Revit Structure 2018 Intermediate and Advanced

Creating Material Takeoff Schedule

Exercise 14-3
1. Start Revit 2018

2. Open the file Exercise 14-3.rvt

3. Create a Material Takeoff Schedule. Select Category = Floors, leave the name
without changing

4. Add the following fields: Level, Material:Name, Material:Area, Material:Volume,


Material:Cost

5. Go to Filter tab, and set the Material:Name = Concrete, Cast In Situ

6. Click OK, to display the schedule. You noticed that Material:Cost = zero

7. Go to Manage tab, locate Settings panel, click Materials button, search for
Concrete, Cast In Situ material, go to Identity tab, and set the price to 100

8. From Properties, click Fields tab, click Add calculated parameter button, type
in “Total Cost” as the name. Discipline = Common, Type = Currency. Type the
following formula: (Material:Volume/1) * Material:Cost

9. Click OK, twice, to display the schedule

10. To set the right format for Total Cost column, go to Properties, click Formatting
button. From left select Total Cost, click Field Format button, click off the Use
project settings checkbox. Set Rounding= 2 decimal places, Unit symbol = $,
and Use digit grouping = on, click OK

11. Click Conditional Formatting button, and set Total Cost < 10000, set the
background color to be Cyan. Click OK

12. Select Calculate Totals from the list

13. Go to Sorting/Grouping tab, switch on Grand Totals, and set it Totals only.
Click OK to display the schedule

14. From Properties, click Fields, click Add calculated parameters button, name it
“Volume Percentage”, it is Percentage of Material : Volume, By Grand total

15. Move it up to be at the right of Material:Volume, and format it to look like:


17.08%

16. Save and close the file

14-24