You are on page 1of 1

CLAUSE 5. FABRICATION AWS D1.1/D1.

1M:2015

5.25.1.1 Overlap, Excessive Convexity, or Excessive soundness shall be verified by appropriate NDT, when
Reinforcement. Excessive weld metal shall be removed. such tests are specified in the contract documents for
groove welds subject to compression or tension stress.
5.25.1.2 Excessive Concavity of Weld or Crater,
Undersize Welds, Undercutting. The surfaces shall be (2) Base metal subject to cyclic tensile stress may be
prepared (see 5.29) and additional weld metal deposited. restored by welding provided:
5.25.1.3 Incomplete Fusion, Excessive Weld Poros- (a) The Engineer approves repair by welding and
ity, or Slag Inclusions. Unacceptable portions shall be the repair WPS.
removed (see 5.25) and rewelded. (b) The repair WPS is followed in the work and
5.25.1.4 Cracks in Weld or Base Metal. The extent the soundness of the restored base metal is verified by
of the crack shall be ascertained by use of acid etching, the NDT method(s) specified in the contract documents
MT, PT, or other equally positive means; the crack and for examination of tension groove welds or as approved
sound metal 2 in [50 mm] beyond each end of the crack by the Engineer.
shall be removed, and rewelded. (3) In addition to the requirements of (1) and (2),
5.25.2 Localized Heat Repair Temperature Limita- when holes in quenched and tempered base metals are
tions. Members distorted by welding shall be straight- restored by welding:
ened by mechanical means or by application of a limited (a) Appropriate filler metal, heat input, and
amount of localized heat. The temperature of heated PWHT (when PWHT is required) shall be used.
areas as measured by approved methods shall not exceed
1100°F [600°C] for quenched and tempered steel nor (b) Sample welds shall be made using the repair
1200°F [650°C] for other steels. The part to be heated for WPS.
straightening shall be substantially free of stress and (c) RT of the sample welds shall verify that weld
from external forces, except those stresses resulting from soundness conforms to the requirements of 6.12.2.1.
a mechanical straightening method used in conjunction
with the application of heat. (d) One reduced section tension test (weld metal);
two side bend tests (weld metal); and three CVN tests of
5.25.3 Engineer’s Approval. Prior approval of the En- the HAZ (coarse grained area) removed from sample
gineer shall be obtained for repairs to base metal (other welds shall be used to demonstrate that the mechanical
than those required by 5.14), repair of major or delayed properties of the repaired area conform to the specified
cracks, repairs to ESW and EGW with internal defects, requirements of the base metal (see Clause 4, Part D for
or for a revised design to compensate for deficiencies. CVN testing requirements).
The Engineer shall be notified before welded members
are cut apart. (4) Weld surfaces shall be finished as specified in
5.23.3.1.
5.25.4 Inaccessibility of Unacceptable Welds. If, after
an unacceptable weld has been made, work is performed
which has rendered that weld inaccessible or has created 5.26 Peening
new conditions that make correction of the unacceptable
weld dangerous or ineffectual, then the original con- Peening may be used on intermediate weld layers for
ditions shall be restored by removing welds or members, control of shrinkage stresses in thick welds to prevent
or both, before the corrections are made. If this is not cracking or distortion, or both. No peening shall be done
done, the deficiency shall be compensated for by addi- on the root or surface layer of the weld or the base metal
tional work performed conforming to an approved revised at the edges of the weld except as provided in 9.2.7.6(3)
design. for tubulars. Care should be taken to prevent overlapping
or cracking of the weld or base metal.
5.25.5 Welded Restoration of Base Metal with Mis-
located Holes. Except where restoration by welding is 5.26.1 Tools. The use of manual slag hammers, chisels,
necessary for structural or other reasons, punched or and lightweight vibrating tools for the removal of slag and
drilled mislocated holes may be left open or filled with spatter is allowed and shall not be considered peening.
bolts. When base metal with mislocated holes is restored
by welding, the following requirements apply:
(1) Base metal not subjected to cyclic tensile stress
5.27 Caulking
may be restored by welding, provided the Contractor Caulking shall be defined as plastic deformation of weld
prepares and follows a repair WPS. The repair weld and base metal surfaces by mechanical means to seal or

178

You might also like