DR No.

: DR-HIBA-AICI-025
Client: USACE DAILY PROGRESS REPORT
Rev No: Rev 0
UD 2.4 Package # 2 Aprons, MSAB Day : Monday
Contractor: AICI
Contract No: W912ER20C0009 Date: 23/11/2020

Sub -Contractor: HiBA

Weather Conditions: Partly sunny Temperature: Min : 14 - Max : 24


PROFESSIONAL STAFF
P: Present A: Absent N.A.: Not Available
Profession Name Attendance Profession No. Comments
Project Manager Ramzi haddad P Worker 15
Construction Manager Mashour Bashtawi P Office Boy
Technical Manager Lab Technician
Office Eng.
Office Eng.
Office Eng.
Office Eng.
Surveyor Odai Al olabi P
QC Engineer Sleman abu hassan P
QC Engineer George issam P
Electrical Foreman jawad al salhout P
Mechanical Foreman Issa barhomeh P
General Foreman Mustafa al killani P
Store Keeper Mohammad shatara P
Acountent Mohammad alkhaldi P
Admin Assistant
Safety Manager Hani Al khateb
Foreman Amer al saied P
PLANT & MACHINERY
Working status Working status
TYPE NO TYPE NO
Active Idle Active Idle
Pick-Up 2 Active
Backhoe Loader 0
Car 3 Active
Bus 3 Active
Loader 1 Active
Trailers 2 Active
Water Truck 0
Trucks 1 Active
Boom Truck 1 Active
Dumper 1 Active
Grader 0
Bulldozer 0
Roller 35 Ton 0
Roller 0.8 m Drum; 1 Ton 0
Forklift 1 idle
Excavator 2 Active
Diesel tank 0
Construction activity
No Location Activity Description QTY Cum.QTY Comments
1 Maintain housekeeping
Storage yard
2 Storage preparation
3 TMO buildings prepaparation for test
3 part 9 /Pressure line-SL Trench preparation 100 100
5 Part 4/MH11 TO MH12-MV Compaction the ground 123 mtr 422 mtr
6 Part 4/MH12 TO MH13-MV Compaction test 146 mtr 422 mtr
7 Stockpile area preparation storage for ductile iron pipe
Note: The Staff arrived to the main gate at 6:45 but entered the site at 7:40
Incoiming Material
No: Description Unit QTY Usage Remarks
1 Elbow 3" SH 40 Piece 7 Presure line
2 Elbow 4" SH 40 Piece 12 Presure line
3
4

Testing
No: Description Locatiom Remarks
1 Natural ground compaction test MH12-MH13/MV Failed

Q.C REQUIRMENTS / NARRATIVES


No. Description

GENERAL NOTES
1-the main contractor still stoping our work in all excavation

2-The main contractor take sample from MH8-MH9 to test it in the lab to determine soil classification.

Site Eng. AICI Q.C Eng.