WORK BREAKDOWN STRUCTURE

PROJECT TITLE Project Tapti decommissioning DATE 26 January 2021

PROJECT ID: REV 1.00

PREPARED BY

SR NO ITERATION 1 ITERATION 2 ITERATION 3 ITERATION 4

Pre-execution
1 Licences and Clearances
1.1 MPCB
1.2 CRZ
1.3 Custons
2 Pre-Dismantling Engineering
2.1 Grillage and transport engineering
Topsides
Onshore Grillage Design and Transportation Analysis
Grillage General Arrangement Drawing
Storage arrangment Drawing
Grillage MTO
Grillage Fabrication Drawing
Jackets
Grillage General Arrangement Drawing
Onshore Grillage Design and Transportation Analysis
Storage Arrangment Drawing
Grillage MTO
Grillage Fabrication Drawing
2.2 Dismantling engineering
Pilot assignment
Subcontractor finalization
First submission
Document approval
Balance dismanatling engineering
First submission
Document approval
3 Pre-dismantling documentation
3.3 Onshore Transportation Procedures
Topside
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
Jackets
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
3.4 Dismantling Engineering Reports
Topside
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
Jackets
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
3.5 stability analysis during dismantling
Topside
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
Jackets
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
3.6 Dismantling weight reports
Topside
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
Jackets
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
3.8 Dismantling Procedures
Topside
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
Jackets
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
Bridge
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
3.9 grillage design and analysis
Topside
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
Jackets
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
3.10 ITP Dismantling and Disposal Phase
Bridge
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
dismantling and disposal phase
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
3.11 Risk assessment
Bridge dismantling
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
Dismantling and disposal
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
3.12 Other general documentation
Project Execution Plan Dismantling & Disposal Phase
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
Familiarization of Working Personnel (on-going)
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
Environmental Plan Dismantling and Disposal Phase
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
Project Control Plan
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
Project Schedule
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
S-Curve overall project & S-Curve Engineering
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
Document approved
Organization chart (updated version)
First submission
Document approval process
Gap Closure Plan Lavgan Disposal Yard (on-going)
First submission
Document approval process
HSSE & SP Plan Dismantling and Disposal Phase
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
Onshore weighing procedure
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
hazardous & other waste handling Procedure
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
Emergency response plan
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
Management of Change Register
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
Document Approved
Sub Bottom Profile
First submission
NDT Procedures CCPL-LSY
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
Document Approved

4 EIA study
4.1 Finalization of subcontractor
4.2 Assessment
4.3 Reports
First submission
Document approval process
DRS
DRS response
Receipt of Approved DRS
2nd submission
CRS
CRS response
Receipt of approved CRS
3rd Submission
Document Approved
5 Pre-Dismantling Fabrication
5.1 Grillages for topside
STA
STB
STC
STD
MTA
5.2 Grillages for Jackets
STA
STB
STC
STD
MTA
6 Disposal vendor finalization
6.1 Shortlisting
6.2 document collection
6.3 submission to BOC
6.4 Response
6.5 2nd submission
6.6 Approval
7 Land development for Jacket dismantling
7.1 Finalization of subcontractor
7.2 execution
8 Dredging
8.1 subcontractor finalization
8.2 Dredging

Execution
9 Bokalift arrival (Trip-1)
9.1 Offloading of Structures(Trip 1)-Topsides
9.1.1 STA
9.1.2 STB
9.1.3 STC
9.1.4 STD
9.1.5 MTA
9.2 Transfer of structures(Trip 1)
9.2.1 STA
9.2.2 STB
9.2.3 STC
9.2.4 STD
9.2.5 MTA
10 Bokalift arrival (Trip-2)-Jackets
10.1 Offloading of Structures(Trip 2)-Jackets
10.1.1 STA
10.1.2 STB
10.1.3 STC
10.1.4 STD
10.1.5 MTA
10.2 Transfer of structures(Trip 2)
10.2.1 STA
10.2.2 STB
10.2.3 STC
10.2.4 STD
10.2.5 MTA
10.3 Dismantlement(Phase-1)
10.3.1 STA
10.3.2 STB
10.3.3 STC
10.3.4 STD
10.3.5 MTA
10.4 Dismantlement(Phase-2)
10.4.1 STA
10.4.2 STB
10.4.3 STC
10.4.4 STD
10.4.5 MTA
11 Seggregation of waste
12 disposal of waste