Professional Documents
Culture Documents
er
1 Week ak
M
TS
W
B 2-3 Weeks
of
n
c tio
e le
r S
Fo
Initiation of
the project Maker of BWTS has
been selected
Feasibility Study
Duration 2-3 Weeks
1 Week
Maker 1 Maker 2
Phase 1: Basic Engineering Phase 2: Verification of Installation Area Phase 3: Detailed Engineering Phase 4: Approval Package &
Retrofit Specification*
Isometric Drawings
Preparation of Post Processing Point Cloud 3D Modelling of Selected
On-board inspection Areas - Equipment Cable Spec
3D Virtual Installation
Preliminary Pressure of WBTP MTO
Losses Calculations Preparation of 3D piping
Diagram – Isometric Drawings Supports Drawings
RETROFIT STUDY
LIABILITY
• Engine Room Arrangement • PID of Ballast System E/R and Hull Part
• Steering Gear Arrangement • PID of Bilge System
• General Arrangement • PID of Compressed Air, Fresh/Sea Water System
• Pump Room Arrangement • Available Piping Arrangement Drawings
• Engine Casing Arrangement
• Available Plot Plans
2x1000m3/h WBP
Filter
TRO-N Unit
Filter
• Laser beam is deflected by mirrors to scan the surrounding area and objects
• Immediate production of a cloud of measured points (point cloud) with additional
color information for each point (x,y,z,i) or (x,y,z,r,g,b)
• Several scanning positions which need registration
• Post processing of produced point clouds, combining on single file
• Minimize time on board for inspection
Registration
Alignment and Position of scan from each scanning position to the correct location.
Keep in mind that in enclose spaces GPS is turned off which could have been used for reference.
Scan no.1 on E/R Lower Floor Scan No.2 on E/R Lower Floor
3D Laser Scanning – Verification of Installation Area
automation system
82K DWT Bulk Carrier Engine Room and Steering Gear Room (Point Cloud)
3D Laser Scanning – Verification of Installation Area
automation system
Option 1
Focus3D
Use of Explosion Proof Laser Scanner for explosion
environment such as pump room, Upper Deck where part of
WBTP equipment may be installed
Option 2
Imager 5006EX
Use of conventional Laser Scanner
EX-plosion Environment
Focus3D Problems
Imager 5006EX
1. Limited availability worldwide for leasing
2. Heavy equipment
Scanner 30kg
1 2 3 4
Hint: Always request together the point cloud deliverable and the
report of the post processing software at the end of the
Accuracy of the measurement
3 registration. Whatever is less than 2/3mm in 3-axis and more than
Depends on the registration and on the operator of the viewer
0.1o-0.5o angle is unacceptable
3D Laser Scanning – Verification of Installation Area
Preparations Precautions
1 1. Area(s) to be clean and tidy 2 1. No crew to be present in the off limit area(s) during scanning
2. No loose equipment to be in way of area(s) to be scanned 2. Instructions by the scanner operators and sup. Engineer(s) or
3. No work or repairs or survey to be performed in the area(s) to be officer in charge shall be strictly followed
scanned 3. Off limit areas(s) will be marked accordingly, markings to be
4. Engine room and pump room floor covers/grating to be removed respected, not violated and not removed
by the crew, according to the scanner operator’s instructions 4. Direct eye contact to the scanner lens to be avoided due to danger
5. Pump room ventilation to be in operation at max power during 3D of the eye sight
scanning 5. Contact/removal/change of location of the reference spheres or
6. Personal gas meter to be provided to scanner operators (two for checkered tables is strictly prohibited
operators and one for the scanner) 6. Works inducing vibrations in the vicinity of the scanner location
7. Gas meter to be installed in several locations in pump room and not to be performed
upper/s deck during 3d scanning 7. Scanner and its supports not to be touched by any unauthorized
8. Cargo lines inside pump room to be stripped personnel
9. Pump room bilges to be clean 8. Sup. Engineer(s) or Officer in charge to order immediate stop of
10. Gas sampling unit to be in operation. System interval to be set to the 3D scanning in case of gas sampling unit alarm (high gas
minimum rate. concentration)
3D Laser Scanning – Verification of Installation Area
Deliverable(s)
Point Cloud
+ 3D Model by the
Maker
+ Piping Routing by
Retrofit Engineer = Assessment of
Equipment Installation
and Pipe Routing
,
Proposal of Different
Scenarios of
Installation and Pipe
Routing
Scenario A Scenario B
Point Cloud
+ 3D Model by the
Maker
+ Piping Routing by
Retrofit Engineer = Assessment of
Equipment Installation
and Pipe Routing
,
Proposal of Different
Scenarios of
Installation and Pipe
Routing
Scenario A Scenario B
Routing Scenarios of the Main Pipes
3D Laser Scanning – Feasibility of BWTS Installation
Point Cloud
+ 3D Model by the
Maker
+ Piping Routing by
Retrofit Engineer = Assessment of
Equipment Installation
and Pipe Routing
,
Proposal of Different
Scenarios of
Installation and Pipe
Routing
Scenario A Scenario B
Maintenance Space Consideration
3D Laser Scanning – Feasibility of BWTS Installation
1 2 3 4
Class
Drawings Calculations 3D Modeling
Revision
Phase 3 – Detailed Engineering
• APT ballasting
Phase 3 – Detailed Engineering
2 Calculations 1
Tricky Part
Final Calculations
