RATE ANALYSIS
PCC (1:2:4) (Manual):-
Wet PCC = 10
Factor = 1.54
Dry PCC = 15.4
Material:-
Cement = 1x15.4/(7x.035)
= 62.857 bags
Sand = 4.4
Crush = 8.8
Labour:-
Mason = 0.1 day/
= 1 day
Waterman = 2.13 day/
=21.3 days
Labour = 0.7day/
= .7x(10+15.4)/2
= 8.89 days
Machinery:-
Viberator = 1 hour for 10
= 0.125 days
www.onlinecivil.tk
Civil Engineering Practice
Wet PCC = 10
Factor = 1.54
Dry PCC = 15.4
Material:-
Cement = 1x15.4/ (10x.035)
= 44 bags
Sand = 4.62
Crush = 9.24
Labour:-
Mason = 0.1 day/
= 1 day
Waterman = 2.13 day/
=21.3 days
Labour = 0.7day/
= .7x(10+15.4)/2
= 8.89 days
www.onlinecivil.tk
Civil Engineering Practice
Wet PCC = 10
Factor = 1.54
Dry PCC = 15.4
Material:-
Cement = 1x15.4/(13x.035)
= 33.85 bags
Sand = 4.74
Crush = 9.48
Labour:-
Mason = 0.1 day/
= 1 day
Waterman = 2.13 day/
=21.3 days
Labour = 0.7day/
= .7x(10+15.4)/2
= 8.89 days
www.onlinecivil.tk
Civil Engineering Practice
Wet PCC = 10
Factor = 1.54
Dry PCC = 15.4
Material:-
Cement = 1x15.4/(7x.035)
= 62.857 bags
Sand = 4.4
Crush = 8.8
Labour:-
Mason = 0.1 day/
= 1 day
Waterman = 2.13 day/
=21.3 days
Labour = 0.3day/
= 3 days
Machinery:-
Viberator = 1 hour for 10
= 0.125 days
Concrete Mixer + Lift Arrangement = 0.45days
www.onlinecivil.tk
Civil Engineering Practice
RCC (1:2:4) (Mechanical):-
Wet RCC = 10
Factor = 1.50
Dry PCC = 15.0
Material:-
Cement = 62.857 bags
Sand = 4.4
Crush = 8.8
Steel = 1% volume of concrete
= 10/100x1x7850
= 785 kg
Labour:-
Mason = 0.1 day/
Waterman = 2.13 day/
Labour = 0.3day/
Steel Cutter = 250 kg/day
Steel fixer = 1000kg/day
Machinery:-
Viberator = 1 hour for 10
= 0.125 days
Concrete Mixer + Lift Arrangement = 0.45days
www.onlinecivil.tk
Civil Engineering Practice
Wet RCC = 10
Factor = 1.50
Dry PCC = 15.0
Material:-
Cement = 77.92 bags
Sand = 4.09
Crush = 8.18
Steel = 2% volume of concrete
= 10/100x2x7850
= 1570 kg
Labour:-
Mason = 0.1 day/
Waterman = 2.13 day/
Labour = 0.3day/
Steel Cutter = 250 kg/day
Steel fixer = 1000kg/day
Machinery:-
Viberator = 1 hour for 10
Concrete Mixer + Lift Arrangement = 0.45days
www.onlinecivil.tk
Civil Engineering Practice
SHUTTERING (Steel):-
SHUTTERING (Wood):-
www.onlinecivil.tk