1. Start Revit 2018
3. Create a Material Takeoff Schedule. Select Category = Floors, leave the name
without changing
6. Click OK, to display the schedule. You noticed that Material:Cost = zero
7. Go to Manage tab, locate Settings panel, click Materials button, search for
Concrete, Cast In Situ material, go to Identity tab, and set the price to 100
8. From Properties, click Fields tab, click Add calculated parameter button, type
in “Total Cost” as the name. Discipline = Common, Type = Currency. Type the
following formula: (Material:Volume/1) * Material:Cost
10. To set the right format for Total Cost column, go to Properties, click Formatting
button. From left select Total Cost, click Field Format button, click off the Use
project settings checkbox. Set Rounding= 2 decimal places, Unit symbol = $,
and Use digit grouping = on, click OK
11. Click Conditional Formatting button, and set Total Cost < 10000, set the
background color to be Cyan. Click OK
13. Go to Sorting/Grouping tab, switch on Grand Totals, and set it Totals only.
Click OK to display the schedule
14. From Properties, click Fields, click Add calculated parameters button, name it
“Volume Percentage”, it is Percentage of Material : Volume, By Grand total