• Short Circuit calculations
• Final Calculation of Pressure losses and new flow rates of Ballast (not available drawing to the class, not complete defined variables during the
Piping System calculations, needs software for the calculation with certification of IEC61363
• Final Calculation of Pressure losses and new flow rates of Cooling or • Actual Operation profile of D/Gs
Heating System
• Calculation of MSB Bus Bar and Branches if required
• Final Calculation of Power Consumption
• Amendment of Electric Power Balance • Actual needs of vessel operation
• New Electric Operation Profile to be defined • Flow rate of auxiliary equipment (i.e. cooler, heater)
• New Ballasting/De-Ballasting rates/time to be defined
• Equipment Supports Structural Strength calculations (*if required)
Phase 3 – Detailed Engineering
2 Calculations 1
• Purpose of 3D Design
• Arrangement Assessment
• Prefabrication of foundation and main
pipes
• Complete prefabrication
• Prefabrication and pre-installation by the
crew and technicians prior DD
• Quotation by Shipyard for the retrofit
• Purpose of 3D Design
• Arrangement Assessment
• Prefabrication of foundation and main
pipes
• Complete prefabrication
• Prefabrication and pre-installation by the
crew and technicians prior DD
• Quotation by Shipyard for the retrofit
• Spool Pieces
3 Technical Specification and drawings 1 • Final adjustment on board (field weld for flanges, extra length)
• Pipe fitting compatible with selected shipyard and Maker
3 Material Lists 1
Cabling MTO
Steel Beam MTO
Pipe MTO
Phase 3 – Detailed Engineering
3 Material Lists 1
3 Material Lists 1
Pipe MTO
Phase 3 – Detailed Engineering
3 Material Lists 1
Cabling MTO
Retrofits of SOx Scrubbers Source: Clarkson
Maker 9
6%
Maker 3
9%
Maker 8
10% Maker 4
5%
Maker 6 Maker 5
Maker 7 3%
4%
3%
New Orders with SOx Scrubber Source: Clarkson
Maker 6
3%
Maker 5
49%
Prediction for Global Marine Use
Source: BP
Source: Shell
1 Week
Requirements to be integrated
1 Week
1 Week
Keep in mind
1Ø Shipping
Week Company should define the design Exhaust Gas flow (kg/hr), Exhaust Gas inlet temperature, SW
alkalinity and temperature.
Ø Maximum design temperature to be defined and cover with sufficient margin the actual most demanding
case (i.e. G/Es at low loads during Tropical Conditions)
Ø Clearly indicate compliance with vessel’s Class Rules. It is highly recommended to assess Vendor’s offered
scope of supply with Class Rules prior to confirming order. In case of non compliance in an aspect, operation
restrictions could be required and/or additional equipment/cost.
Ø In case of Dry Running, the unrestricted duration of dry running and the maximum allowable exhaust gas
temperature should be defined.
Ø Auxiliaries’ Specification (e.g. Dampers, valves, pumps) to be assessed
Ø Guarantee terms should be assessed. Guarantee based on running hours to be requested.
Ø In case of Boiler(s) connection, special consideration together with Boiler’s Maker should be given in respect
to the back pressure. In-line forced fan shall be required in case of retrofitting projects.
Ø In case of Auxiliary Boiler(s) connection, special consideration should be given in respect to the IGS
operation.
Keep in mind
Arrangement Aspects
Calculations
1Ø Exhaust
Week gas piping back pressure Calculations. The challenge is on the modelling of exhaust gas
mixing.
Ø Exhaust Gas Piping Thermal Deflection Calculations
Ø Exhaust Gas Piping stress calculations iwo tricky arrangements
Ø Tower’s Foundation and Bracing strength calculations. Dynamic loads should be considered
Ø Short Circuit Calculations
Ø Assessment of the S/C and Main Sea Cross Line size
Ø CFD Analysis of the SW washing overboard discharge
Ø Assessment of the installed Fixed Fire Fighting Capacity
Ø Electric Load Analysis
Ø Stability assessment
Ø Equipment Number assessment
Keep in mind
Class Aspects
1 Week
Ø In case of In-Line scrubber the necessity of the exhaust gas by-pass
Ø Redundancy Issues (e.g. 1x100% SW Washing pump or 2x100% SW Washing pumps)
Ø Approval of Vendors Drawings
Ø Safety issues in respect to M/E, G/Es & Boilers Operation
Ø Inducing operation restrictions by the Class should be avoided
Ø E/R Unmanned Operation (i.e. interface with AMS)
Ø Safety Devices and Alarm Devices
Ø Class should define the Rules’ Edition that is applicable for the SOx Scrubber
Retrofitting.
Keep in mind
On Board Testing
1 Week
Ø Makers, Class, Shipyard & Shipping company are involved. Tests’
Scheme should be prepared and mutually agreed well in advance
Ø M/E, G/Es & Boilers’ transient operation profiles should be checked
Ø Tests with the vessel chartered may be required.
Ø HFO with 3.5% sulphur should be available
Ø Exhaust gas back pressure measurements should be carried out in line
with M/E Makers Guidelines
Ø SW water temperature and alkalinity to be close to the design values
Keep in mind
Technical
Department should
About 6 Affects the be pro-active. At
Top months for Limited Time operation of least detailed
Demanding
Management Innovative Several Parties having a for the M/E, G/Es and feasibility study
Engineering
Decision Involved concluded installation Boiler(s) should be carried
design operation out and conclusion
on a Maker, if
practicable