occur inside the reactor core can be shown
as follows:
0n
1
+ 92U235 92U
236* 38Sr94 + 54Xe140 + 2 0n1
235 36Kr94 + 56Ba139 + 3 0n1
1
0n + 92U 92U
236*
0n
1
+ 2 H2O 2 H2O + O2 (gas)
16
1
0n + 8O 7N
16
+ 1p1 + n
The TRIGA reactor coolant use a pure water (H2O) with pH ranging between 5,5 – 7
that have function such as a moderator (slowing down) neutron, a shielding of radiation
exposure so that it does not scatter freely in air surface and also to compensate (capture) the
energy/ heat which will be discharged through the circulation of heat exchanger system (HE)
so that the water temperature of reactor tank (ATR) remains low, not exceeding the allowable
limit of 40 oC.
For safe operation of reactor, all systems including measuring device of reactor
parameter and also auxiliary system must be equipped with procedure documents and
operational guidelines as well as regular schedules of calibration and maintenance.
2
Dokumen Bidang Reaktor
PSTA – BATAN, April 2018.
III. Kartini Reactor Operational Procedure
Before reactor is operated at certain power level, 2 operators lead by a supervisor fill
checklist for reactor instrumentation & control and also every parameter of auxiliary system
to make sure all system is works fine.
There are 3 types of reactor operation checlist, those are start up checklist, power
operation checklist, and shutdown checklist.
START UP CHECKLIST
Operator : 2 persons.
Supervisor : 1 person.
Radiation Safety Officer : 1 person
A. Auxiliary system C. Interlock:
- Primary flow : liter/minute Interlock from control rod:.....
- Secondary flow : liter/minute D. Calibration
- Primary Temperature (HE) : LCR :
o
- In HE : C Campbell :
o
- Out HE : C Period :
- Primary cooler resistance : Linear Power :
- Demin In : E. Scram test
- Demin Out : Safety Compensating Regulating
- pH ATR : Manual :
- Secondary flow : GPM % Power :
- Blower : ( ) Period :
B. Reaktor HV :
* Reaktor core : F. Conclusion
* Neutron source :
G. Singnature :
* Beamport :
* Beamport : Supervisor
Information:
: Good ( )
X : Not good
3
Dokumen Bidang Reaktor
PSTA – BATAN, April 2018.
POWER OPERATION CHECKLIST
Power operation checklist is done while reactor is operating at certain power level. Usually
power operation checklist is done every 1 hour while reactor is operating. This procedure
have to perform to find out every events occured during operation, therefore if any anomaly
happened it will be detected as soon as possible and safety handling operations can be
performed.
1. Time :
2. Power :
3. Control Rod Position :
Safety Rod Compensating Rod Regulating Rod
% % %
4
Dokumen Bidang Reaktor
PSTA – BATAN, April 2018.
SHUTDOWN CHECKLIST
1. Shutdown Time :
2. Power :
3. Control Rod Position :
Safety Rod Compensating Rod Regulating Rod
% % %
Supervisor Explanation
Signature,
( )
5
Dokumen Bidang Reaktor
PSTA – BATAN, April 2018.
TECHNICAL SPECIFICATION OF KARTINI REACTOR
40oC
6
Dokumen Bidang Reaktor
PSTA – BATAN, April 2018.
SCHEDULE OF CALIBRATION AND MAINTENANCE OF KARTINI REACTOR
SYSTEM
COMPONENT TIME
1. Environmental air monitor 1 x each month
7
Dokumen Bidang Reaktor
PSTA – BATAN, April 2018.
Reference
3. Kartini Reactor Safety Analysis, Gamma Atomic Power Research Center Yogyakarta,
National Atomic Energy Agency.
8
Dokumen Bidang Reaktor
PSTA – BATAN, April 2018.